What Decides an Office to Residential Conversion in Toronto
An office to residential conversion works when the building already has most of what an apartment building needs: a floor plate shallow enough that every bedroom can reach a window, a structure and height that can take new plumbing and ventilation, exits that can be brought up to residential standards, and land where the City allows people to live. Most office buildings fail at least one of those tests, so most aren’t converted. Some pass, and they can make good rental or condominium buildings. The first thing to check is the distance from the windows to the core on a typical floor. If it’s well over 50 feet, the building is unlikely to work without major changes.
This guide is for the owner of an older office building in Toronto or the GTA. It covers the building test, the Building Code and City rules when the use changes, the cost drivers, today’s programs, and the order to check it all in before you pay for design.
Can any office building be converted to residential?
Not economically, no. Almost any building can be converted if money is no object. The real question is whether the finished apartments will be worth more than the building as offices plus the cost of the work.
The market explains why owners are asking. Altus Group’s Q3 2026 office market update (October 2026) puts Toronto’s office availability at 15.1%, down 190 basis points from a year earlier. Downtown Class A availability fell to 11.2%. The same report says older Class B and C buildings across Canada “continued to face utilization challenges.” Tenants are moving up to better space, and the buildings they leave behind are the ones that get offered for conversion.
Older mid-rise offices with narrow floors and punched windows are also the ones most likely to suit housing. A tower with deep floors and a sealed glass curtain wall usually doesn’t convert well, however empty it is.
The Canadian Urban Institute’s Charting the Path to Office Conversions in Canadian Cities (March 2024, funded through CMHC’s National Housing Strategy Demonstrations Initiative) includes an office building assessment framework. It’s the most useful public checklist we know of, and the building test below follows its order, with the Ontario rules added.
What makes a building convertible: the checklist
Walk through these with the floor plans and structural drawings. Each item can end the project or add real cost.
- Window-to-core distance. The CUI framework treats 24 to 50 feet from the outside wall to the core as compatible, with 40 feet as ideal. Beyond that, the middle of the floor can’t be lit or ventilated as bedrooms, and you end up with leftover space you can’t rent. A rectangular floor plate is easiest to lay out; irregular shapes take more design work and lose more area.
- Windows on enough sides. CUI’s framework prefers windows on three or more sides of the building. Two sides can work if the floor plate is narrow.
- Operable windows and the façade. Bedrooms need windows that open. Buildings with glazed curtain walls will likely need the whole wall replaced, which the framework says has to be counted in the cost from the start. Punched windows in masonry or precast are cheaper to replace one by one.
- Floor-to-floor height. Apartments need a ceiling, a sprinkler system, ventilation ducts and drain lines from every bathroom and kitchen running sideways to a stack. Generous floor-to-floor height leaves room for all of it. Tight height pushes you to more stacks, more coring and lower ceilings.
- Structure and loading. Ask a structural engineer whether the slabs can be cored for new plumbing stacks and whether the columns sit where unit walls can go. Office floors are designed for higher live loads than apartments, so loading is rarely the problem; new openings, balconies and rooftop amenities can be.
- Plumbing and mechanical. Offices have a few washroom stacks near the core. Apartments need a kitchen and bathroom in every unit. The CUI framework expects most plumbing and electrical for the units to be new, and the HVAC to be replaced or heavily modified, so carry them as new until an engineer says otherwise.
- Exits and fire separations. Residential use brings fire separations between units and corridors, and the exit stairs have to work for people who are asleep. Check whether the existing stairs and their locations can meet the requirements, and whether a new stair could be added if not.
- Elevators. Count them and check their condition. Residential traffic is lighter than office traffic, so an office tower often has enough cars. The question is their age and whether a modernization is already due.
- Parking and loading. By-law 89-2022 removed most of Toronto’s minimum parking requirements, so a building with little parking isn’t usually ruled out. Residential visitor parking was kept at a lower rate. You’ll still need bicycle parking, a loading and garbage plan and a place for move-ins.
- Heritage. Check the City of Toronto Heritage Register. A designated building needs heritage approval for exterior changes, which matters when you’re replacing windows.
- Environmental history. A former garage, dry cleaner or industrial use on the property changes the approvals path (see the Record of Site Condition section below).
- Hazardous materials. Buildings of a certain age often contain asbestos and other designated substances. You’ll need a survey before work begins anyway, and it affects the cost.
A building that passes items 1 to 3 is worth an engineer’s time. One that fails them usually isn’t.
A condition assessment is the right first spend
Most of that checklist can be answered by a building condition assessment with the question “what survives a change to residential?” written into the scope. It costs far less than a design team and tells you whether one is worth hiring.
The Building Code when the use changes
Do you need a permit to convert commercial to residential in Ontario?
Yes. Section 10 of the Building Code Act says no one may change the use of a building, or part of one, in a way that increases the hazard as determined under the Building Code unless the chief building official has issued a permit, “even though no construction is proposed.” The same section says the official issues it unless the proposed use would breach the Act, the Code or any other applicable law, the application is incomplete, or fees are unpaid. Apartments are a residential occupancy where people sleep, which the Code treats as a higher hazard than offices, so an office-to-apartment conversion needs a permit, and in practice it also needs a building permit for all the construction that comes with it.
“Any other applicable law” is why zoning comes first. If residential use isn’t permitted on the land, the permit can’t be issued, however good the drawings are.
Part 10 and Part 11 of the Ontario Building Code
The 2024 Ontario Building Code (O. Reg. 163/24, in force January 1, 2025, and amended since) has two parts written for this situation. The article numbers below are from the OAA’s Part 11 data matrix (May 2026, current to O. Reg. 119/26), which architects use to document a renovation for the permit. The full Code text is in the Province’s Building Code Compendium.
- Part 10, Change of Use. Article 10.1.1.2. sets out when a change in major occupancy happens. Office (Group D, business and personal services) to apartments (Group C, residential) is a change in major occupancy.
- Part 11, Renovation. Part 11 applies to work on existing buildings. It doesn’t ask an old building to become a new one. Instead it rates the existing building (a construction index and a hazard index, Table 11.2.1.1.A and the tables after it), classes the work as a basic or an extensive renovation (Articles 11.3.3.1. and 11.3.3.2.), and asks whether the work reduces the building’s performance level.
- Reduction in performance level. Article 11.4.2.3. covers a reduction caused by a change of major occupancy, alongside structural changes, a higher occupant load, plumbing and sewage systems (Articles 11.4.2.1. to 11.4.2.5.). Where performance is reduced, Subsection 11.4.3. sets out the compensating construction needed to bring it back up, such as sprinklers, fire separations, exits or structural upgrades.
- Compliance alternatives. Subsection 11.5.1. lists compliance alternatives: set ways of meeting a requirement in an existing building that the Code accepts in place of the new-building rule. Your architect proposes them and the City’s examiner accepts them as part of the permit review. Where neither works, an alternative solution can be proposed under Division A.
In plain terms, the conversion doesn’t have to make the building identical to a new apartment building, but it has to show that the building as converted is at least as safe as the Code requires for its new use. How much construction that takes depends on the building, and it’s the architect and the fire protection engineer who work it out. Ask for that work early, because it decides whether the fix is a few fire separations or a new stair.
Barrier-free design
Part 11 also sets out when a renovation has to add barrier-free features (the matrix points to Articles 11.3.1.2., 11.3.2. and 11.3.3.2.). On a whole-building conversion, expect the examiner to ask how the entrances, suites and common areas meet them. If you plan to use CMHC financing that rewards accessibility, the CMHC standard can go further than the Code; see our guide to MLI Select points.
Zoning and approvals in Toronto
The building can be perfect and the conversion can still fail on land use. Check four things.
Is residential permitted on the land?
Look the property up on the City’s interactive zoning map under Zoning By-law 569-2013. The Commercial Residential (CR) zone permits residential uses under the “r” in its zone label (Chapter 40, regulation 40.10.20.10). Employment zones generally don’t. Then check the Official Plan land use designation, because the plan can restrict what the zone seems to allow.
If residential is permitted and the building as converted fits the zoning numbers (height, density, setbacks, amenity space, bicycle parking), you go straight to site plan and the building permit. If the conversion needs small departures from those numbers, a minor variance at the Committee of Adjustment may be enough. If residential isn’t permitted at all, you need a zoning by-law amendment, and possibly an Official Plan amendment as well.
Employment areas after 2024
Until 2024, office buildings inside designated employment areas were among the hardest to convert, because Ontario law protected employment land from conversion. That changed. The definition of “area of employment” in section 1(1) of the Planning Act now covers manufacturing, research tied to manufacturing, warehousing, and offices and retail associated with those uses, and it expressly excludes institutional uses and commercial uses, “including retail and office uses” not tied to them. That definition came into force on October 20, 2024.
The practical effect is that a stand-alone office building is less likely to sit inside a legally protected employment area than it was. It doesn’t mean the City’s Official Plan designation has disappeared. Where the land is still designated an Employment Area in the Official Plan, a conversion will need a planning application, and a land use planner should read the current designation and any appeals against it before you buy or design.
Toronto’s office replacement policy
In parts of downtown and midtown, the City has asked owners who redevelop office buildings to replace the office space. The City’s Office Space Needs Study (page updated October 30, 2026) explains where that policy stands:
- The replacement policy is in Official Plan Amendment 231, which is under appeal, and mediation on it has been paused.
- The proposed direction cuts required office replacement from 100% to 25%, and lets that 25% be other non-residential uses and/or affordable housing, with a minimum non-residential share.
- It applies in the Financial District, the Health Sciences District and the Bloor-Bay Office Corridor (Downtown Plan), and in Mixed Use Areas A and B of the Yonge-Eglinton Secondary Plan.
- On December 16, 2025, Council authorized staff to negotiate office replacement site by site under the proposed directions.
If your building is in one of those areas, raise replacement with City Planning before you design.
Site plan control
Toronto’s Municipal Code Chapter 415 (consolidated July 30, 2026) exempts interior alterations or conversions of an existing building from site plan approval where the zoning permits the use and the building will have no more than 10 dwelling units in total (§ 415-45.3). A conversion creating more than 10 units isn’t exempt, so plan for site plan control, and confirm the scope at the pre-application consultation. Exterior changes, new balconies, waste and loading areas and landscaping are the usual site plan subjects on a conversion.
Record of Site Condition
Ontario’s Environmental Protection Act, section 168.3.1, prohibits changing the use of a property from commercial or industrial to residential without a Record of Site Condition, which means environmental site assessments and filing with the Province. O. Reg. 153/04 (as amended by O. Reg. 236/25, in force October 23, 2025) exempts some building conversions under section 15. The one most relevant to offices applies where:
- the property is used for commercial or community use before the change, and afterward will be used for commercial or community use as well as residential;
- the residential use is limited to floors above the ground floor;
- there’s no addition at ground level, other than for fire safety, accessibility or an attached outdoor structure (additions above the ground floor are allowed since the 2025 amendment, and the old six-storey cap is gone); and
- the property has never been used for industry, as a garage, as a gas station or other bulk liquid dispensing facility, or for dry cleaning equipment.
A building with shops or offices kept at grade and apartments above can often use that exemption. A full residential conversion, or a property with a garage in its history, generally can’t, and the Record of Site Condition becomes part of the schedule. Your environmental consultant should confirm which applies before you commit to a plan.
How much does it cost to convert an office to apartments?
We don’t know of a published, dated Toronto cost range for office conversions that we’d stand behind, so this section gives no dollar per square foot. Calgary’s downtown program, which the CUI report describes as paying $75 per square foot of converted space, is often quoted as a reference; the City of Calgary’s downtown incentive page now lists that conversion program as closed for applications.
What we can say is where the money goes. These are the big lines in a conversion budget.
| Cost line | What drives it | How to get a number early |
|---|---|---|
| Façade and windows | Curtain wall vs punched windows; operable windows in every bedroom; heritage approval; energy performance of the new wall | Façade consultant’s review of the existing wall; a budget price from a curtain wall or glazing contractor |
| Plumbing and drainage | Number of new stacks; coring through slabs; floor-to-floor height for horizontal runs; water service size | Plumbing engineer’s riser layout on a test floor plan |
| HVAC and ventilation | Replacing central office systems with suite-by-suite heating, cooling and ventilation; make-up air for kitchens and corridors | Mechanical engineer’s concept; check the electrical service against it |
| Electrical | New distribution to every unit, suite metering, possibly a larger service | Electrical engineer’s load estimate; early request to the utility |
| Fire protection and exits | Sprinklers, fire alarm, fire separations between suites, new or altered stairs | Fire protection engineer’s Part 11 review |
| Vertical transportation | Elevator modernization, a new car if residential code or accessibility needs it | Elevator consultant’s condition report |
| Abatement and demolition | Asbestos and other designated substances; stripping the floors back to the structure | Designated substances survey, then an abatement budget price |
| Structure | New openings, balconies, rooftop amenity loading | Structural engineer’s review of the drawings and site |
| Interior construction | Unit walls with acoustic separation, kitchens, bathrooms, finishes | Cost consultant’s estimate on the test floor plan, at a unit count |
Designated substances come first
Section 30 of Ontario’s Occupational Health and Safety Act requires the owner, before beginning a project, to determine whether designated substances are present and list them, and to include that list in any tender. In an older office building that survey is both a legal step and one of the first cost inputs. Commission it with the condition assessment.
Government charges and taxes
Two lines catch owners who expect a conversion to be cheaper than new construction:
- Development charges. Toronto charges development charges on new residential units created by a conversion. Chapter 415 gives a credit for the existing non-residential space, but for a non-residential building redeveloped for residential purposes the credit is calculated on the existing non-residential floor area on the ground floor only, at the non-residential rate. On a ten-storey office building, nine floors of apartments pay the residential charges with no credit. Our article on development charges in Ontario covers the rates and when they’re due.
- HST. Converting to rental means self-supplying the building and paying HST on its fair market value when it’s first occupied. The CRA’s purpose-built rental housing rebate page (June 2026) says the enhanced federal rebate may apply to “a conversion from a non-residential building, such as an office building, to a multiple unit residential complex.” The building needs at least 10 units, each with its own kitchen, bathroom and living area, and at least 90% of them held for long-term rental. Construction must begin after September 13, 2023 and before 2031, and be substantially completed before 2036; the page gives the same windows for Ontario’s portion. Confirm with your tax adviser how it applies to your building.
Programs and financing available today
As of November 2026, these are the programs we could confirm from primary sources. We found no City of Toronto incentive program for office-to-residential conversion; the Office Space Needs Study describes exploring incentives but doesn’t say any has been adopted.
| Program | Who runs it | What it does for a conversion | Source |
|---|---|---|---|
| Apartment Construction Loan Program (standard rental) | CMHC | Construction and term lending that “also supports the conversion of non-residential to standard rental housing.” At least 5 rental units and a $1 million loan; up to 100% loan to cost on residential space and 75% on non-residential, depending on the application; at least 20% of units at or below 30% of median family income for at least 10 years under one option | CMHC ACLP (published Nov 2024) |
| MLI Select | CMHC | Mortgage insurance for 5+ unit rental, with better terms for affordability, energy and accessibility points | CMHC MLI Select |
| Purpose-built rental HST rebate | CRA and Ontario | Rebate of the federal and Ontario portions of HST on qualifying rental, conversions included | CRA (June 2026) |
Ask your lender early how it will treat a conversion under MLI Select, because affordability, energy and accessibility points have to be designed in from the start. Our guide to construction financing in Ontario covers draws and holdback, which work the same way on a conversion.
A feasibility sequence, in order
This is the order we’d check a building in. Each step is cheaper than the next and can stop the project before you spend on it.
- Read the zoning and Official Plan designation. Is residential permitted? Is the land in an Employment Area or an office replacement area? A one-page answer from a land use planner settles this.
- Measure the floor plate. Window-to-core distance, shape, windows on how many sides.
- Check the history of the property. Past uses that rule out the Record of Site Condition exemption, heritage status, any open orders or permits.
- Commission a condition assessment scoped for conversion, with a designated substances survey.
- Test-fit two typical floors. An architect lays out units on a typical floor and on the ground floor, which gives you a unit count and mix, saleable or rentable area and efficiency.
- Get a Part 11 review. The architect and fire protection engineer set out the compensating construction the Code will ask for, and where compliance alternatives might apply.
- Get an engineering concept for plumbing, mechanical and electrical on the test fit, including whether the electrical service is big enough.
- Price it. An independent cost estimate on the test fit, with the façade, abatement and services carried as separate lines and a design contingency suited to an existing building.
- Book a pre-application consultation with the City if any planning approval or site plan is needed, and add those timelines to the schedule.
- Run the pro forma. What the finished units are worth, less every cost above, the government charges, financing and the return you need, compared with what the building is worth as offices. Our guide to the development pro forma walks through the lines.
- Talk to the lender with the pro forma and the test fit, before you commit to design.
Sign a full design contract only after step 11.
Frequently asked questions
Can any office building be converted to residential?
Physically, most can. Economically, most can’t. The deciding features are the window-to-core distance (CUI treats 24 to 50 feet as compatible), windows that can be made operable, enough floor-to-floor height for new plumbing and ventilation, exits that can meet residential requirements, and land where residential use is permitted or can be approved. A building that fails the floor plate test rarely works at any price.
Do you need a permit to convert commercial to residential in Ontario?
Yes. Section 10 of the Building Code Act requires a permit for any change of use that increases the hazard under the Building Code, even if no construction is planned, and office to residential is that kind of change. The permit can’t be issued unless the new use complies with zoning and other applicable law. A Record of Site Condition may also be required unless an exemption in O. Reg. 153/04 applies.
How much does it cost to convert an office to apartments?
There’s no reliable published Toronto range, and costs vary widely from building to building. The big lines are the façade and windows, new plumbing stacks, suite-by-suite HVAC and electrical, fire protection and exits, elevators, and abatement. Development charges apply to new units, with Toronto’s credit limited to ground-floor non-residential space. Get a test fit and an independent estimate before relying on any number.
What is adaptive reuse?
Adaptive reuse means giving an existing building a new use instead of demolishing it, such as an office turned into apartments. In Ontario, the Building Code treats it as a change of use under Part 10 and a renovation under Part 11, and the City treats it like any other development for zoning, site plan and development charges.
What to do next
If you own an office building and want to know whether it can become housing, start with the zoning answer and the floor plate, then a condition assessment scoped for conversion. Those three tell you whether the rest is worth paying for.
Our office experience, built at PCL Constructors and Oxford Properties, includes 85 Richmond Street West, a 1923 heritage office building gutted to its structure with new services, and capital programs across Cadillac Fairview’s downtown office towers. Myhal hasn’t delivered an office-to-residential conversion as a firm. What we bring is knowledge of how office buildings are built and serviced, and of how a development is taken from feasibility to a permit. If you’d like an experienced hand to scope the studies, read the results with you and run the feasibility in order, that’s our development management for conversions.