October 27, 2026 · Updated November 10, 2026

CCDC 9A Statutory Declaration and How to Complete It in Ontario

CCDC 9A is a statutory declaration, the “stat dec” in site-office shorthand: a statement the contractor’s signing officer swears before a commissioner, saying that everyone the contractor owed money to on your project has been paid up to the last progress payment it received from you, except for holdback, amounts deferred by agreement and amounts in genuine dispute. Under the current CCDC 2 – 2020 contract it comes with every application for payment after the first, and a separate one comes with the application to release holdback. The form is free from CCDC, and the current edition is CCDC 9A – 2018.

For an owner it’s one of the few pieces of paper each month that says, under oath, where your last payment went. It isn’t a lien release, and it doesn’t replace the other checks you make before paying. Below: what the 9A and its subcontractor version, 9B, say, how to fill one in, how they sit beside Ontario’s holdback and lien rules, and the checks worth making each month. It’s practice, not legal advice: where money is in dispute, a construction lawyer reads your contract.

What CCDC 9A and 9B are

The Canadian Construction Documents Committee publishes two declarations, both 2018 editions, both free and electronic only:

CCDC 9A – 2018CCDC 9B – 2018
Full titleStatutory Declaration of Progress Payment Distribution by ContractorStatutory Declaration of Progress Payment Distribution by Subcontractor
Who makes itThe contractor you hold the contract withA subcontractor, to the contractor it works for
Who signsPresident, vice-president, secretary or another signing officer authorized by resolutionThe same, for the subcontractor
WhenAs a condition of the second and later progress payments, or of a release of holdbackThe same, on the subcontract
What it declaresAccounts the contractor incurred directly on the work, for which you might be held responsible, are paid up to the last payment receivedAccounts the subcontractor incurred directly, for which the contractor might be held responsible, are paid up to the last payment received
Sworn beforeA commissioner for taking affidavits, notary public or justice of the peaceThe same

Sources: CCDC 9A and CCDC 9B on ccdc.org, checked October 2026.

Each form has two boxes at the top: one for “second and subsequent progress payments” and one for “release of holdback”. The two are separate declarations. The Ontario Construction Association, which commissions these forms for its members, puts it plainly: one declaration can’t be used for both conditions, so a holdback application comes with its own 9A.

What the declaration actually says

The 9A wording, from the 2018 form on ccdc.org:

I solemnly declare that, as of the date of this declaration, I am an authorized signing officer, partner or sole proprietor of the Contractor, and as such have authority to bind the Contractor, and have personal knowledge of the fact that all accounts for labour, subcontracts, products, services, and construction machinery and equipment which have been incurred directly by the Contractor in the performance of the work as required by the Contract, and for which the Owner might in any way be held responsible, have been paid in full as required by the Contract up to and including the latest progress payment received, as identified above, except for: 1) holdback monies properly retained, 2) payments deferred by agreement, or 3) payment withheld by reason of legitimate dispute which has been identified to the party or parties from whom payment has been withheld.

The 9B says the same for a subcontractor, with the contractor as the party who might be held responsible. Phrase by phrase:

Which payment it speaks to

This is the part owners most often misread. When the contractor sends in application number 6, the 9A that comes with it is about application number 5, the last one you paid. It tells you that the money you released last month has gone where it was supposed to go. It says nothing about the trades whose work is in this month’s claim, because they haven’t been paid for it yet.

That’s why there’s no 9A with the first application: there’s no previous payment to account for.

How to fill in a CCDC 9A, line by line

The form is a single page. On the 2018 PDF from ccdc.org (checked November 2026), the fields run top to bottom like this:

  1. The two condition boxes. Under “To be made by the Contractor as a condition for either”, tick one: “second and subsequent progress payments” or “release of holdback”. One box, one form.
  2. Application for payment number and date. The box at top right reads “Application for payment number ___ dated ___ is the last application for payment for which the Contractor has received payment.” Enter the application already paid, not the one this form travels with. With application 6, that’s application 5 and its date.
  3. Name of Project. This block sits under the heading “Information Appearing in the Contract Documents”, so copy the name as the contract gives it.
  4. Date of Contract. The date of the signed agreement, not the day work started on site.
  5. Name of Owner and Name of Contractor. Two boxes side by side, with the legal names from the contract. If the owner is a numbered or holding company, that name goes here.
  6. The declaration. The printed paragraph and its three exceptions. Nothing is filled in and nothing should be changed: the note at the foot says a sealed form is meant to be “an accurate and unamended version of CCDC 9A – 2018”. Anything the contractor needs to qualify goes in a covering letter.
  7. “Declared before me in ___ this ___ day of ___ in the year ___”. The city or town and province, and the date it’s sworn. CCDC’s page for the form says the commissioner completes this, not the signer.
  8. Name, Title and Signature. The declarant’s printed name and title, then their signature, made in front of the commissioner.
  9. The commissioner’s signature. The line beside it, marked “A Commissioner for Oaths, Notary Public, Justice of the Peace, etc.”, usually with a stamp giving their details.
  10. The copyright seal. The box at bottom right reads “Apply a CCDC 9 copyright seal here.” The form says using it without one infringes copyright.

So the contractor’s office fills in items 1 to 5 and the officer’s name and title, and the rest happens at the appointment. The 9B is laid out the same way, with the subcontract date and the contractor and subcontractor names in place of the owner and contractor. The reasons a commissioner sends one back are listed under why commissioners turn forms away.

Where your contract asks for a statutory declaration

CCDC 2 – 2020

The 2020 edition of CCDC 2, the standard stipulated price contract, made the declaration a monthly item. Each application for payment after the first must include evidence of compliance with workers’ compensation legislation and a CCDC 9A statutory declaration by the contractor (MLT Aikins, April 2021). Under CCDC 2 – 2008 one was only required with the application for holdback at the end; Torkin Manes (February 2021) notes that supplementary conditions often added the monthly declaration to the old form. If you’re still on a 2008-based contract, check yours. Our guide to the CCDC 2 stipulated price contract walks through the rest of the payment part of that form.

Other contracts and other people who ask

Others on the same project may ask for one too:

How it fits the prompt payment clock

Ontario’s Construction Act runs a fixed clock from the day you receive a proper invoice: 7 days to flag anything missing, 14 days to give a notice of non-payment for any amount you dispute, and 28 days to pay the rest, less holdback.

The Act defines a proper invoice as one that contains the information listed in section 6.1(1) and “meets any other requirements that the contract specifies”. If your contract says an application for payment includes a 9A, the declaration is one of those requirements. Since January 1, 2026, an invoice that’s missing a required item is deemed proper unless you tell the contractor in writing, within seven days of receiving it, what’s missing and what’s needed to fix it (s. 6.1(2)).

So the 9A check happens in the first week. If application 6 arrives without a declaration, or with one that’s unsigned or uncommissioned, write to the contractor by day 7 and keep the dated notice. Certification can’t hold the invoice up either: a term making a proper invoice conditional on the certifier’s prior certification has no effect (s. 6.3(2)), which is why CCDC 2 – 2020 sends the application to you and the consultant at the same time (Torkin Manes, 2021). The construction liens and holdback guide sets out the full invoice clock with each section.

What a 9A does and doesn’t do for you in Ontario

What it gives you

A 9A gives you a sworn statement, from a named officer with authority to bind the company, that last month’s money reached the people the contractor owed, and it records the contractor’s position on anything it is withholding from a trade.

It also sits on top of an obligation the contractor already has. Under section 8 of the Construction Act, every amount owing to or received by a contractor on account of the contract price, holdback included, is a trust fund for the subcontractors and suppliers it owes. The contractor can’t use that money for anything else until they’re paid (s. 8(2)). Directors and officers who assent to a breach of trust they know, or reasonably ought to know, about can be personally liable for it (s. 13(1)). The 9A is the officer putting their name to compliance with that, under oath, every month.

What it doesn’t do

The declaration is evidence. It doesn’t change anyone’s legal rights.

The 9A tells youIt doesn’t tell youWhat covers that
The contractor’s own accounts are paid up to the last paymentWhether the subcontractors have paid their own trades and suppliers9B declarations from the main subcontractors
Which payment it coversAnything about the work in the current claimNext month’s 9A
That some amounts are withheld in disputeHow much, or from whom, unless the contractor saysAsk for the list in writing
The contractor’s statement as of the date signedWhether a lien has been registered sinceA title search (subsearch)
Payments to trades and suppliers onlyWhether the contractor’s WSIB premiums are paid upA current WSIB clearance

Four things in particular sit outside it.

It isn’t a lien release. A subcontractor or supplier keeps its lien rights whatever the contractor declares, generally until 60 days after publication of the certificate of substantial performance, or after its contract is completed, abandoned or terminated, or its own last supply (s. 31).

It doesn’t change your holdback obligation. Your liability to lien claimants is capped at the holdback you were required to retain (s. 23). Pay out more than 90% because the 9A looks clean, and the shortfall is yours if a trade turns out to be unpaid.

It doesn’t override a written notice of lien. If you’ve received one before you pay, you keep back enough to cover it as well as the holdback (s. 24(2)).

It doesn’t cover the excepted amounts. Deferred and disputed amounts are still owed, and they’re the ones most likely to become liens, so ask what’s behind them.

A false declaration

The warning at the foot of the form is real: perjury under section 131 of the Criminal Code includes a false solemn declaration made knowingly with intent to mislead, and section 132 makes it an indictable offence. That isn’t how owners use the form, though. A discrepancy is usually a timing issue or a disputed invoice the contractor hadn’t listed, and a phone call and a corrected schedule sort most of them out.

Before you release a progress payment: a monthly checklist

Give this to one person, usually the owner’s representative or the payment certifier, and run the same steps each month. Here’s the routine we’d set up before the first application arrives.

  1. Log the date the application arrives. That’s day 0 of the prompt payment clock. Put days 7, 14 and 28 in the calendar.
  2. Check the package is complete by day 7. The application, the updated schedule of values, the 9A for the previous payment (from application 2 on), evidence of workers’ compensation compliance, and anything else your contract lists. Anything missing goes back to the contractor in writing, saying what’s needed.
  3. Read the 9A against your payment record. Run down the fields in the line-by-line section. The application named should be the last one you paid, and the declaration should be dated after you paid it: if you paid application 5 on the 14th, a declaration signed on the 10th can’t speak to it.
  4. Ask about the exceptions. If the contractor is withholding from anyone because of a dispute, or has agreed to defer a payment, ask which trades and how much. It’s a fair request, and the answer goes in your file.
  5. Compare the subcontractor list to the schedule of values. Any trade that’s billed work through the contractor should be one the contractor is paying. On larger jobs, ask for 9B declarations from the main subcontractors (mechanical, electrical, structure, envelope) with the contractor’s 9A. Your contract or supplementary conditions should say so if you want it as a requirement.
  6. Check the WSIB clearance is current. In Ontario, a person who directly retains a contractor for construction work has to obtain a clearance certificate before the work begins, and a new one if it expires before the work is done (Workplace Safety and Insurance Act, s. 141.2). Without one, you can be liable for premiums the contractor fails to pay (s. 141.1). The WSIB says clearances are valid for up to 90 days (page updated July 2026), so this is a check that recurs on a long job.
  7. Note any written notice of lien. If one has arrived, hold back enough to cover it as well as the holdback before paying anything more, and call your lawyer.
  8. Review the work and the amount by day 14. Any amount you dispute goes in a notice of non-payment, with every reason, by day 14. Many disputed amounts turn out to be changes; our article on change orders covers keeping those priced and agreed before they reach the invoice.
  9. Pay the undisputed amount by day 28, less 10% holdback. Record the payment date. Next month’s 9A should speak to it.
  10. File everything together, per application: application, certificate, 9A, clearance, any notice and the payment record. If a lien claimant asks for a state of accounts under section 39, the answer is already in one place.

Before you release holdback: the extra steps

Holdback is the money the Act keeps back to protect people with lien rights, so its release is where the declaration matters most. Since January 1, 2026, Ontario owners release it every year after the contract anniversary and again at the end of the job; the liens and holdback guide covers the timetable in full.

A separate declaration, with the holdback box ticked. The contractor’s application for holdback comes with its own 9A. Don’t accept the latest progress declaration in its place.

The annual release. You publish a notice (Form 6) within 14 days after each contract anniversary and pay the year’s holdback 60 to 74 days after it, unless a lien has been preserved (s. 26(3)–(4)). The final release. Once liens against the holdback have expired or been dealt with, you pay the rest within 14 days (s. 26(8)). The lien periods run from publication of the certificate of substantial performance; our guide to substantial performance in Ontario covers the certificate and the closeout list that comes with it.

Before either release, the checks we’d run:

  1. A 9A for holdback release, ticked correctly, signed by an officer and commissioned.
  2. 9B declarations from the main subcontractors, also for holdback release, if your contract calls for them.
  3. A subsearch of title on the day before payment for any preserved lien, and a check of your own correspondence for any written notice of lien.
  4. A current WSIB clearance.
  5. The holdback ledger reconciled: what was retained, what was released at the last anniversary, and what’s being paid now.
  6. Your lender’s sign-off, if the project is financed and the lender’s agreement requires it.

If a lien has been preserved, the annual payment waits until the lien is discharged or vacated, and then it’s due within 14 days (s. 26(4), (7)). Vacating a lien by posting security (s. 44) is work for the lawyers.

Commissioning a CCDC 9A in Ontario

Who can commission it

The declaration has to be made before someone authorized to take it. In Ontario, the Commissioners for Taking Affidavits Act gives every commissioner power to take declarations (s. 7). Those who are commissioners by virtue of their office are listed in O. Reg. 386/12, among them licensed lawyers and paralegals, justices of the peace, and municipal clerks. Notaries public can also take declarations, and construction associations such as the OCA run commissioning services for members.

Doing it remotely

Since 2020, Ontario has allowed a declaration to be taken by video under O. Reg. 431/20. Everyone has to see, hear and talk to each other in real time for the whole transaction, the commissioner confirms the declarant’s identity, and the declaration wording is modified to say it was done under the regulation and where each person was.

Why commissioners turn forms away

From the OCA and the Construction Association of Saskatchewan guidance, the usual problems are:

When a declaration doesn’t add up

When something looks off, it’s usually one of these.

A trade calls you to say it hasn’t been paid. Write down who, how much, and for what period. Check it against the last 9A: is that trade covered by one of the exceptions? Then ask the contractor, in writing, for its position. If the trade sends written notice of a lien, section 24 applies: keep back enough to cover it before you pay anything more. Don’t pay the trade directly unless your lawyer has looked at it; your contract is with the contractor.

The contractor lists a disputed amount. That’s the form working as intended. Ask what the dispute is; one that runs for months is a lien risk at holdback time.

A payment dispute you can’t resolve. Adjudication under Part II.1 of the Act gives a fast interim decision on payment disputes, and since 2026 the matters it covers include changes to the contract price, scope and delay claims (Pallett Valo, March 2026). The adjudicator works from the notices and records the parties kept, so the monthly file above is what you’d hand over.

Frequently asked questions

What is a CCDC 9A form?

CCDC 9A – 2018 is the Statutory Declaration of Progress Payment Distribution by Contractor. The contractor’s signing officer swears, before a commissioner, that the contractor’s own accounts on the project are paid up to the last progress payment it received, except holdback, agreed deferrals and identified disputes. CCDC 2 – 2020 requires one with every application after the first and another with the holdback application.

What’s the difference between CCDC 9A and 9B?

The 9A is made by the contractor that holds the contract with the owner. The 9B is the same declaration made by a subcontractor to the contractor, about the subcontractor’s own trades, suppliers and equipment. Owners who want a view below the first tier ask for 9Bs from the main subcontractors alongside the contractor’s 9A, and say so in the contract.

Where do I get a CCDC 9A form?

From CCDC. The CCDC 9A page on ccdc.org offers the 2018 form as a free PDF download, and the CCDC 9B page has the version subcontractors make to the contractor. Both are electronic only. The completed copy carries a CCDC 9 copyright seal in the box at the bottom right, and a 2018 form takes a 2018 seal.

No. A declaration is the contractor’s sworn statement about its own payments as of the day it was signed. It doesn’t stop anyone registering a lien within the Act’s time limits. Before releasing holdback, owners check title for preserved liens and their own files for written notices of lien, as well as collecting the declaration.

Who signs a CCDC 9A, and does it need a notary?

An authorized signing officer of the contractor signs it, in person, before a commissioner for taking affidavits, a notary public or a justice of the peace. In Ontario a licensed lawyer or paralegal can commission it, and it can be done by video under O. Reg. 431/20. An employee without signing authority can’t make it.

Where to start

If you’re about to sign a contract, decide what you want with each application (the 9A, a WSIB clearance, 9Bs from the main subcontractors, anything your lender needs) and make sure the contract or supplementary conditions say so. If you’re mid-project, pull last month’s 9A and check it against your own payment record: right box, right application, right date, commissioned, and any exceptions explained. If a holdback release is coming up, work backwards from the payment date so the declaration, the subsearch and the clearance are all in hand before the money moves.

We’ve spent more than 20 years on office, residential, retail and industrial projects, with experience built at PCL Constructors and Oxford Properties. If you’d like an experienced hand to set up the routine, review applications and declarations each month, or work through a discrepancy with your lawyer, that’s part of our construction consulting work on payment certification and cost review.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada