The OAA 600 Architect Agreement in Ontario, Explained for Owners

OAA 600 is the Ontario Association of Architects’ standard form of contract between a client and an architect. The current edition is OAA 600-2021 A (the A is for architects), and the 2013 edition you may still see quoted was withdrawn from use in June 2023. The contract sets what the architect will do, how the fee is calculated, what counts as extra, who owns the drawings, how invoices are paid and how either side can end the arrangement. Many owners read the fee and sign. The parts that decide how the relationship goes are the services schedules, the budget clause and the list of things that count as extra services, and they’re worth an hour of your time before the first drawing.

Clause numbers below come from the OAA’s published contract (Version 1.2, March 2023) and its guide, read on November 11, 2026. Check the OAA’s contract page on the day you sign, because the OAA says an update is under way.

What OAA 600 is, and which version you’re signing

The OAA publishes a family of standard contracts for its members and their clients. Its Index to OAA Contracts and Guides (Version 6.3, July 2025) lists what’s current:

DocumentWhat it’s forCurrent version
OAA 600-2021 ALong form contract between a client and an architectV1.2
OAA 600-2021 LTThe same contract for a Licensed Technologist OAAV1.3
OAA 800-2021Short form contract for less complex projects, derived from OAA 600A V1.1, LT V1.2
OAA 900-2021Subcontract between the architect and its sub-consultants (structural, mechanical, electrical and others)A V1.1, LT V1.2

The index notes that the 2021 suite was revised for CCDC 2-2020 and changes in the law, and that “older versions of the contracts have been withdrawn from use as of June 2023.” If an architect sends you a 2013 form for a new project, ask for the 2021 one.

The 2021 contract is a locked PDF. Every change the two of you agree goes into Schedule 5 (Other Terms and Conditions), so you can see exactly where your contract departs from the standard. The services sit in schedules: Schedule 2 lists Basic Services and Schedule 3 Additional Services, each item marked as included, not included, by the client or to be decided, with a fee reference beside it. The OAA 600-2021 Guide says lawyers for both clients and architects reviewed the 2021 edition “with the aim of developing a balanced contract.”

The January 2026 Construction Act changes

Amendments to the Construction Act came into force on January 1, 2026. The OAA’s contract page (last updated January 27, 2026) says they affect “both contracts for professional services and construction” and that “work is underway to update the OAA Contracts Suite and guides to reflect these changes.” Until a revised edition is published, the 2021 form is the one in use; the holdback section below covers the clause most likely to need a Schedule 5 amendment.

OAA 800, OAA 900, RAIC Document Six and CCDC 15

OAA 800-2021 is the short form. The OAA’s index describes it as for “less complex projects,” and the guide suggests it where the long form isn’t appropriate. It uses the same schedules.

OAA 900-2021 is the architect’s contract with its own sub-consultants. You don’t sign it, but OAA 600 requires the architect to obtain licences from them so your right to use the drawings covers their work too (GC08.6.4).

RAIC Document Six is the Royal Architectural Institute of Canada’s national form; British Columbia publishes a guide to its 2022 edition (version 2, November 2024) for provincially funded projects. In Ontario, OAA 600 is the usual form.

CCDC 15 is the contract between a design-builder and its consultant, reissued in 2026 alongside CCDC 14; your contract is with the design-builder, as our CCDC 14 design-build guide explains. The OAA’s Practice Tip PT.25 (November 2024) offers a modified OAA 600 as “the Association’s recommended alternative to CCDC 15.” Our comparison of design-build and design-bid-build covers how the architect’s role changes.

What’s in the contract

OAA 600 has five parts. A27 sets the order of priority if they conflict, with your Schedule 5 amendments at the top.

PartWhat it setsWhat to check
Agreement (A01–A32)Parties, project, budget, dates, delivery method, insurance, fees, rates, retainer, invoicing, interest, holdbackEvery blank is filled in, and the numbers match what you discussed
DefinitionsBasic, Additional and Extra Services, Construction Cost, General Review, Proper Invoice, Ready-for-TakeoverHow “Construction Cost” is defined, if the fee is a percentage
General Conditions (GC01–GC18)Each side’s duties, extras, budget, construction phase, copyright, liability, suspension, termination, payment, disputesFixed text; changes go in Schedule 5
Schedules 1–5Fee legend, Basic Services, Additional Services, Other Services, amendmentsEach service is marked, and the fee reference is right
Appendices A and BRelease of editable CAD or BIM files; waiver of moral rightsWhether you need either, and on what terms

The blanks you fill in

Several set the baseline later changes are measured against.

Your responsibilities as client

GC05 asks for a clear statement of what the building has to do (the “Functional Program”), a current budget, one named person who speaks for you, timely decisions, signatures and fees for permits, your own legal and insurance advice, and your own consultants on compatible terms. On the single representative, the guide is blunt: “It is not uncommon to experience major redesign and substantial delays when several individuals with disparate views officially represent the client.” If your project answers to a board or a family, choose that person before you sign. GC05.3.10 also asks you to “generally accept the Architect’s professional judgement,” which the guide ties mainly to life safety, code and zoning.

The budget clause

GC06 is the clause owners most often misread. The architect’s estimates are its judgement as a design professional, and the contract says plainly that the architect “cannot and does not warrant or represent that bids or negotiated prices will not vary” from them (GC06.1). What the clause does is set out what happens when the numbers come in high:

  1. Before tender, if the architect’s estimate exceeds your budget, it recommends adjustments to the budget, size or quality (GC06.2).
  2. If bids come in over budget but within the Permitted Budget Exceedance, you can raise the budget, ask for redesign or rebid; the architect’s help is an Extra Service (GC06.5).
  3. If bids exceed the Permitted Budget Exceedance, you choose to raise the budget, redesign, rebid or abandon the project (GC06.6). Unless the overrun came from extraordinary market conditions or something the architect couldn’t foresee or control, you can require the redesign to bring it back within the limit at no extra fee (GC06.7).
  4. If tender is more than 90 days after the documents are complete, the agreed estimate is adjusted for price movement in the meantime (GC06.4).

The guide puts the “traditional” Permitted Budget Exceedance at up to 15%, and warns that pushing it to 10% or 5% tends to come back as a higher fee or a design drawn to 85% or 90% of your budget. Have the budget, plus the exceedance, plus contingency available before you start. The architect’s Basic Services estimate is Class D, from area or volume unit costs (Schedule 2, 2.1.7); detailed estimates are an Additional Service, and many owners use an independent cost consultant, whose estimate the architect may rely on (GC06.8). Our guides to how much contingency is enough and why independent estimates pay for themselves cover how to set those numbers.

The architect keeps the copyright in the drawings and specifications (GC08.1). You get an exclusive, royalty-free, perpetual licence to use them to build, use, maintain, renovate and add to this project (GC08.6.1), and to use renderings for marketing with credit (GC08.6.2). Three conditions matter:

Editable CAD or BIM files aren’t included: the contract’s electronic documents are PDFs, and editable files come under Appendix A. If you’ll want the model for facilities management or a future fit-out, mark it now.

Liability, insurance and lenders

The architect’s liability is capped at the professional liability insurance amount in A14.1 (GC09.3), claims must be notified within six years (GC09.10), and neither side is liable for consequential losses (GC09.12). The architect also isn’t required to prepare reliance letters or documents for your lender (GC09.6.6). If your lender will want them, write it into Schedule 5; our guide to construction financing in Ontario covers what lenders ask for at each draw.

Suspension and termination

You can end the contract for convenience on 28 days’ notice, or seven days’ if you abandon the project (GC11.3). Unless you’re terminating for the architect’s default or a force majeure event, you pay for services to date plus termination expenses, which include “10% of the value of the Services remaining” (GC11.9, 11.10). The architect can suspend on seven days’ notice if a proper invoice goes unpaid without a notice of non-payment (GC10.2), and terminate if the project is suspended for over 60 days (GC11.5).

Architect fees in Ontario under OAA 600

OAA 600 doesn’t set a fee. It gives you a set of methods, labelled in Schedule 1, and you mark each service in Schedules 2 to 4 with the method that applies.

Fee referenceHow the fee is calculated
F1Percentage of Construction Cost by phase, each set on the estimate agreed at that phase’s end (bid price for bidding, final cost for construction)
F2Percentage of final Construction Cost, invoiced on estimates and trued up at the end
F3Fixed fee for a defined scope
F4Hourly rates by staff level, common for early studies and Extra Services
F5Unit rates, per task or per visit

Under F1 and F2, the work of making a change that lowers the cost is paid hourly (Schedule 1), which is worth knowing before value engineering; our guide to value engineering without wrecking the building covers when it pays.

How the fee is spread across the phases

A19 apportions a percentage or fixed fee across the phases, which sets how much you pay as each phase is delivered. The OAA guide gives the normal range and typical split as of 2022:

PhaseNormal range (CAD)Typical (CAD)Typical (BIM/IPD)
Pre-designvariesvariesvaries
Schematic design12–18%12.5%20%
Design development12–18%12.5%25%
Construction documents45–50%50%30%
Bidding or negotiating2.5–6.5%2.5%2.5%
Construction22.5–35%22.5%22.5%

Source: OAA 600-2021 Guide, A19. Roughly half the fee goes on the construction documents, so if approvals are uncertain, the split tells you what you’ll have spent before that point.

What drives the fee

We don’t quote a percentage because no current published Ontario figure applies across project types. The RAIC’s free Guide to Determining Appropriate Fees for the Services of an Architect (2019) explains how architects price, and OAA 600’s Basic Services schedule lines up with it. What moves the fee:

Around the fee sit reimbursable expenses with an administrative charge (A20), a mileage rate (A21) and a retainer (A22), which is credited to the final invoice and is the minimum you pay if the project is cancelled. Hourly rates rise each anniversary with Statistics Canada’s residential construction price index for Toronto (Table 18-10-0135-02), and rates for helping you in a dispute with a contractor default to 200% (A18).

Basic, additional and extra services

OAA 600 sorts every service into three groups. Basic Services (Schedule 2) are the core design and contract administration. Additional Services (Schedules 3 and 4) are known at signing but priced separately. Extra Services (GC04) are anything not anticipated at signing; the architect must tell you in writing and can’t proceed without your written authorization (GC04.1).

ServiceWhere it sits in OAA 600-2021 A
Design from program review to construction documents, with Class D estimatesBasic (2.1.1–2.1.17)
Building permit application and responses to examiner commentsBasic (2.1.18–2.1.21)
Prequalification, tendering and the construction contractBasic (2.1.22–2.1.23)
General review, site meetings, payment certificates, shop drawings, RFIs, change ordersBasic (2.1.25–2.1.35)
Substantial performance, close-out, takeover, warranty reviewBasic (2.1.37–2.1.41)
Pre-design study, existing building assessment, programming, measured drawingsAdditional (Schedule 3, .1–.6)
Detailed estimates and quantity surveys; value engineeringAdditional (.11–.12, .23)
Interior design, furniture and equipment, signage, tenant layoutsAdditional (.14–.18)
Marketing materials, models, renderings, photographyAdditional (.19–.21)
Editable CAD or BIM files; waiver of moral rightsAdditional (.24–.25)
Rezoning, Committee of Adjustment, site plan approvalAdditional (.26)
Multiple bid packages, phases or contracts; full-time site representationAdditional (.28, .30, .33–.34)
Record drawings, commissioning, help with notices of non-payment and disputesAdditional (.39–.42)

The schedules don’t name the Toronto Green Standard (see our Toronto Green Standard guide) or funding program reports such as the energy and accessibility documentation for CMHC MLI Select. If your project needs them, add them in Schedule 4.

What becomes an Extra Service

GC04.1 lists fourteen triggers. The common ones, in an owner’s words: you change something you’d already approved; the program, budget, size or schedule changes; you switch delivery method; a code changes or an examiner reads it unexpectedly; your decisions run late; the contractor sends unusual numbers of substitutions or RFIs not caused by unclear drawings; the project is delayed through no fault of the architect; or one of your own consultants doesn’t deliver. The guide says “minor changes in a project are considered normal and do not typically give rise to requests for extra fees.” Agree to record each extra on the OAA’s Standard Form for Extra Services or Contract Change, with a scope and fee signed before work begins.

The construction phase and general review

During construction the architect is your representative, with authority to pass your instructions to the contractor, reject non-conforming work, require testing and order minor changes that don’t affect cost or time (GC07.2). Under CCDC 2 it’s the Consultant who administers the contract for you; our guide to the CCDC 2 stipulated price contract shows how CCDC 2 describes that role.

On site the architect performs General Review: visits “at intervals appropriate to the stage of the construction” to determine whether the work is in general conformity with the documents, reported in writing. It’s sampling. The architect isn’t required “to make exhaustive or continuous on-site reviews” (GC09.6.1) and isn’t responsible for the contractor’s means, methods or safety (GC09.6.3). Schedule 2 offers limited review for life safety and code only (2.1.24) or full general review (2.1.25); full-time site representation is an Additional Service. Under the Architects Act, s. 11(4), rule 6, only an architect may carry out general review of a building built to an architect’s design.

A payment certificate says the work has progressed to that value, what was observed generally conforms and the contractor is entitled to the amount (GC07.3). It doesn’t say the architect checked how earlier payments were spent or the contractor’s WSIB standing (GC07.4). Certificates are due within 10 days of the contractor’s proper invoice (2.1.30), inside the Act’s 14-day window for disputing it; our article on the schedule of values walks through that monthly cycle.

Prompt payment, holdback and the architect’s invoices

The Construction Act’s prompt payment rules apply to your architect’s invoices too. The OAA’s Practice Tip PT.10.3 (December 2023) says prompt payment “applies equally to payments made under the construction contract and under the architectural services contract,” and the Act confirms architects have lien rights (s. 14(3)).

  1. The clock starts with a proper invoice. The Act sets its minimum contents; A23 lets you add requirements, and suggests the OAA Certificate of Payment and Distribution form with the second and later invoices.
  2. Day 14. If you dispute any part, give a notice of non-payment in the prescribed form, stating the amount and every reason (Construction Act s. 6.4(2)). The OAA says these deadlines are calendar days and can’t be extended by contract.
  3. Day 28. Pay everything not disputed, less any holdback (s. 6.4(1); OAA 600 A24). Interest runs from day 29 at the A25 rate or the Act’s rate, whichever is higher.
  4. Disputes. Either side can refer a payment dispute to adjudication (GC16.2).

You also can’t deduct amounts withheld from the contractor from the architect’s fees unless the architect is proven responsible (GC12.4), and a budget overrun isn’t grounds to withhold them (GC12.6).

Holdback on the architect’s fees

A24 has you pay each invoice “less any applicable statutory holdback,” the Act’s 10%. Since January 1, 2026, owners must release accrued holdback every year: publish a notice of annual release within 14 days after each contract anniversary, and pay 60 to 74 days later unless a lien has been preserved (s. 26(2)–(4)). A new s. 14(4) also means that if you hold back on design for a project that never starts, a lien is presumed unless you prove the design added no value to your land.

OAA 600-2021’s A26 was written for the earlier rules. It lets the parties name a design phase after which holdback is released, “where permitted by the Lien Legislation.” The optional annual and phased release sections it relied on, ss. 26.1 and 26.2, were repealed on January 1, 2026, and the mandatory annual release in s. 26 replaced them. Our reading is that the annual release now governs holdback on your architect’s contract as it does on the construction contract, and that A26 needs a look in Schedule 5. Ask your lawyer to confirm it until the OAA publishes its revision. Our guide to construction liens and holdback in Ontario covers the annual release step by step.

What to settle before you sign

Work through this with your architect and your lawyer. Each item should have an answer you can write down.

  1. The edition. OAA 600-2021 A (or LT), with every change in Schedule 5.
  2. Schedules 2 and 3, line by line. Every service marked X, C, NI or TBD, with a fee reference.
  3. Schedule 4 for anything missing, such as Toronto Green Standard or funding program reports.
  4. A budget in A06 you can fund, and a Permitted Budget Exceedance in A09 you understand.
  5. Dates in A07 you believe, since they set the baseline for extensions.
  6. The delivery method in A08, or how a change would be priced if you’re not sure.
  7. The consultant list in A11, split between the architect’s and yours.
  8. Site information in A12: who commissions the survey and reports, and when.
  9. Insurance limits in A14, set with your insurance advisor.
  10. Site reviews: how many are in the fee and the rate for more.
  11. The fee basis for each service and the A19 split.
  12. Appendices A and B if you’ll need editable files or will alter the building later.
  13. Lender requirements written into Schedule 5.
  14. Holdback and A26 checked by your lawyer against the 2026 Act.
  15. One representative, named in writing with authority to decide.

The OAA’s guide says disputes over extra fees are best avoided by “good management of the process, project, and client expectations,” not by rewriting the contract. Our five questions to ask before you sign apply to consultant contracts as much as construction ones.

Frequently asked questions

How much does an architect cost in Ontario?

There’s no single figure. The fee depends on construction cost, building type and complexity, new build or renovation, which engineers are included, the approvals path, delivery method and construction length. The RAIC’s free fee guide (2019) sets out how architects calculate percentage fees, and OAA 600 lets you choose a percentage, fixed or hourly fee for each service. Get two or three proposals priced against the same Schedules 2 and 3 so you can compare them.

Do I need an architect in Ontario?

Under the Architects Act, an architect is generally required for buildings over three storeys or 600 m² of gross area, and for assembly and institutional buildings of any size (s. 11(4)). Smaller residential, business, mercantile and industrial buildings are exempt (s. 11(3)(a)), as are houses and on-grade townhouses of up to three storeys (s. 11(3)(b)) and most interior alterations that don’t touch structure, fire separations or exits. Large industrial buildings can be designed by an engineer instead.

Who owns the drawings under OAA 600?

The architect keeps the copyright (GC08.1). You get an exclusive, perpetual licence to use the drawings to build, operate, maintain and alter this project, once the fees are paid (GC08.6 and 8.7). You can pass the licence to a future owner of the site on notice. Editable CAD or BIM files are released separately under Appendix A.

Where to start

Before you interview architects, write down what the building has to do, the budget you can fund and the dates you need, since those go straight into A06, A07 and Schedule 2. Then ask each architect for a proposal on OAA 600-2021 with the schedules marked up.

Setting the scopes and terms for the consultant team is part of the development and preconstruction work we do for owners, drawing on experience built at PCL Constructors and Oxford Properties across office, residential, retail and industrial projects. If you’d like an experienced hand to read the schedules with you before you sign, see how our development management service builds the development team.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada