November 11, 2026
Development Pro Forma for Ontario Sites, with a Worked Example
A development pro forma is a one-page model of a project that answers one question: at today’s costs, rents or prices and government charges, does this building make money, and how much can you pay for the land? It starts with what the finished building is worth, takes off the hard costs, the soft costs, the municipal charges, the financing and the profit you need for the risk, and whatever is left is what the land can carry. That last number is the residual land value. If it’s higher than the asking price, the site may work. If it’s lower, the price, the design or the plan has to change before you commit.
This guide walks through each line of a development pro forma with the Ontario numbers that go into it, builds a residual land value from labelled assumptions with the arithmetic shown, and shows which lines move the answer most. Every rate below was checked against its source between October 7 and November 10, 2026; check each one again on the day you run your own numbers.
What a development pro forma is
A pro forma is a forecast, built before anything is spent, of every dollar into and out of a project. Developers use it to decide whether to buy a site, lenders use it to decide whether to fund the project, and appraisers use the same logic to value development land. On a real estate development pro forma the structure is always the same:
Value of the finished project − hard costs − soft costs − financing − profit = residual land value
It differs from a construction budget in two ways. It starts from revenue: the market sets what the building is worth, and every cost has to fit under it. And profit is a cost line, set aside before the model tells you what’s left for land, because a project that only breaks even has paid nothing for the risk.
At land purchase it’s built from benchmarks and assumptions. By the construction loan it should rest on a measured estimate, fee proposals, the City’s schedules and an appraisal.
Pro forma, feasibility study and budget
A feasibility study is the wider exercise; the pro forma is its financial core. A development budget is the cost side alone, line by line, which our guide to hard costs vs soft costs sets out in full. A cash flow spreads the pro forma’s lines over time, month by month, so the interest can be calculated.
The lines of a development pro forma, and where each number comes from
The order matters. Build revenue first, because many costs (land transfer tax, parkland, the community benefits charge, financing) depend on numbers further up.
| Line | What it includes | Where the number comes from |
|---|---|---|
| Revenue: sale | Unit sales net of HST the builder remits, commissions and incentives | Comparable new sales, a market study, the sales team |
| Revenue: rental | Net operating income ÷ capitalization rate = stabilized value | Comparable rents, operating cost budgets, an appraiser’s cap rate |
| Hard costs | Site work, structure, envelope, services, finishes, the contractor’s general conditions and fee | A measured estimate; a cost guide as a check |
| Hard cost contingency | Unfinished design and unknown site conditions | Sized by design stage |
| Consultants | Architect, engineers, planner, cost consultant, development manager | Fee proposals |
| Approvals and permits | Rezoning, site plan, Committee of Adjustment, building permit fees | Municipal fee schedules, dated |
| Municipal charges | Development charges, education development charges, parkland, community benefits charge | Municipal by-laws and rate pamphlets, dated |
| Land acquisition | Purchase price, land transfer tax, closing legal | Agreement of purchase and sale; provincial and municipal tax tables |
| Other soft costs | Legal, insurance, property tax during construction, utility connections, marketing, leasing, Tarion and HCRA for homes for sale | Quotes and schedules |
| HST | Self-supply on rental, net of rebates; or HST in sale prices | Your accountant, CRA and Ontario rebate rules |
| Financing | Interest during construction, lender and broker fees, the lender’s cost consultant, mortgage insurance premiums | Term sheet and the cash flow |
| Soft cost contingency | Consultant changes, extra resubmissions, fee increases | A separate amount from the hard cost contingency |
| Profit | The return you need for the risk | Your own hurdle; what your lender and equity partners expect |
Revenue
For sale (condominium or freehold). Revenue is the expected price of each unit from comparable new projects, net of the HST the builder remits, rebates credited to buyers, commissions and incentives.
For rent. Revenue is the value of the finished, leased building. Start with gross rents for each unit type, take off vacancy and bad debt, then operating costs (property tax, insurance, utilities, repairs, management, reserves) to get net operating income. Divide by a capitalization rate and you have what an investor would pay for the stabilized building. CBRE’s Canada cap rate survey for the third quarter of 2026 reported a national all-property average of 6.56% and noted that multifamily was the only asset class where cap rates rose slightly, under pressure from higher bond yields (CBRE, October 2026). The rate for your building is an appraiser’s opinion, and it moves.
Hard costs
The best hard cost number is a measured estimate from current drawings. At land purchase there usually aren’t drawings, so the first pro forma uses cost per square foot for the building type, checked against a published guide. Altus Group’s Canadian Cost Guide is the one most Canadian lenders and cost consultants use; the 2026 edition was released on April 23, 2026 and benchmarks hard construction costs by asset class and city (Altus Group, 2026). Altus’s commentary on the 2026 guide reported that Toronto’s overall construction costs stabilized in 2025, while residential costs declined (Altus Group, 2026). A guide can’t see your site’s shoring, dewatering, soil or heritage facade. If you’ve been handed an estimate, our guide to reading a construction estimate explains the classes from D to A and what each can be relied on for.
Soft costs
Build soft costs line by line from fee proposals and dated schedules, not a percentage.
Financing
Interest is calculated from the cash flow, not added as a percentage. It depends on how much you borrow, when each dollar is drawn, the rate, and how long the loan runs, including the lease-up or closing period after construction. Our guide to construction financing in Ontario covers what lenders ask for and how draws work. For purpose-built rental, CMHC’s MLI Select can change the financing lines entirely: for new construction it allows loans of up to 95% of cost and amortization of up to 50 years at 100 points, with a minimum debt coverage ratio of 1.10 for standard rental (CMHC, MLI Select). The insurance premium is then a financing line of its own. Our guide to CMHC MLI Select explains the points and what the building has to do to earn them.
Contingency and profit
Carry hard and soft contingency separately, and size the hard side by how complete the design is; our guide to construction contingency covers what to carry at each design stage.
Profit can be expressed as a share of total cost, a share of revenue, a yield on cost (net operating income ÷ total development cost, for rental), or an internal rate of return on your equity. We don’t quote a “good” margin, because there isn’t a sourced Ontario figure that holds across project types and years. What you need depends on how much risk you carry, how long your equity is tied up, and what your lender and any equity partner require. Set the number before you run the residual, and don’t lower it to make a site work.
Ontario costs that catch first-time developers
Each of these is set by statute, by-law or a published schedule, so each can be worked out before you agree a land price.
Development charges and education development charges
Toronto’s development charges, effective June 26, 2025, are set per unit by type and tenure. Rental rates are lower: $48,299 for a two-bedroom rental apartment and $33,497 for a one-bedroom or bachelor, against $80,690 and $52,676 for the same units built for sale (City of Toronto, DC rates pamphlet). Council adopted reduced rates in July 2026, but they depend on a funding agreement with the Province and other conditions, so carry them as a separate line until they’re in force. The Development Charges Act sets when the charge is paid: rental in six annual instalments from occupancy, and non-rental residential at occupancy since November 3, 2025 (Development Charges Act, s. 26.1). The payment date changes how much interest the loan carries. Education development charges are separate; in Toronto they’re $3,893 per unit to December 2, 2026 and $4,193 from December 3, 2026, payable at the first above-ground permit (City of Toronto, Education DCs). Outside Toronto, regional charges sit on top of local ones. Our guide to development charges in Ontario covers the rules, exemptions and the rate freeze in full.
Charges that depend on the land value
Three lines are calculated from what the land is worth, which is why they matter so much to a residual:
- Parkland dedication or cash-in-lieu. Up to 5% of the land for residential development under section 42 of the Planning Act, or a higher alternative rate capped at 10% of the land’s value on sites of five hectares or less (Planning Act, s. 42). In Toronto the alternative rate applies only in Parkland Acquisition Priority Areas, and the City values the land through its own appraisal, due before the first above-grade permit (City of Toronto, Parkland Dedication).
- Community benefits charge. Up to 4% of land value on buildings of five or more storeys with ten or more units, and Toronto levies the full 4% when the building permit is issued (City of Toronto, Community Benefits Charge).
- Land transfer tax. Ontario’s rate on land other than one or two single-family homes climbs to 2% on the portion over $400,000 (Government of Ontario, Land Transfer Tax). In Toronto the Municipal Land Transfer Tax adds the same brackets again (City of Toronto, MLTT rates), so on a Toronto development site the two together come close to 4% of the price.
On a mid-rise Toronto site outside a priority area, those three can add roughly 13% to every dollar you pay for the land, before you pay interest on it.
HST
On purpose-built rental, the owner is generally treated as having sold the building to itself when the first unit is occupied, and owes HST on its fair market value. For qualifying projects the federal government rebates the full GST portion, and Ontario rebates the full 8% provincial portion on projects that start construction by December 31, 2030 and finish by December 31, 2035 (CRA, purpose-built rental rebate; Government of Ontario). CRA lists what doesn’t qualify, including duplexes, triplexes, condominiums and substantial renovations. If your pro forma depends on a rebate, show the tax and the rebate as two lines and have your accountant confirm eligibility before it goes to a lender.
On homes for sale, HST is inside the price, and buyer rebates such as CRA’s first-time home buyers’ rebate (full federal portion on a new home up to $1 million) affect what buyers will pay.
Tarion and HCRA
Homes for sale need Tarion enrolment and an HCRA licence before construction, with enrolment fees from $585 to $6,055 by price, plus HST. Rentals the vendor keeps are generally out; confirm with Tarion.
Approvals, permits and the Toronto Green Standard
Toronto’s 2026 site plan fee is $43,605.12 plus $5.37 per square metre of gross floor area, and a zoning by-law amendment is $63,679.83 plus $6.23 per square metre (City of Toronto, planning fees). The building permit fee for a multi-unit residential building is $18.56 per square metre plus $56.33 per unit (City of Toronto, building permit fees). The fees are small next to the time: every extra month of approvals is a month of interest on the land. Our guides to site plan control, zoning by-law amendments and the Toronto Green Standard cover each step.
Residual land value: a worked example
Every input is a labelled assumption chosen to show how the model works. None is market data, and none comes from a real project. The municipal charges are the City of Toronto’s published rates, cited above.
The project (assumptions): a six-storey purpose-built rental building in Toronto, 48 units (24 one-bedroom, 24 two-bedroom), 33,600 sq ft rentable inside 42,000 sq ft (3,902 m²) gross floor area. Zoning is in place, so site plan is the only planning application. The site is outside a Parkland Acquisition Priority Area.
Step 1: what the finished building is worth
| Line | Assumption | Amount |
|---|---|---|
| Gross rent | 48 units × $3,000 a month × 12 | $1,728,000 |
| Less vacancy and bad debt | 3% | −$51,840 |
| Effective gross income | $1,676,160 | |
| Less operating costs | $9,500 per unit a year | −$456,000 |
| Net operating income | $1,220,160 | |
| Stabilized value | $1,220,160 ÷ 4.5% cap rate | $27,114,667 |
Step 2: everything except the land
| Line | Basis | Amount |
|---|---|---|
| Hard costs | 42,000 sq ft × $350 (assumption) | $14,700,000 |
| Hard cost contingency | 5% (assumption) | $735,000 |
| Consultants | Assumption | $1,300,000 |
| Site plan fee | $43,605.12 + $5.37 × 3,902 m² | $64,559 |
| Building permit | $18.56 × 3,902 m² + $56.33 × 48 | $75,125 |
| Development charges | 24 × $33,497 + 24 × $48,299 (rental) | $1,963,104 |
| Education development charges | 48 × $4,193 | $201,264 |
| Legal, insurance, taxes during construction, utilities, leasing | Assumption | $900,000 |
| Soft cost contingency | Assumption | $200,000 |
| Subtotal before financing | $20,139,052 | |
| Interest | Loan of 75% of subtotal ($15,104,289), half drawn on average, 6%, 30 months | $1,132,822 |
| Lender and broker fees | 1% of the loan | $151,043 |
| Total before land | $21,422,916 |
HST on the self-supply is assumed to be fully rebated under the federal and Ontario purpose-built rental rebates; in a real pro forma it would be two lines, the tax and the rebate.
Step 3: set the profit
Assume the owner needs a profit of 15% on total development cost. That means total cost, land included, can’t exceed the value divided by 1.15:
$27,114,667 ÷ 1.15 = $23,577,971
Step 4: account for the costs that come with the land
Each dollar of land brings the land-linked costs with it. On the assumptions here:
| Per dollar of land | Rate |
|---|---|
| The land itself | 1.00 |
| Parkland cash-in-lieu (basic rate) | 0.05 |
| Community benefits charge | 0.04 |
| Ontario + Toronto land transfer tax (top brackets) | 0.04 |
| Interest carrying the land (6% for 2.5 years, simple) | 0.15 |
| Total cost per dollar of land | 1.28 |
The land transfer tax brackets below $400,000 are lower than 2%, which saves $3,525 on each of the two taxes, $7,050 in total.
Step 5: solve for the land
What’s left for land and its costs is $23,577,971 − $21,422,916 = $2,155,055. Add back the $7,050 bracket saving and divide by 1.28:
($2,155,055 + $7,050) ÷ 1.28 = $1,689,144, about $35,000 per unit
Check: land $1,689,144 + land-linked costs $465,910 + everything else $21,422,916 = $23,577,970 total cost, leaving a profit of $3,536,697, 15% on cost. The yield on cost is $1,220,160 ÷ $23,577,970 = 5.2%.
On this example the land-linked costs add $465,910 to a $1.69 million land price; compare an asking price to the residual without them and you overpay by that much. Parkland and the community benefits charge are set on the City’s appraisal the day before the permit, not on what you paid, so a rising land market raises them.
Rental, condo and multiplex pro formas
The lines change with what you’re building and whether you keep it.
| Purpose-built rental | Condominium for sale | Toronto multiplex (4–6 units) | |
|---|---|---|---|
| Revenue | NOI ÷ cap rate | Sales, net of HST and commissions | Either; often held as rental |
| Development charges | Rental rates, six annual instalments | Non-rental rates, at occupancy | Toronto exempts units 2 to 6 in developments of up to six units |
| Parkland and CBC | Both, if 5+ storeys and 10+ units | Both, if 5+ storeys and 10+ units | Parkland exempt for units 2 to 6; no CBC below five storeys |
| HST | Self-supply, rebates if eligible | In the sale price; buyer rebates | Self-supply; duplexes, triplexes and substantial renovations miss the rental rebate |
| Tarion / HCRA | Generally not, if the vendor keeps it | Yes, fees by price | Yes if sold |
| Financing | MLI Select at 5+ units, sized on debt coverage | Conventional, usually with presales first | Conventional, or MLI Select at 5+ units |
| Profit measure | Yield on cost, IRR | Margin on cost or revenue | Yield on cost, or margin if sold |
Rental
A lender sizes the loan on the debt coverage ratio (net operating income ÷ annual debt payments), so a building can have a positive residual and still not support the loan you planned. If you use MLI Select, its affordability commitments lower revenue too, because affordable units rent below market. If the building already exists as offices, a conversion pro forma also has to carry the façade, new services and abatement; our guide to office to residential conversion in Toronto covers those tests.
Condominium
A condo pro forma turns on sales pace and price per square foot. Lenders usually want a meaningful share of units presold before they’ll advance, and buyers’ deposits are held in trust under the Condominium Act, so the equity and timing differ from rental. Development charges are now paid at occupancy, which cuts the interest the loan carries.
Multiplex
A Toronto fourplex or sixplex carries far fewer government charges than a mid-rise: the first unit is the only one that pays development charges, units two to six are exempt from parkland, and there’s no community benefits charge. The trade-off is a small building with less efficient construction, and duplexes, triplexes and substantial renovations don’t qualify for the rental rebate. Our guide to building a multiplex in Toronto covers the rules and the budget.
Sensitivity: what moves the answer most
A residual is a small number left after subtracting large ones, so it moves a lot. Here’s the example rerun, one assumption at a time:
| Change | Residual land value | Change from base |
|---|---|---|
| Base case | $1,689,144 | |
| Hard costs +10% | $406,411 | −76% |
| Rents −5% | $423,927 | −75% |
| Interest rate +1 point (6% to 7%) | $1,512,108 | −10% |
| Cap rate +0.25 points (4.5% to 4.75%) | $719,655 | −57% |
| Toronto’s reduced rental DCs, if the conditions are met | $2,534,387 | +50% |
Three things stand out:
- Revenue and hard cost dominate. A 10% hard cost overrun or a 5% shortfall in rents takes three quarters of the land value. Those are the two numbers to test hardest at land purchase.
- The cap rate is a revenue number. A quarter-point change in the market’s yield moved the answer by more than half. You can’t control it, but you can make sure the pro forma doesn’t rest on the lowest cap rate anyone has quoted.
- Time costs as much as the rate. A full point on the rate cost 10%. Six more months of approvals or construction, on the same arithmetic, cuts the residual to about $1.48 million (−13%), before any cost escalation.
Run it before you make an offer. Hard costs +10% and rents −5% together leave this site with a negative residual.
Who builds the pro forma, and who checks it
| Who | What they bring | What they check |
|---|---|---|
| Owner or developer | The plan, the profit target, the equity | That the numbers support the decision |
| Development manager | The model, the schedule, the approvals path, every line pulled together | That each line has a source and a date |
| Planner | What zoning allows or what a rezoning might achieve: the yield in units and floor area | That the building in the pro forma can be approved |
| Architect | Massing and areas: gross floor area, rentable or saleable area, efficiency | That the floor areas are real |
| Cost consultant | Hard cost estimate by design stage | That the hard cost and contingency match the design |
| Accountant | HST, rebates, the tax structure | That the tax lines are right for your entity |
| Appraiser | Value as completed, and often land value | Revenue and cap rate, independently |
| Lender and its cost consultant | Loan terms and a review of the budget | Cost to complete, equity, debt coverage |
CMHC’s guide for insured standard rental construction loans describes the review a lender will typically commission: a quantity surveyor’s cost review, a fixed-price or construction management contract, and CMHC approving the first and last advance (CMHC, reference guide). Conventional lenders work much the same way, and a pro forma that sources every line gets through that review faster.
Mistakes experienced owners check for
These are what we look at first when we review a pro forma.
- Land-linked costs left out of the residual. Parkland, the community benefits charge and land transfer tax all scale with the land, and in Toronto there are two land transfer taxes.
- Gross and net areas mixed up. Revenue runs on rentable or saleable area; hard costs run on gross floor area. A building that’s 80% efficient has a quarter more floor to build than to rent.
- Development charges at the wrong rate or the wrong time. Rental and non-rental rates differ, rates are frozen only under the Act’s conditions, and the payment date drives the interest. Pending reductions belong on a separate line until they’re in force.
- A schedule that skips approvals. The interest and carrying costs on land run from purchase, not from construction start.
- One contingency for everything. Hard and soft contingency are spent for different reasons and should be tracked separately.
- Profit as the balancing figure. If the margin has to drop to make the land price work, renegotiate the price or change the plan.
- The best case as the base case. The base case should be the number you’d defend to a lender, with the upside listed separately.
Frequently asked questions
What is a good profit margin on a development project?
There’s no sourced Ontario figure that holds across project types, so we don’t quote one. Lenders and equity partners look at it from their side: a lender wants enough margin that a cost overrun or a slower sale doesn’t leave the loan uncovered, and an equity partner wants a return that reflects how long its money is at risk. Set your target with them before you price the land, and hold to it.
What’s the difference between a pro forma and a feasibility study?
A feasibility study asks whether a project can and should go ahead: zoning, the approvals path, the market, the cost, the schedule and the risks. The pro forma is the financial model at its centre: whether the numbers work and what the land is worth. Each needs the other, because the pro forma’s inputs come from the study’s zoning, market and cost work.
How accurate should a pro forma be at land purchase?
At land purchase there are usually no drawings, so the hard cost is a benchmark from a cost guide or comparable projects, and the estimate is at its least precise. That’s acceptable if the pro forma carries contingency to match and the sensitivity shows how much the land value moves. It gets firmer at each stage: massing, a class C estimate, then a class B or A estimate from detailed drawings before the construction loan.
Where to start
If you’re weighing a site, start with what zoning allows, a hard cost benchmark from a named Canadian cost guide, and the municipal charges from the City’s schedules. That’s enough for a first residual and a sensitivity table before you spend on consultants.
We’ve built and reviewed pro formas from the first land offer to the lender’s cost review. Our experience, built at PCL Constructors and Oxford Properties, includes projects such as Scarborough Junction in Toronto, where the work covered all preconstruction planning, and the Ashley Mar Co-op Renewal in Vancouver, overseen from development through completion. If you’d like an experienced hand to test the numbers on your site, see how our development management service works from land to occupancy.