October 8, 2026 · Updated October 27, 2026
Toronto Multiplex Rules in 2026: Fourplex, Sixplex and Permits
Toronto lets you build a multiplex of up to four units on almost any residential lot in the city without rezoning, and up to six units in the Toronto and East York district and Ward 23 in Scarborough. A fourplex built within the zoning rules needs a building permit and nothing more from City Planning. Since July 2025 the City charges no development charges or parkland fees on the second to sixth units of a multiplex on one lot. Whether a multiplex in Toronto works on your lot comes down to the zoning detail, the permit, who designs it, what it costs beyond construction and how long it takes before rent comes in.
Every rule and fee below was checked against City of Toronto and Ontario sources in October 2026 (the zoning and permit steps on October 26). It isn’t legal or tax advice.
What Toronto allows for a multiplex
A multiplex, in the City’s words, is a building with “2 to 6 homes (dwelling units) in one residential building” (City of Toronto, Multiplex Housing). Council permitted multiplexes of up to four units city-wide in May 2023 through By-law 474-2023, and in June 2025 it adopted a further round of changes for duplexes to fourplexes (By-law 648-2025) and permissions for fiveplexes and sixplexes in Toronto and East York and the northern part of Scarborough that makes up Ward 23 (By-law 654-2025) (City of Toronto, By-law 654-2025).
You can convert an existing house, add to it, or demolish and build new. The City’s monitoring of the first 18 months found 452 multiplex permits issued, and 75% of them were for renovations, conversions or additions rather than new buildings (City Planning presentation to the Planning and Housing Committee, June 12, 2025).
| Duplex to fourplex | Fiveplex and sixplex | |
|---|---|---|
| Where | All R, RD, RS, RT and RM zones, city-wide | Toronto and East York district and Ward 23 only, for now |
| Height | At least 10 m, or the zone’s limit if higher | Up to 10.5 m where the lowest level is a partly raised unit meeting the by-law’s tests |
| Building depth | 17 m, or 19 m on qualifying deep lots | Multiplex standards for the zone apply |
| Floor space index | Doesn’t apply, unless a Chapter 900 exception says otherwise | Same |
| Parking | None required | None required |
| Bedrooms | Building total of 3 × units for 3+ units (4 × units in a duplex) | 3 × units |
| Development charges | $0 on units 2 to 4 | $0 on units 2 to 6 |
Sources for the table: the City’s considerations when building multiplexes, By-law 654-2025, By-law 648-2025 and the City’s multiplex monitoring final report of May 29, 2025.
Fourplex rules across the city
The multiplex rules borrow the built form of a detached house in the same zone. Where the zone allows less than 10 m of height, a multiplex gets 10 m so a third storey works. Setbacks are the same as for any other residential building in the zone. The floor space index limit (the “d” number in a zone label) doesn’t apply to multiplexes.
The June 2025 by-law added a cap on bedrooms in all five residential zones. A building with three or more units can have three times as many bedrooms as units, so twelve across a fourplex however you split them, with a bachelor counted as one. A duplex gets four per unit (By-law 648-2025).
Where sixplexes are allowed
Five and six units are permitted in the Toronto and East York district, as its boundary stood on June 26, 2025, and in the area bounded by Steeles Avenue, Neilson Road and the Rouge River, Highway 401 and Midland Avenue. A fiveplex or sixplex has to be a detached building on one lot, and no part of a semi-detached house or townhouse can be converted to one. The areas may widen, so check the City’s multiplex page before you buy on the strength of a sixth unit.
A fiveplex or sixplex can go to 10.5 m if its lowest level is partly raised. The bottom of that level’s ceiling joists has to sit between 1.0 and 1.5 m above grade, with at least 2.4 m of headroom, both over 80% of the floor, and the level has to contain a dwelling unit.
Rules that can still catch you
Two things override the general rules. Chapter 900 exceptions are site- or area-specific rules, often stricter, that prevail where they conflict. Of 290 multiplex variance applications the City reviewed, 40 involved one of these exceptions (multiplex monitoring final report). And any work that could injure or remove a private tree 30 cm or more in diameter needs a permit under the Tree Protection By-law (City of Toronto, considerations when building multiplexes).
Multiplex zoning in North York, Etobicoke and the other former municipalities
Before amalgamation in 1998, the old City of Toronto, North York, Etobicoke, Scarborough, York and East York each had their own zoning by-law. Most of the city is now under the city-wide Zoning By-law 569-2013, but the City says some properties “remain subject to one of the comprehensive zoning by-laws of the pre-amalgamation municipalities,” and shades them grey on its interactive zoning map (City of Toronto, Zoning By-law 569-2013, page modified September 28, 2026).
By-laws 474-2023, 648-2025 and 654-2025 are each written as amendments to 569-2013, so the multiplex standards above are 569-2013 standards, and the City’s multiplex pages don’t say how they apply on a grey lot. What does apply everywhere is the Planning Act: no zoning by-law can prohibit three units in a detached house, semi or rowhouse on urban residential land, or two in the house and one in a garden or laneway suite (Planning Act, s. 35.1).
Search your address on the City’s map. A 569-2013 zone label (RD, RS, RT, R or RM) means the rules above apply. If the lot is grey, ask Toronto Building which by-law governs a fourth unit there before you pay for drawings.
Is your lot a multiplex candidate?
Before you buy or spend on design, work through this list.
- Zone and exceptions. Find the zone label on the City’s interactive zoning map and check for a Chapter 900 exception. A multiplex needs an R, RD, RS, RT or RM zone; a grey lot is under a former municipal by-law (above).
- Lot width and depth. Width decides how much of the side yard setbacks you lose and whether a side entrance or walkway fits. Depth decides whether you get the 19 m building depth.
- What’s there now. A sound structure and foundation can carry three or four units; a tired one becomes a demolition, which is a different budget.
- Trees. A large tree on your lot, a neighbour’s lot or the City boulevard can fix where the building and its foundations go. Have an arborist look early.
- Water and sewer. A fourplex may need a larger water service, and the City has flagged wet-weather sewer capacity where multiplexes cluster on combined sewers.
- Hydro. Toronto Hydro expects most fourplexes to need a 400-amp service, delivered underground (multiplex monitoring final report). More than that usually means a transformer on your property, and meter clearance on a tight side yard often pushes meters to the front wall. Call Toronto Hydro early.
- Heritage and ravines. Heritage status and the ravine protection area bring their own approvals. Near a railway, ravine or other water feature the City can also require site plan control, and with it the Toronto Green Standard.
- Tenants. If the house has tenants and the work needs them to move out, Toronto’s Rental Renovation Licence By-law applies (more below).
- Semi-detached lots. One half of a semi can be converted, but the City found new semis with five or more units across both halves going to the Committee of Adjustment.
The cheapest way to test a lot is a zoning review on early drawings, before you design in detail. The permit steps below give the 2026 fees.
As of right, a variance, and the building permit
Most multiplexes go straight to a building permit. Of 222 multiplex permits the City reviewed in detail, 90% needed no minor variance; the rest mostly asked for a narrower side yard, and height variances ran from 0.2 m to 1 m. Of 290 variance applications for duplexes to fourplexes from May 2023 to April 2025, 72% were approved and 10% refused (City of Toronto, multiplex monitoring final report).
A variance is worth it when small relief buys a usable third floor or a fourth unit. It adds a fee, notice, a hearing and a 20-day appeal window. On our reading of the 2026 schedule a fourplex pays the “all other” fee of $6,485.59, since the lower rates are for three units or fewer (City of Toronto, Committee of Adjustment fees). A 2025 provincial change also allows building up to 10% into a required setback without a variance on most urban residential land outside the Greenbelt (Environmental Registry of Ontario, 025-0463, decision November 24, 2025). Our guide to the Committee of Adjustment in Toronto covers the tests and the timing.
Ask your designer for the scheme with no variances first, then for what each variance would add, and decide from there whether the hearing is worth the time.
Getting a multiplex building permit in Toronto
Converting a house to a fourplex needs a building permit, and so does any new multiplex. The order runs like this, with the City’s 2026 figures:
- Zoning Applicable Law Certificate. Toronto Building checks your drawings against zoning and other applicable law, with up to three reviews, for $644.38 on a house conversion or addition, $888.14 for another building up to 300 m² and $1,863.82 above that. File the permit with the City’s declaration form and that fee comes off the permit fee (City of Toronto, Zoning Applicable Law Certificate, modified October 15, 2026). Without an issued certificate the City treats a permit application as incomplete, with no review time frame (City of Toronto, Building Permit Review Streams, modified June 26, 2026).
- Committee of Adjustment, only if the certificate shows a variance.
- The application. For a conversion: a site plan with a zoning summary, floor plans, sections and construction details, the designer form (Schedule 1), the Rental Renovation Licence screening form and a plumbing data sheet, plus the tree declaration and road damage deposit where they apply (City of Toronto, Multiplex Conversion guide, modified July 14, 2026). On a new build, the demolition application follows the new building’s (City of Toronto, Residential Demolition Permit with Replacement Building).
- Review. A duplex is in the House Stream, where complete applications are reviewed within 10 business days. A Part 9 triplex to sixplex is in the Small Building Stream, at 15. A Part 3 building is in the Large/Complex stream, at 20 or 30 (Review Streams). Each round of examiner comments adds time.
- Fees. In 2026, $18.56 per m² of new residential floor area, $11.53 per m² of interior alteration on a conversion, and $56.33 per new unit, with a $214.79 minimum. No permit is issued until all fees and charges are paid (City of Toronto, Building Permit Fees, modified June 19, 2026).
Our laneway house guide runs through the same sequence for a suite at the back of the lot.
Who designs and builds a multiplex
Part 9 or Part 3 of the Building Code
Ontario’s Building Code (O. Reg. 163/24) puts a residential building of three storeys or fewer with a building area (footprint) of 600 m² or less under Part 9, the part that covers houses. Anything larger is Part 3, with more demanding fire protection and exits and, in practice, elevators.
Almost every multiplex is Part 9: the City’s monitoring found a single four-storey multiplex in its permit data.
Part 9 still asks more of a multiplex than of a house: fire and sound separations between units, separate exits, and limits on windows near a side lot line. A 0.9 m side yard can cost you the windows on that wall, so plan bedrooms with that in mind.
Architect, BCIN designer or Licensed Technologist
Who can legally design your multiplex depends on its gross area, which under the Architects Act is the total area of all floors above grade.
| Building | Who can design it |
|---|---|
| Residential, up to 3 storeys, over 600 m² gross area | An architect (Architects Act, s. 11(4)) |
| Residential, over 3 storeys | An architect and a professional engineer |
| Residential, up to 4 storeys, three or more attached units, up to 600 m² building area | A Licensed Technologist OAA can also design it (OAA) |
| Part 9 residential, up to 600 m² gross area | A designer registered under the Building Code (a BCIN designer qualified in the Small Buildings category), an architect or an engineer; the permit application asks you to name which |
A three-storey fourplex on a 200 m² footprint is already at 600 m² above grade (a fully below-grade basement doesn’t count), so measure before you hire. You’ll also need a structural engineer, a mechanical designer, a surveyor and often an arborist.
Toronto’s pre-approved multiplex plans
The City now offers free pre-approved plans for four-unit and six-unit multiplexes, in narrow and wide versions, designed by LGA Architectural Partners. The fourplex comes with electric, gas or hybrid heating and the sixplex with electric or hybrid (City of Toronto, Pre-Approved Multiplex Building Plans). Permit fees still apply, changing the plan takes it out of the pre-approval, and you still need professionals for grading, foundations, structure and mechanical. On a lot that suits one, they shorten design and review.
What to ask a multiplex architect or designer
Put these to every designer you interview, before you sign a design contract.
- Can you legally design this building, and under which registration? Check the answer against the table above.
- Will this be a Part 9 or a Part 3 building, and have you designed under both? You want to hear what a fourth storey or a bigger footprint would do before you’re attached to it.
- Which multiplexes have you taken through Toronto Building’s review, and how many rounds of examiner comments did they need? Ask for addresses, and ask what the comments were about.
- Will you prepare the Zoning Applicable Law Certificate application and answer the zoning examiner? If not, find out who will.
- If the scheme needs a variance, who prepares the Committee of Adjustment application and attends the hearing? Some designers do it themselves; others bring in a planner on a separate fee.
- What’s in your fee and what isn’t? Structural and mechanical design, the survey, the arborist, revisions after permit comments and site visits during construction are the usual gaps. Get the exclusions in writing.
The builder, and who runs the project
Multiplexes are mostly built by small and mid-sized residential builders, on a fixed price once drawings are complete or earlier on cost-plus or design-build. Our article on the budget that matters most explains why the first price you approve shapes everything after it.
On a multiplex you’re the developer: you hold the land, the loan, the permits and the schedule, and everyone comes to you for decisions. Decide before you sign anything whether you’ll do that yourself, hand it to a design-build contractor or hire someone independent.
The multiplex development budget
A builder’s quote covers construction; your budget also has to carry the land, the soft costs and the financing. We don’t publish a per-unit construction cost, because no current public source for Toronto multiplexes stands up and a conversion and a new build are far apart. What follows is the outline, with the government charges that can be priced exactly.
The four parts of the budget
| Part | What’s in it | Who prices it |
|---|---|---|
| Land | Purchase price, land transfer taxes, legal fees, or the value of a lot you already own | Your lawyer and the market |
| Hard costs | Demolition, foundations, structure, envelope, interiors, mechanical and electrical, site work, utility connections | The builder, checked against an independent estimate |
| Soft costs | Design, engineering, survey, arborist, zoning review, permits, any variance, legal, insurance, development charges on the first unit, HST | Mostly fixed by fee schedules and quotes |
| Financing and contingency | Interest during construction, lender and appraisal fees, and a contingency for what can’t be priced yet | Your lender and your own judgement |
Government charges, priced
- Development charges. Toronto charges none on the second, third or fourth unit, and since By-law 845-2025 the fifth and sixth are reduced to $0, provided there are no more than six units on the lot (City of Toronto, By-law 845-2025). The first unit is the one that isn’t exempt; on a conversion that unit is the existing house. Where you’re replacing an existing house, the by-law credits the charge for the demolished unit if the demolition permit was issued within 60 months before your complete building permit application (Toronto Municipal Code, Chapter 415).
- Parkland. The second to sixth units are exempt from parkland dedication, or up to seven units where one is a garden or laneway suite. Council set this in July 2025 and corrected the wording in March 2026 (City of Toronto, By-law 269-2026).
- Education development charge. This one is the Toronto Catholic District School Board’s, under its own by-law, and the City’s exemptions don’t speak to it. The rate is $3,893 per unit to December 2, 2026 and $4,193 from December 3 (City of Toronto, Education Development Charges). Ask the examiner how it applies to your units.
- Building permit and variance. At the 2026 rates in the permit section above, a new 400 m² fourplex would be about $7,650 before plumbing, HVAC and other permit lines, as an illustration only. A variance adds $6,485.59 plus a planner and drawings for the hearing.
- Tenants. If the work requires an existing tenant to move out, you need a Rental Renovation Licence. The fee is $728 per unit in 2026, you apply within seven days of serving the N13 notice, and you offer temporary housing or rent-gap payments plus a $1,500 or $2,500 moving allowance (City of Toronto, Rental Renovation Licence, Information for Landlords). The Residential Tenancies Act adds its own rules, so talk to a lawyer before you serve anything.
HST: the line owners miss
If you build or substantially renovate a residential building and rent it out, the Excise Tax Act treats you as a builder who has sold the building to yourself at fair market value when the first tenant moves in, and HST is due on that value. The Canada Revenue Agency calls this a self-supply (CRA, Residential Real Property: Deemed Supplies).
The federal purpose-built rental rebate returns 100% of the GST (the federal part of HST) on a new building of at least four self-contained units, 90% held for long-term rent, started after September 13, 2023 and before 2031 and finished before 2036 (CRA, Purpose-built Rental Housing Rebate). Ontario matches it with an 8% rebate on projects started between September 14, 2023 and the end of 2030 and finished by the end of 2035 (Ontario, Building More Homes Faster). A new fourplex can qualify; a triplex can’t. The CRA lists substantial renovations as ineligible, so a conversion generally won’t qualify even where self-supply applies. Bring an accountant in at the feasibility stage.
Selling the units instead
Selling units means a builder licence from the Home Construction Regulatory Authority, Tarion enrolment before construction starts (Tarion, Qualification for Enrolment process) and condominium registration, which industry told the City costs over $80,000 for a multiplex. Decide before design.
Financing and contingency
A fourplex is usually financed as a residential property of up to four units; at five and up, CMHC programs such as MLI Select come in, which the City’s report names as a reason the fifth unit matters. Our guide to construction financing in Ontario covers how draws, holdback and a lender’s cost review work. A conversion needs a larger contingency than a new build, because more is unknown until the walls are open; our article on how much contingency is enough sets out how to size it.
For the income side, the City’s 2025 report found multiplex units renting at an average of $2.93 per square foot, from listings and owner data gathered between 2023 and 2025. Use it as a starting point and test it against rents on your own street.
The multiplex schedule from idea to tenants
A simple conversion and a new build with a variance take very different times, so we give the phases rather than one number:
- Feasibility. Survey, arborist, a first read on servicing and hydro, and a budget with every line above in it.
- Design and zoning certificate. Concept, permit drawings, structure and mechanical. A pre-approved City plan can shorten this if your lot fits one.
- Committee of Adjustment, if needed. The City reported complete applications reaching a hearing in under six weeks in 2025 (City of Toronto, May 28, 2026 report), then a 20-day appeal period.
- Building permit. 10 or 15 business days a review on a complete application, plus each round of comments.
- Tenants, if any. The Rental Renovation Licence needs the permit in hand, so this follows it.
- Pricing and contract. Compare quotes on the same basis; our guide to reading a construction estimate helps.
- Utilities. Apply early for water and hydro; Toronto Water and Toronto Hydro set their timing.
- Construction and inspections.
- Occupancy and lease-up. Loan interest runs until the units are leased.
As on larger projects, most of a fourplex’s schedule risk sits in the approvals and decisions before construction starts. Our article on what developers get wrong about schedules covers how to plan for it.
Frequently asked questions
What is a multiplex in Toronto?
A residential building on one lot with two to six dwelling units, at least one of them partly or entirely above another. A house with a secondary suite is not a multiplex under the by-law.
Do you pay development charges on a fourplex in Toronto?
Not on the second to sixth units, as long as there are no more than six on the lot. The first unit isn’t exempt, but where you replace an existing house, a demolition permit issued within 60 months before your complete permit application earns a credit. The school board’s education charge is separate.
Do I need an architect to build a fourplex?
Over three storeys or 600 m² of gross area above grade, you need an architect, or a Licensed Technologist OAA within that licence’s limits. Below that, a designer qualified under the Building Code in the Small Buildings category, a Licensed Technologist OAA, an architect or an engineer can generally design it.
Can I build a fourplex and a garden suite on the same lot?
Yes. Since July 2025 a suite under the City’s development charge deferral program doesn’t count toward the six-unit total for the charge exemption (By-law 845-2025), and parkland is exempt for up to seven units where one is a garden or laneway suite. Our guides to garden suite costs and laneway houses cover the suite itself.
Do I need a permit to convert a house to a fourplex in Toronto?
Yes. A conversion needs a building permit, and the City treats an application as complete only with an issued Zoning Applicable Law Certificate, which costs $644.38 for a house conversion in 2026. A triplex or fourplex within Part 9 goes in the Small Building Stream, where complete applications are reviewed within 15 business days. You’ll need a variance first only if the design breaks a zoning rule.
Where to start
Spend first on the lot, not the drawings. A survey, the trees, the servicing, an early zoning read and a budget that names every line, HST and the first unit’s charges included, tell you whether the project works. Then pick the team and decide who runs the project on your side.
We haven’t delivered a multiplex as a firm. Our 20+ years and $3B+ of delivered work were built at PCL Constructors and Oxford Properties on larger residential, office, retail and industrial projects, and the disciplines carry over: a line-by-line budget, approvals planned as their own phase, quotes compared on the same basis, and cost and schedule tracked through the build. If you’re weighing a multiplex and want an experienced hand on the feasibility, the budget and the team, our development management service is where to start.