November 4, 2026
Development Charges in Ontario: 2026 Rules, Rates and Timing
Development charges are one-time fees a municipality collects on new construction to pay for the growth-related roads, transit, water, sewers, parks and emergency services that new buildings need. In Ontario they’re authorized by the Development Charges Act, 1997 and set in each municipality’s own by-law, with school boards adding an education development charge under the Education Act. In Toronto, a two-bedroom condominium apartment currently carries $80,690 and a two-bedroom rental apartment $48,299 in City development charges, at rates in effect since June 26, 2025. Non-rental homes now pay at occupancy, rental buildings over six years from occupancy, and non-residential space at the first building permit.
The rules have changed almost every year since 2022, and Toronto’s much lower adopted rates wait on a funding agreement. Every rule below was checked on November 3, 2026 against e-Laws (the Development Charges Act consolidated from June 2, 2026) and the City of Toronto’s and York Region’s own published schedules. This is a practical guide for owners and developers testing a site, not legal advice. The municipality’s development charge staff confirm the charge for a specific permit.
Who charges what on a GTA site
On most GTA sites development charges come from three or four governments, each on its own schedule.
| Layer | Who sets it | Toronto | Peel, York, Durham, Halton |
|---|---|---|---|
| Municipal development charge | The single-tier city, or the local municipality | City of Toronto (single tier) | The local city or town (e.g. Markham, Mississauga, Oshawa) |
| Regional development charge | The upper-tier region | None | The region, usually the largest share: water, wastewater, regional roads, transit |
| Education development charge | A qualifying school board, under the Education Act | Toronto Catholic District School Board, collected by the City | Varies by board; check the local and regional pages |
| Area-specific charges | A municipality, for one area’s infrastructure | Built into the City’s schedule | Some areas only, e.g. York’s Nobleton wastewater charge |
A regional example: York Region
York Region passed new development charge by-laws (No. 2026-20 and 2026-21) that came into effect on May 21, 2026. The Region-wide residential rates, before any local municipal or education charge is added, are (York Region, Development Charge Rates effective May 21, 2026):
| York Region unit type | Region-wide charge per unit |
|---|---|
| Single and semi-detached | $84,718 |
| Multiple unit dwelling | $72,392 |
| Apartment, 700 sq. ft. or larger | $58,721 |
| Apartment, under 700 sq. ft. | $37,202 |
| Industrial, office, institutional | $26.37 per sq. ft. of GFA |
| Retail | $72.42 per sq. ft. of GFA |
York sorts apartments by floor area (700 sq. ft.), not bedroom count, and indexes its rates each July 1 from July 1, 2027. The local municipality’s charge and any education charge are added on top from their own schedules.
The rules in 2026, after four provincial bills
Provincial laws since 2022 have rewritten when development charges are set, when they’re paid and who is exempt. This is what’s in force as of November 3, 2026.
| Rule | What it says now | Section of the Act | In force |
|---|---|---|---|
| Rate freeze | The charge is set at the rate on the day of the site plan application, or the zoning by-law amendment application if there’s no site plan | s. 26.2(1) | Jan 1, 2020; amended Nov 28, 2022 |
| Freeze expiry | The frozen rate falls away if more than 18 months pass between approval of that application and the first building permit | s. 26.2(5) | June 6, 2024 (Bill 185) |
| Lower of the two | If the frozen charge plus interest is more than the current charge, you pay the current charge | s. 26.2(5.2) | June 5, 2025 (Bill 17) |
| Interest on frozen charges | The municipality may charge interest from the application date, capped at the average big-five bank prime rate plus 1% | s. 26.2(3), s. 26.3 | Nov 28, 2022 |
| Rental discount | Rental units: 25% off for three or more bedrooms, 20% for two, 15% for the rest | s. 26.2(1.1) | Nov 28, 2022 (Bill 23) |
| Rental and institutional payment | Six equal annual instalments, starting at the earlier of the occupancy permit and first occupation | s. 26.1(3) | Jan 1, 2020; amended Nov 3, 2025 |
| Non-rental residential payment | Paid in full at the earlier of the occupancy permit and first occupation | s. 26.1(3.1) | Nov 3, 2025 (Bill 17) |
| Interest on instalments | Stopped. Only interest that had accrued before November 3, 2025 can be charged | s. 26.1(7) | Nov 3, 2025 (Bill 17) |
| Non-residential payment | At the first building permit, unless an agreement says otherwise | s. 26 | Unchanged |
| Additional units in houses | Second and third units in a new or existing house, and one unit in an ancillary building, are exempt | s. 2(3.2), (3.3) | Nov 28, 2022 |
| Units in existing rental buildings | The greater of one unit or 1% of existing units is exempt in buildings of four or more units | s. 2(3.1) | Nov 28, 2022 |
| Affordable units | Exempt if they stay affordable for 25 years, under an agreement with the municipality | s. 4.1(8), (9) | June 1, 2024 |
| Attainable units | Exempt only where the development is of a class prescribed by regulation | s. 4.1(4), (10) | Depends on regulation |
| Non-profit housing | Exempt | s. 4.2 | Nov 28, 2022 |
| Inclusionary zoning units | Exempt | s. 4.3 | Nov 28, 2022 |
| Long-term care homes | Exempt | s. 4.4 | June 5, 2025 (Bill 17) |
| Non-profit retirement homes | Exempt | s. 4.5 | June 2, 2026 |
The 2026 amendment, in the Building Homes and Improving Transportation Infrastructure Act, 2026, added the non-profit retirement home exemption. The bigger 2026 change is a funding program, and Toronto’s reduced rates depend on it.
The Canada–Ontario Development Charge Reduction Program
Ontario’s Development Charge Reduction Program is part of the $8.8 billion Canada–Ontario Partnership to Build. It pays for growth infrastructure such as roads, water, wastewater and transit in municipalities that cut development charges by 30% to 50% or more for three years, with up to 90% of eligible costs paid by the two senior governments and at least 10% by the municipality. It was open to municipalities with a development charge by-law in place on March 30, 2026, and applications are now closed (Government of Ontario, Development Charge Reduction Program).
On June 23, 2026, the two governments announced $1.5 billion for Toronto, on Toronto’s commitment to reduce residential development charges by 40% to 60%. The release makes the money conditional on a transfer agreement with the Province and on federal approval (Government of Canada, June 23, 2026).
Until your municipality has passed a reduced-rate by-law and the agreement behind it is signed, treat any reduction as a proposal.
Toronto’s development charges in 2026
Toronto is a single-tier city, so its by-law (By-law 1137-2022, in Municipal Code Chapter 415) covers what a region and a local municipality would split elsewhere. Rates are per unit by type, with separate schedules for non-rental and rental housing.
Current rates, effective June 26, 2025
From the City’s rate pamphlet, which is still the current schedule on the City’s by-laws, rates and study page as of November 3, 2026:
| Unit type | Non-rental, per unit | Rental, per unit |
|---|---|---|
| Single or semi-detached | $137,846 | n/a |
| Multiple, 3+ bedrooms | $113,938 (2+ rate) | $63,937 |
| Multiple, 2 bedrooms | $113,938 | $68,199 |
| Multiple, 1 bedroom or bachelor | $57,153 | $36,351 |
| Apartment, 3+ bedrooms | $80,690 (2+ rate) | $45,280 |
| Apartment, 2 bedrooms | $80,690 | $48,299 |
| Apartment, 1 bedroom or bachelor | $52,676 | $33,497 |
| Dwelling room | $37,356 | $23,759 |
| Non-residential, per m² | $805.64, ground floor only | n/a |
Rental rates aren’t the condo rates less 15% to 25%. Toronto publishes a separate rental schedule that applies to purpose-built rental as the by-law and the Act define it. The City lists the statutory rental reductions among its reductions, so confirm with the City that the rental figures already reflect them before you take anything further off.
A three-bedroom rental apartment is charged less than a two-bedroom. That’s how the schedule reads ($45,280 against $48,299). Price the actual unit mix, not an average.
Non-residential charges apply only to ground-floor space. Retail at grade in a residential building attracts $805.64 per square metre; office floors above it don’t attract the City’s non-residential charge. That line is often smaller than owners expect, and due earlier.
Council removed indexing for 2025 and 2026, which is why these rates haven’t moved since June 2025.
The reduced rates, and why you can’t count on them yet
In July 2026 Council adopted an amendment to the development charge by-law (Bill 1268, item CC43.9) that sets “time limited decreases” for residential development (City of Toronto, Bill 1268). The decreased amounts include:
| Unit type | Current rate | Reduced rate | Reduction |
|---|---|---|---|
| Non-rental single or semi | $137,846 | $55,138 | 60% |
| Non-rental apartment, 2+ bedrooms | $80,690 | $32,276 | 60% |
| Non-rental apartment, 1 bedroom or bachelor | $52,676 | $31,606 | 40% |
| Rental apartment, 3+ bedrooms | $45,280 | $18,112 | 60% |
| Rental apartment, 2 bedrooms | $48,299 | $19,320 | 60% |
| Rental apartment, 1 bedroom or bachelor | $33,497 | $20,098 | 40% |
The reductions apply only if every condition in the by-law’s Schedule D is met:
- The Transfer Payment Agreement with Canada and/or Ontario has been fully executed.
- No building permit was issued for the development before March 30, 2026 (or any that were had been revoked before that date).
- The first building permit is issued between March 30, 2026 and three years after the agreement takes effect.
- The first above-grade permit is issued by the later of three years after the agreement takes effect and 24 months after the first permit.
- That above-grade permit isn’t revoked before occupancy.
Whether the conditions were met is confirmed at occupancy. If you paid early and they weren’t, the difference is due at occupancy. The by-law also says the full rates still apply for the purpose of the section 26.2 freeze, so the frozen amount is the full rate, and the reduction is applied on top if you qualify.
As of November 3, 2026, the City’s development charges page still says the program is “subject to a Transfer Payment Agreement with the Province of Ontario” and that “additional information will be available once the Agreement is received.” Budget at the current rates and carry the reduction as a separate line you can release once the agreement is signed and your permit dates fit inside its window.
The same amendment removes indexing in 2027, 2028 and 2029, with indexing resuming May 1, 2030. That part isn’t tied to the agreement.
Education development charges in Toronto
The City collects an education development charge on behalf of the Toronto Catholic District School Board. It rises every December 3 (City of Toronto, Education DCs):
| Period | Per residential unit | Non-residential, per sq. ft. GFA |
|---|---|---|
| Dec 3, 2025 to Dec 2, 2026 | $3,893 | $1.67 |
| Dec 3, 2026 to Dec 2, 2027 | $4,193 | $1.77 |
| Dec 3, 2027 to Dec 2, 2028 | $4,493 | $1.87 |
It’s payable at the first building permit for above-ground construction, not at occupancy, so it isn’t moved by the Bill 17 changes. On a project whose above-grade permit straddles December 3, a few weeks can change the line.
Multiplexes, suites and the City’s deferral programs
Since July 24, 2025, Toronto exempts the second to sixth units in developments of up to six units, where the Act doesn’t already exempt them (City of Toronto, DC overview). On a new fourplex or sixplex, that usually leaves only the first unit’s charge. Our guide to building a multiplex in Toronto prices every government charge on one.
Additional units in a house are exempt under the Act, and the City runs a deferral program for laneway and garden suites; our garden suite cost guide covers that side.
Where you’re replacing an existing building, Toronto gives a credit for the units or ground-floor non-residential space demolished, provided the demolition permit was issued within 60 months (for dwelling units) or 36 months (for non-residential floor area) before a complete building permit application for the new development (Municipal Code Chapter 415). If you’re buying a site with buildings on it, ask when they’ll come down and keep inside that window.
Freezes, instalments and exemptions in practice
The freeze is set by your last application, and it can lapse
Under section 26.2, the charge is fixed at the rate on the day of a complete site plan application. If there’s no site plan application, it’s the day of the zoning by-law amendment application. If there’s more than one of either, the later one counts. In practice the site plan application usually sets the rate, even when the rezoning came first. Our guides to site plan control and the zoning by-law amendment explain when each application is filed.
The freeze lasts only if the first building permit is issued within 18 months of the application being approved. Miss that and the charge is whatever the by-law says on the day it’s payable. Since June 5, 2025, you pay the lower of the frozen amount (plus any interest) and the current one, so a lapse can no longer cost you a rate cut. It can still cost you a freeze that was protecting you from an increase.
The municipality may charge interest on frozen charges from the application date, at no more than the average prime rate of the big five banks plus one percentage point. Toronto’s overview page says that, following a letter from the Minister dated November 28, 2025, the City stops accruing that interest on the date the building permit is issued. Ask your municipality what rate and period it uses, because on a long approval the interest can be a real number.
Paying at occupancy and in instalments
Since November 3, 2025, a condominium or other non-rental residential project pays its development charges in full at the earlier of the occupancy permit and first occupation. Rental and institutional projects pay in six equal annual instalments starting at the same point, and no interest accrues on those instalments after November 3, 2025.
A section 27 agreement with the municipality can set different timing and prevails over the statutory schedule. The Act also lets a municipality require security for a non-rental charge payable at occupancy, but only in circumstances a regulation prescribes.
Exemptions need paperwork before the permit
The statutory exemptions aren’t automatic. An affordable unit is exempt only if the owner signs an agreement with the municipality to keep it affordable for 25 years, measured against the rents and prices in the Province’s Affordable Residential Units bulletin, and that agreement can be registered on title. Non-profit housing must be developed by a non-profit corporation or co-operative whose primary object is housing. The attainable unit exemption has the definition in the Act but needs the development to be of a prescribed class, so check the current regulation before you count on it.
Raise any exemption early: the municipality calculates the charge when the permit is issued, and that’s the time to have it recognized.
Parkland and the community benefits charge
These two aren’t development charges: they’re valued from the land, not counted per unit, and they’re paid at or before the first building permit. Our hard costs vs soft costs article covers both as budget lines.
Parkland dedication and cash in lieu
Under section 42 of the Planning Act, a municipality can require land for parks, or a payment instead, of up to 5% of the land for residential development and 2% for commercial or industrial. A by-law can set a higher alternative rate based on units, capped at 10% of the land or its value on sites of five hectares or less and 15% on larger sites. The requirement is frozen at the site plan (or rezoning) application, like development charges, but that freeze lapses if more than two years pass from approval to the first permit, not 18 months (s. 42(2.4)). The land is valued as of the day before the first building permit.
In Toronto, the alternative rate applies only in the City’s Parkland Acquisition Priority Areas, the payment is set by the City’s own appraisal (four to eight weeks after the permit application), and it’s due before the first above-grade permit (City of Toronto, Parkland Dedication).
Community benefits charge
The community benefits charge applies to buildings of at least five storeys with at least ten residential units (Planning Act, s. 37), capped at 4% of land value as of the day before the first building permit (O. Reg. 509/20, s. 3). Toronto levies the full 4% under By-law 1139-2022 and collects it when the building permit is issued, or as an in-kind contribution if Council accepts one (City of Toronto, Community Benefits Charge).
Together they can reach 14% of land value on a small Toronto site, and both are financed for the whole construction period.
Estimating development charges for your site
The arithmetic below is ours, using the published schedules. It’s a way to test a site, not a quote: the municipality calculates the actual charge at permit. The building is hypothetical: an 80-unit Toronto mid-rise with 30 one-bedroom, 40 two-bedroom and 10 three-bedroom apartments, no existing building to credit and no exempt units.
Step 1: price each tenure at current and reduced rates
Count units in the by-law’s own categories (Toronto by bedrooms, York by floor area), then price them.
| Scenario | Arithmetic | Total | Per unit |
|---|---|---|---|
| Condominium, current rates | 30 × $52,676 + 50 × $80,690 | $5,614,780 | about $70,200 |
| Condominium, reduced rates | 30 × $31,606 + 50 × $32,276 | $2,561,980 | about $32,000 |
| Rental, current rates | 30 × $33,497 + 40 × $48,299 + 10 × $45,280 | $3,389,670 | about $42,400 |
| Rental, reduced rates | 30 × $20,098 + 40 × $19,320 + 10 × $18,112 | $1,556,860 | about $19,500 |
For the condominium, the gap between current and reduced rates is $3,052,800. For the rental version it’s $1,832,810. That’s the size of the line that turns on a signed agreement and your permit dates.
Tenure matters as much as the reduction. At current rates the same building costs about $2.2 million less in City development charges as rental than as condominium, and it pays later: the condominium pays $5.6 million at occupancy, while the rental pays $564,945 a year for six years starting at occupancy.
Step 2: add the other layers
- Education development charge: 80 × $4,193 = $335,440 if the above-grade permit is issued between December 3, 2026 and December 2, 2027, or $311,440 at the rate before that.
- Non-residential space: if the ground floor had 400 m² of retail, 400 × $805.64 = $322,256, due at the first permit.
- Parkland and the community benefits charge: from your land appraisal, at the percentages above. If it is five storeys or more, an 80-unit building is over the community benefits charge thresholds.
Outside Toronto, add the regional layer. For comparison only, the same 30 one-bedrooms (if each is under 700 sq. ft.) and 50 larger units (if each is 700 sq. ft. or more) would carry York Region’s charge of 30 × $37,202 + 50 × $58,721 = $4,052,110, before the local municipality’s and school boards’ charges.
Step 3: put each charge on its date
| Charge | When it’s due | What the lender sees |
|---|---|---|
| Parkland cash in lieu | Before the first above-grade permit (Toronto) | Equity or an early draw |
| Community benefits charge | At the building permit | Equity or an early draw |
| Education development charge | At the first above-grade permit | Equity or an early draw |
| Non-residential development charge | At the first building permit | Equity or an early draw |
| Non-rental residential development charge | At occupancy | Funded from closings, or a late draw |
| Rental and institutional development charge | Six annual instalments from occupancy | Carried in the operating pro forma, after the construction loan |
A charge paid at occupancy isn’t financed through construction, and an instalment paid from rents may never touch the construction loan. Our guide to construction financing in Ontario explains how lenders treat soft costs and draws.
What can go wrong
- The freeze lapses. The first permit comes more than 18 months after site plan approval. Track the approval date and the permit target together, and talk to your permit team about a conditional permit if the gap is getting close. Parkland has its own two-year clock.
- The reduced rates’ conditions aren’t met. A permit issued before March 30, 2026, an above-grade permit that comes too late, or a revoked permit can all take the reduction away, and the difference is due at occupancy.
- The unit mix changes after the freeze. The frozen rate applies per unit type, so converting two-bedrooms to one-bedrooms or the reverse changes the total. Re-run the arithmetic every time the unit schedule changes.
- Tenure changes. Rental and condominium sit on different schedules and pay at different times. Check how your municipality treats a change before you decide.
- The demolition credit is missed. In Toronto, a demolition permit issued more than 60 months before a complete building permit application loses the credit for the units demolished, and for non-residential space the window is 36 months. On a site assembly that sits for years, that can be a large number.
- The charge is calculated wrong. You can complain to council that the charge was incorrectly determined or the by-law was misapplied, but only within 90 days of the day the charge, or any part of it, is payable (DCA s. 20). Check the City’s calculation against your own when the permit is issued.
Frequently asked questions
Who pays development charges in Ontario?
The owner or developer taking out the building permit pays. The charges go to the municipality (and the region, outside Toronto) under the Development Charges Act, and to qualifying school boards under the Education Act. On a pre-construction condominium, read the purchase agreement: it may pass some charges or later increases to buyers.
When are development charges paid in Toronto?
Non-rental residential charges are paid at the earlier of the occupancy permit and first occupation. Rental and institutional charges are paid in six equal annual instalments from the same date, without interest after November 3, 2025. Non-residential charges and the education development charge are paid at the first building permit, unless a section 27 agreement sets different timing.
Are development charges going down in Ontario?
In some places. Under the Canada–Ontario Development Charge Reduction Program, municipalities are being paid to cut residential charges by 30% to 50% or more for three years. Toronto has adopted reduced rates of 40% to 60%, but as of November 3, 2026 they wait on a signed Transfer Payment Agreement. Rates elsewhere move with each municipality’s own by-law, so check the current schedule for your site.
Do I pay development charges on a secondary suite or a fourplex?
A second or third unit in a house, and one unit in a garden or laneway suite, are exempt under the Development Charges Act, within the limits in section 2. In Toronto, the City also exempts the second to sixth units in developments of up to six units, so a new fourplex usually pays only the first unit’s charge. Education charges and other fees may still apply.
Where to start
Before you buy a site or commit to a unit mix, build the charges from the schedules in force today, with the date and the source beside each one: the municipal and regional development charges, the education charge, parkland and the community benefits charge. Then put each on its real payment date in the cash flow, and carry any reduction you’re hoping for as its own line with its conditions next to it. That exercise often changes what you can pay for the land.
This is the feasibility work we do in the first weeks of a project. If you’re testing what a site can carry before you buy it, we’ve built these budgets before and can tell you where the numbers on your site are likely to move. Talk to us through development management.