Schedule of Values and Progress Claims for Ontario Owners

A schedule of values is the contract price broken into line items, each with a dollar value, that add up exactly to the price. Every monthly progress claim is measured against it: the contractor says how far along each line is, the consultant checks that against the site, and the owner pays the value earned since the last claim, less the 10% holdback. A clear schedule of values, agreed before the first claim, is how you make sure the money you pay each month matches the work in place.

Most of what you’ll find online about schedules of values is written for American contractors billing on AIA forms. This guide is for the Ontario owner or developer about to receive a first progress claim, or one whose claims have stopped adding up: how to set the schedule up, check each claim, and fit certification inside the Construction Act deadlines. It’s general guidance, not legal advice.

If you’ve come across US terms: an AIA G703 “continuation sheet” is the schedule of values, a G702 “pay application” is the application for payment, and “retainage” is roughly what Ontario calls holdback, although holdback here is set by statute rather than by the contract.

What a schedule of values looks like

A schedule of values is a table with one row per part of the work and a value against each row. The values come from the contractor’s own pricing: mostly its subcontract prices, plus its own forces, general conditions, overhead and fee spread across the lines. The total at the bottom has to equal the contract price.

Here is an example for a $5,000,000 (before HST) stipulated price contract for a small commercial building. The values are illustrative, made up for this article to show the structure, not data from a real project.

LineDescriptionValue ($)
01General conditions (site staff, temporary facilities, monthly)380,000
02Mobilization50,000
03Bonds and insurance60,000
04Demolition and site preparation120,000
05Concrete560,000
06Masonry180,000
07Structural steel450,000
08Carpentry and millwork250,000
09Roofing and waterproofing210,000
10Doors and frames, supply90,000
11Doors and frames, installation30,000
12Glazing340,000
13Drywall and ceilings400,000
14Flooring and finishes260,000
15Plumbing260,000
16HVAC520,000
17Electrical560,000
18Fire protection150,000
19Close-out documents (manuals, as-builts, warranties)30,000
20Cash allowances100,000
Contract price5,000,000

General conditions, mobilization and bonds have their own lines, door supply is split from installation, and close-out documents and cash allowances carry their own values. Each of those choices is explained below. On a real project the trade lines are often broken down further, by floor, area or material and labour. How fine to go is a judgment call, and the test is simple: can someone walk the site and say with reasonable confidence what percentage of this line is done?

What CCDC 2 – 2020 says about the schedule of values

Most Ontario stipulated price jobs are on CCDC 2 – 2020, and its payment rules are in Part 5. The clauses that matter here, from the published form text:

ClauseWhat it says, in plain terms
GC 5.2.1Applications for payment go monthly to the owner and the consultant at the same time
GC 5.2.2Each is dated the last day of the payment period: month end, or another day the parties agree in writing
GC 5.2.3The amount claimed is the value, proportionate to the contract, of work performed and products delivered to the site as of that date
GC 5.2.4The contractor submits a schedule of values, adding up to the contract price, to the consultant at least 15 calendar days before the first application
GC 5.2.5It’s in the form the contract specifies, supported by whatever evidence the consultant reasonably requires
GC 5.2.6Applications are based on the schedule of values accepted by the consultant, and must comply with payment legislation
GC 5.2.7Each application includes evidence of workers’ compensation compliance and, after the first, a CCDC 9A statutory declaration
GC 5.2.8Products delivered but not yet installed are supported by evidence of their value and delivery
GC 5.3.1.1The consultant certifies within 10 calendar days of receiving the application, for the amount claimed or the amount it finds properly due
GC 5.3.1.2The owner pays within 28 calendar days of receipt, and in any event as payment legislation requires
GC 5.7.1No payment is acceptance of work that doesn’t conform to the contract

GC 2.2.4 makes the consultant responsible for determining the amounts owing from its own observations, and GC 3.4 asks for the construction schedule before the first application too. Reviewing a claim against both shows whether each line is moving when the schedule says it should.

The Ontario Association of Architects’ commentary on the schedule of values (2020, template updated 2021) adds the practical side. The breakdown by discipline (architectural, structural, mechanical, electrical) should match the bid form, even where individual lines differ. The contractor’s first version is usually built around its subcontracts and rarely has the detail a reviewer needs, so the OAA’s advice is to put a draft schedule in the specifications so the format is known at tender. CCDC 24 – 2022 has model forms for CCDC 2 – 2020, including the Schedule of Values and Work Performed and the Certificate for Payment, if your consultant doesn’t have a house format.

The OAA’s FAQ 07 answers a question owners often ask: under CCDC 2 without supplementary conditions, the contractor doesn’t have to attach every subcontractor invoice to each claim. If you want that backup, say so in the supplementary conditions or the specification.

On a cost-plus contract you pay actual costs, so the schedule of values works as a budget breakdown that costs are tracked against rather than a measure of earned value.

Building a schedule of values you can check every month

The 15 days before the first claim are the best chance you’ll get to make every later claim easy to review. Once the contractor has billed against a schedule for a few months, changing it means reworking every claim since. These are the points worth settling at the start.

Lines small enough to measure

A line called “Mechanical: $780,000” is hard to check. Splitting it into plumbing and HVAC, then by floor or by rough-in and finish, makes each percentage something you can see. The OAA commentary gives three useful rules: show material and labour separately when materials can arrive in bulk before installation (its example is hollow metal doors and frames); split a trade where it supplies different materials of different values (porcelain floor tile against ceramic wall tile); and split work that happens in sequence (ceiling grid, then tile).

More lines take the contractor more time to update each month, so stop at the level of detail you can actually measure.

General conditions, mobilization and bonds on their own lines

General conditions are the contractor’s site costs for the life of the job: supervision, the site office, hoarding, temporary power. They’re usually billed evenly by month across the planned duration or in proportion to overall progress; agree which before the first claim. If the job runs late, billing by month can put general conditions ahead of the work, so some owners cap the line at the overall percentage complete. Mobilization and bonds are genuinely incurred at the start, and as separate, modest lines they’re paid when spent instead of sitting inside the trade values.

Front-loading, and how to spot it

Front-loading means early items in the schedule carry more of the price than they’re worth, and later items less, so cash arrives ahead of the work. It’s often unintended. Contractors carry real early costs, such as deposits on long-lead equipment and mobilization, and a schedule built from subcontract prices can lean early without anyone setting out to do it. The effect on the owner is the same either way: you pay for more work than is in place, holdback is calculated on a figure higher than the work it’s meant to cover, and if the job is interrupted the remaining contract balance may not pay for the remaining work.

To check for it, line the schedule up by trade against a cost estimate prepared for you during design, and look for lines priced well above it early and well below it late. Our guide to reading a construction estimate explains how those are laid out. Without an estimate, look at the shares: structure and site work taking more of the price than the building type suggests, finishes looking thin. Ask about any line that stands out. Most are resolved with a short conversation and a rebalanced schedule, which is much easier before the first claim than after the fifth.

Allowances and close-out documents

Cash allowances under CCDC 2 (GC 4.1) cover work the contract defines but hasn’t priced exactly, such as hardware or signage. Expenditures are authorized by the owner through the consultant (GC 4.1.3) and the work under an allowance can be claimed in progress payments (GC 4.1.6). Show each allowance as its own line so you can see what’s been spent against it.

The OAA commentary also recommends giving close-out documents (as-built drawings, operation and maintenance manuals, warranties) their own value at the start, because “the end of a project is not the time to determine how much the documents are worth.” It suggests a value low enough that the contractor can reach substantial performance without them, but high enough that the job can’t be deemed complete until they’re handed over. In our example, $30,000 sits under what’s left at substantial performance on a $5 million contract (about $80,000 by the Act’s 3%, 2% and 1% test) and above the $5,000 deemed-completion threshold in s. 2(3) of the Act. Our article on substantial performance in Ontario explains both tests.

Change orders as their own lines

Each approved change order goes on the schedule as a new line numbered to match it, rather than being folded into a trade line, so every change can be tied back to its approval. The OAA recommends adding a change to the contract value only once it’s approved and signed. Undisputed work under a Change Directive can also be included in progress payments (GC 6.3.11). How changes arise and get priced is covered in our guide to change orders.

The monthly progress claim, step by step

At each month end the contractor updates the percentage complete on every line, works out the value earned to date, takes off what was claimed before, and claims the difference. Here’s month five of the example contract, with one $25,000 change order approved and complete. Again, the numbers are illustrative.

LineDescriptionValue ($)% completeEarned to date ($)Previously claimed ($)This claim ($)
01General conditions380,00050%190,000152,00038,000
02Mobilization50,000100%50,00050,0000
03Bonds and insurance60,000100%60,00060,0000
04Demolition and site preparation120,000100%120,000120,0000
05Concrete560,000100%560,000476,00084,000
06Masonry180,00035%63,00018,00045,000
07Structural steel450,00090%405,000270,000135,000
09Roofing and waterproofing210,00025%52,500052,500
15Plumbing260,00025%65,00039,00026,000
16HVAC520,00020%104,00052,00052,000
17Electrical560,00025%140,00084,00056,000
18Fire protection150,00015%22,5007,50015,000
CO-01Change Order 1 (approved)25,000100%25,000025,000
Lines 08, 10–14, 19, 201,500,0000%000
Total5,025,00037%1,857,0001,328,500528,500

The summary at the foot of the claim then turns the earned value into an amount payable:

$
Value of work this period528,500.00
Less 10% holdback (s. 22(1) of the Act)(52,850.00)
Net amount this period475,650.00
HST at 13%61,834.50
Amount payable this claim537,484.50
Holdback retained to date (10% of $1,857,000)185,700.00

Ontario’s HST rate of 13% is from the Canada Revenue Agency. How HST on the holdback portion is reported and paid is a timing question for your accountant; what matters on the claim is that it’s shown the same way every month.

Two lines are worth a look even though the arithmetic is fine. Structural steel jumped from 60% to 90% in a month, which a site walk will confirm or correct. And the change order billed at 100% needs the signed change order on file and the work visibly complete.

What comes with each claim

Under GC 5.2.7 each application includes evidence of workers’ compensation compliance, which in Ontario means a current WSIB clearance certificate, and after the first payment, a CCDC 9A statutory declaration that the contractor has paid its trades and suppliers out of the money received up to the last payment. Read the 9A against the previous month’s payment; it speaks to the money you’ve already paid, not this claim.

Holdback in every claim

The Act requires the owner to retain 10% of the value of services and materials supplied as they’re supplied (s. 22(1)). It’s taken off every claim, as in the summary above, and kept as a running total. Since January 1, 2026, the Act also requires holdback to be released annually on each contract anniversary, not only after substantial performance. Release, liens and the owner’s liability cap are covered in our guide to construction liens and holdback in Ontario; each claim should show the running holdback total so it’s easy to check.

Stored materials, on site and off

CCDC 2 pays for products “delivered to the Place of the Work” (GC 5.2.3), with whatever evidence of value and delivery the consultant reasonably asks for (GC 5.2.8): typically the supplier’s invoice and a delivery slip, and the material visible on site, stored and protected.

Materials stored off site, such as fabricated steel in a shop yard or switchgear at the manufacturer, aren’t covered by the standard wording. If you need to pay for them, perhaps to hold a price on long-lead equipment, set conditions in the supplementary conditions first. Owners commonly require the material to be identified as theirs and stored separately, insured, transferred to them on payment by bill of sale, open to inspection, and itemized on its own line. A lawyer should draft the clause, and your lender may have its own requirements.

Certificates of payment and the Construction Act clock

Under CCDC 2 the consultant (usually the architect or prime consultant) reviews each application, visits the site, and issues a certificate for payment to the owner with a copy to the contractor. The certificate says what the consultant finds properly due, which may be the full amount claimed or less (GC 5.3.1.1). It records the consultant’s assessment of value; under GC 5.7.1 it isn’t acceptance of the work.

Other people do the same job on other projects:

Contract or settingWho certifies
CCDC 2 stipulated priceThe consultant
CCDC 14 design-buildA payment certifier, a role the contract names separately from the design-builder
CCDC 5A / CCDC 17 construction management (CM as agent)The construction manager certifies trade payments under CCDC 17 (OAA Practice Tip PT.23.2, 2026); see our guide to CCDC 17 trade contracts
CCDC 5B construction management (CM at risk)The consultant certifies the CM’s fee for construction services and the work, but not its pre-construction services (same OAA practice tip)
Any financed projectThe lender’s cost consultant also reviews the claim for its own purposes before each advance

The lender’s cost consultant works for the lender, not for you; the draw process is in our guide to construction financing in Ontario. Using the same lines for the contractor’s schedule of values and your lender’s hard-cost budget saves a monthly reconciliation.

How the review fits inside the Act’s deadlines

The Construction Act sets the outer limits, and the contract’s own timing has to fit inside them. Proper invoices are given monthly unless the contract says otherwise (s. 6.3(1)). In practice the contractor’s application for payment is the proper invoice, provided it contains what s. 6.1(1) lists. Here’s how a CCDC 2 claim runs against the Act, counting from the day you receive it:

DayWhat happensWhere it comes from
0Application received by the owner and consultant at the same timeGC 5.2.1
By day 7If the invoice is missing information it must contain, tell the contractor in writing what’s missing; otherwise it’s deemed properAct s. 6.1(2), from 2026
By day 10Consultant issues the certificate for paymentGC 5.3.1.1
By day 14If you’re paying less than the invoice, give a notice of non-payment (Form 1.1) stating the amount and every reasonAct s. 6.4(2); GC 5.3.1.1
By day 28Pay everything not covered by the notice, less holdbackAct s. 6.4(1), (3); GC 5.3.1.2
7 days after you payContractor pays its subcontractors their shareAct s. 6.5(1)

Two rules shape the review. The giving of a proper invoice can’t be made conditional on the consultant certifying first or on your approval (s. 6.3(2)), but certification after the invoice is allowed (s. 6.3(3)). That’s exactly how CCDC 2 works: the contractor invoices, then the consultant certifies. And the 14-day notice is the only way to pay less than the invoice on day 28. If the consultant certifies less on day 10 and nobody sends the notice by day 14, the full invoice amount falls due.

So the four days between the certificate and the notice deadline are tight. Agree beforehand who drafts the notice (often the consultant or your owner’s rep, from the certificate’s reasons), who signs it and how it’s delivered. Since 2026 you can also require anything your accounts payable system reasonably needs on the invoice (s. 6.1(1) para 6.1); put that list in writing before the first claim. The OAA/OGCA recommended supplementary conditions for CCDC 2 – 2020 (revised 2024) add a defined term, Proper Invoice, tied to the Act; your lawyer will advise whether to go further.

Late payment carries interest. CCDC 2’s Article A-5 sets 2% a year above prime for the first 60 days and 4% above prime after that, compounded monthly.

When a claim doesn’t match the site

It happens on most projects at some point, and it’s usually a matter of judgment: progress estimated from the office at month end and checked on the floor a week later, a delivery counted before it arrived, a change billed before it was signed. The process is the same in every case:

  1. Certify what’s earned. The consultant certifies the amount it finds properly due, line by line, and records why each line was adjusted. Adjusting the percentage on two lines is ordinary contract administration, and doesn’t mean rejecting the claim.
  2. Give the notice on time. The notice of non-payment goes out within 14 days, stating the amount not being paid and every reason (s. 6.4(2)). Reasons like “masonry certified at 25%, not 35%; north elevation not started” are specific enough for anyone to check.
  3. Pay the rest on time. Everything not in the notice is due on day 28 (s. 6.4(3)). Holding back the whole payment over one disputed line isn’t permitted, and it’s hard on the trades who are waiting on it.
  4. Talk it through. A short call or a site walk with the contractor’s project manager settles most differences. If the contractor was right, the amount goes in next month’s claim. If it can’t be agreed, either party can take a payment dispute to adjudication under Part II.1 of the Act, which the lien and holdback guide explains.

What helps most is a schedule both sides trust. When lines are small and balanced, adjustments are rare and a month-end claim takes hours to review instead of days, which serves the contractor as much as the owner.

If it turns out mid-job that the schedule itself doesn’t fit the work, a revised one needs the consultant’s acceptance (GC 5.2.6) and is best agreed with the contractor. Splitting a broad line into measurable parts while keeping its total is usually an easy conversation; rebalancing values partway through is a negotiation, since the contractor has billed against them in good faith.

A monthly progress claim review checklist

For the owner, or whoever reviews claims for you:

  1. Date and period. Dated the last day of the payment period (GC 5.2.2), and received by you and the consultant.
  2. Proper invoice. Carries everything in s. 6.1(1) and your contract requires; if not, write within 7 days saying what’s missing.
  3. Arithmetic. Values total the current contract price, and “previously claimed” matches last month’s certified amount line by line. Keep your own spreadsheet copy, as the OAA recommends.
  4. Site walk. See the lines with the biggest movement this month.
  5. Construction schedule. Lines moving in the order the schedule says they should.
  6. Changes. Every change order line backed by a signed change order; Change Directive amounts limited to the undisputed value.
  7. Stored materials. Invoices and delivery slips for products on site; nothing off site billed without the conditions in your contract.
  8. Allowances. Spending against each cash allowance matches what you authorized.
  9. Backup. WSIB clearance current; CCDC 9A for the previous payment, sworn and complete.
  10. Holdback. 10% taken off, and the running total agrees with your records and your lender’s.
  11. Certificate by day 10, and if it’s less than the claim, the notice of non-payment signed by day 14.
  12. Payment by day 28, with your lender’s cost consultant warned early if its timetable is tight.

Frequently asked questions

What is a schedule of values in construction?

It’s a breakdown of the contract price into line items, each with a value, that add up to the full price. Each month the contractor reports how complete each line is, and the progress claim is the value earned since the last one. Under CCDC 2 – 2020 the contractor submits it to the consultant at least 15 days before the first claim, and claims are based on the version the consultant accepts.

Who prepares the schedule of values?

The contractor prepares it, because the values come from its own pricing and subcontracts (GC 5.2.4). The consultant accepts it or asks for changes (GC 5.2.6). The owner shapes it in advance by putting a required format and level of detail in the specification, as the OAA recommends, and an owner’s rep or cost consultant often checks it against the design-stage estimate.

What is a certificate of payment?

It’s the consultant’s statement of how much is properly due on a progress claim. Under CCDC 2 – 2020 it’s issued to the owner, with a copy to the contractor, within 10 calendar days of the application (GC 5.3.1.1). It can be for less than the amount claimed, and it doesn’t mean the work is accepted (GC 5.7.1). On design-build contracts a payment certifier issues it.

What’s the difference between a progress billing and a proper invoice?

“Progress billing” is the general term for invoicing as work proceeds. A proper invoice is the Ontario Construction Act’s term: a written request for payment containing the information in s. 6.1(1), which starts the 28-day clock. On most Ontario projects the monthly progress claim is the proper invoice. If it’s missing required information you have 7 days to say so, or it’s treated as proper anyway.

Can the owner change the schedule of values?

Not on your own once it’s accepted, since claims run on the schedule the consultant accepted. Before the first claim you can ask through the consultant for more detail, a different format or rebalanced values. Later, approved change orders are added as new lines, and lines can be split or rebalanced if the contractor agrees and the consultant accepts the revision.

Getting the first claim right

If your contract is signed and the first claim is a few weeks away, the schedule of values is the thing to look at now: line size, general conditions, front-loading against your estimate, close-out documents, and how changes and stored materials will be shown. If you’re still at tender, put a draft schedule and your claim requirements in the specification so every bidder prices against the same rules. Our guide to the CCDC 2 stipulated price contract covers the supplementary conditions those requirements belong in.

Reviewing schedules of values and progress claims is part of the independent construction consulting we do for Ontario owners. Our experience was built at PCL Constructors and Oxford Properties, so we’ve seen both the claim being put together and the claim being reviewed. If you’d like a second set of eyes on a schedule before the first claim, or on a claim that isn’t adding up, we’re happy to talk it through.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada