November 4, 2026

CMHC MLI Select in 2026: What the Points Mean for Your Building

MLI Select is CMHC’s points-based mortgage loan insurance for rental buildings of five or more units. You earn points by committing to affordable rents, energy performance beyond the national codes, or accessible units, and you need at least 50 points to qualify. For new construction, 50 points opens up to 95% loan to cost and a 40-year amortization, 70 points a 45-year amortization, and 100 points a 50-year amortization with limited recourse (CMHC, MLI Select, checked November 3, 2026).

Most of what’s written about MLI Select covers the loan; this guide covers what the points ask of the building. Every block of points is something the design and construction team has to deliver and prove: an energy model at application and an attestation after the last advance, accessible units the architect has to draw, and a rent cap that runs at least ten years. Those are concept-stage decisions, which is why we test them alongside the site when we provide development management for a purpose-built rental.

We’re not a mortgage broker and this isn’t financial advice. A CMHC-approved lender submits the application, usually found through a broker.

What MLI Select is and who qualifies

MLI Select replaced CMHC’s MLI Flex product on March 7, 2022. It insures a loan from an approved lender, which lets that lender advance more, for longer, at better pricing. New construction and existing buildings have different points tables; this article deals with new construction.

The headline terms, from CMHC’s MLI Select page and its program fact sheet (CMHC, MLI Select at-a-glance, October 2025):

New construction50+ points70+ points100+ points
Maximum loan to cost (residential)95%95%95%
Maximum amortization40 years45 years50 years
RecourseFullFullLimited
Minimum debt coverage ratio (standard rental)1.101.101.10
Premium discount10%20%30%
Replacement reserveDiscretionaryDiscretionaryDiscretionary

The premium discounts are from CMHC’s multi-unit fees and premiums sheet (May 2025).

The eligibility questions to answer first

CMHC’s page and fact sheet set the basic tests:

How the MLI Select points work for new construction

There are three pillars, and you can earn points from any combination of them. CMHC’s new construction table, as published on the MLI Select page on November 3, 2026:

PillarLevel 1Level 2Level 3
Affordability (10-year commitment)50 points: 10% of units at or below 30% of median renter income70 points: 15% of units100 points: 25% of units
Energy efficiency, compared with 2020 NECB or 2020 NBC Tier 120 points: 25% better than NECB, or 20% better than NBC35 points: 50% better than NECB, or 40% better than NBC50 points: 60% better than NECB, or 70% better than NBC
Accessibility (all units visitable at every level)20 points: 15% of units accessible to CSA B651:23, or 15% universal design, or Rick Hansen Foundation certification v4.0 at 60–79%30 points: 15% accessible and 85% universal design, or 100% universal design, or 100% accessible, or RHF v4.0 Gold (80%+)No Level 3

A commitment to keep the affordable rents for 20 years or more adds 30 points to the affordability score.

Existing buildings use a different table (40%, 60% or 80% of units affordable, and energy savings against the building’s own pre-retrofit use), so read that one if you’re buying or renovating.

Combinations that reach 50, 70 and 100

Energy and accessibility together top out at 80 points, so the 50-year amortization isn’t available without an affordability commitment. If the pro forma needs 50 years, settle the rent commitment first.

MLI Select affordability: what you commit to

The affordability pillar asks you to rent a share of the units at or below 30% of the median renter household income for your market, and to keep doing so for at least ten years from the building’s first occupancy.

What the rent cap works out to in Ontario

CMHC publishes the incomes it uses in a median renter income workbook. The version linked from the MLI Select page on November 3, 2026 shows 2019 incomes (Statistics Canada’s Canadian Income Survey), rounded to the nearest $100, and says it was last updated in March 2021. Thirty percent of those incomes, divided by twelve, gives a monthly ceiling. That’s our arithmetic, not a CMHC table:

Market in CMHC’s workbookMedian renter household income (2019)30% as a monthly rent
Toronto CMA$53,900$1,347.50
Mississauga$49,000$1,225.00
Brampton$67,700$1,692.50
Oshawa$54,000$1,350.00
Hamilton$44,400$1,110.00
Ottawa–Gatineau (Ontario part)$61,400$1,535.00
Ontario, outside the CMAs$41,500$1,037.50

Before you rely on a figure, ask your lender which line applies to your site (Mississauga and Brampton are listed apart from the Toronto CMA), whether a newer workbook has replaced this one, and whether the capped rent has to include parking or utilities you’d otherwise charge separately.

How the cap moves each year in a new Ontario building

CMHC’s rule is that the base rent on the designated affordable units can’t rise by more than the increase permitted under provincial rent legislation, and where none applies, by more than the consumer price index. Ontario’s rent increase guideline is 1.9% for 2027, but the province says the guideline doesn’t apply to new buildings first occupied for residential purposes after November 15, 2018 (Government of Ontario, Residential rent increases, updated June 23, 2026).

On our reading, a new Ontario building therefore falls under the CPI limit, which CMHC’s page sets at 0.7% for Ontario in 2027 (the lowest positive CPI between September 2025 and August 2026). Ask your lender to confirm, because the difference compounds over ten years.

How long it runs and how it’s checked

Unlike the energy and accessibility pillars, affordability is proven every year for the whole commitment.

What it does to the pro forma

The cost of the affordability pillar is the gap between market rent and the cap, on the designated units, for the length of the commitment. You can size it with simple arithmetic before anyone runs a full model. On a 60-unit building, Level 1 means at least 6 affordable units, Level 2 at least 9, and Level 3 at least 15. Every $100 a month between your market rent and the cap is $7,200 a year on 6 units and $18,000 a year on 15. The actual gap comes from your market study.

Set that against what the points buy: a longer amortization, a lower premium and, at 100 points, limited recourse. Model the building with and without the commitment side by side, and remember the appraisal values the building on its income, capped units included.

The rule is a share of units, not of floor area, so the unit mix matters. Check how your lender rounds a 10% share on a unit count that doesn’t divide evenly before the architect locks the plan.

MLI Select energy efficiency requirements

The energy pillar asks the building to beat a national code reference by a set percentage of total energy use, shown by a computer model at application and confirmed after construction.

The baseline is the 2020 national code

For Part 3 buildings (most rental buildings over three storeys, or over 600 m² of building area), the comparison is the Tier 1 performance of the 2020 National Energy Code for Buildings: 25%, 50% or 60% better for Levels 1, 2 and 3. For Part 9 low-rise buildings, it’s the 2020 National Building Code: 20%, 40% or 70% better. The measure is total annual energy consumption, with greenhouse gas emissions reported alongside it.

CMHC says it won’t accept modelling against local building codes. Ontario’s Building Code, O. Reg. 163/24, has its own energy efficiency requirements, so your energy modeller builds a separate reference building to the national code for the CMHC report. That reference must be “reasonable or commonly built” for your area and permitted by local code.

Two of CMHC’s answers on its FAQ change the design conversation:

Low-flow fixtures and efficient appliances count too, modelled against a stated baseline.

Who models it and what they hand over

For Part 3 buildings, CMHC’s documentation guide accepts a professional engineer, architect, Certified Engineering Technologist or Certified Energy Manager with modelling experience; for Part 9 buildings under four storeys, a residential energy advisor accredited by Natural Resources Canada. The software must be whole-building, hourly and compliant with ASHRAE Standard 140 (EnergyPlus, CanQUEST, eQUEST, IES-VE and others; HOT2000 for small Part 9 buildings).

The report goes in with the application: annual energy and emissions for the reference and proposed buildings with the percentage saving, a breakdown by end use, the envelope and mechanical features that produce the saving, the model’s input and output files, and the modeller’s signed energy efficiency attestation.

CMHC also accepts some third-party certifications in place of the model. For Ontario builders the relevant ones are Passive House (Classic, Plus or Premium), which CMHC treats as energy Level 3, and the CaGBC Zero Carbon Building Standard v2 Design, which counts as Level 2 on the Flexible and Passive paths and Level 3 on the Renewable path.

When the points are proven

Within 60 days of the final advance, you sign an attestation that the energy criteria have been met, with supporting documentation. CMHC’s fact sheet says that where you complete the work with your own money or non-insured financing, the documentation is due within 24 months of the last advance. Once the energy and accessibility criteria are met, the fact sheet says the commitment is fulfilled and there’s no annual reporting.

If the finished building falls short, the documentation guide says the lender gets the facts from you and notifies CMHC promptly; CMHC doesn’t publish what follows. Design to the target with a margin, and keep the modeller involved through construction.

What usually moves the number

We know of no published Ontario costing for each MLI Select level, so we won’t give you a premium. Here’s where the modeller will look first, so the cost consultant knows what to price:

Each is easier to change at concept than after the drawings are coordinated; a late change of heating system can move the electrical service, the mechanical rooms and the roof. Energy measures are also among the first things proposed for cutting when a tender comes in high, and cutting them can cost the points the loan was sized on. Our article on value engineering without wrecking the building covers how to test those proposals.

How it sits beside the Toronto Green Standard

The Toronto Green Standard energy targets became voluntary after Bill 98 in June 2026, but still matter for the Tier 2 or 3 development charge refund. The TGS measures intensities per square metre (TEUI, TEDI, GHGI); CMHC measures a percentage saving against a national code reference. One model can serve both, but a building can pass one test and miss the other, so brief the modeller on both.

MLI Select accessibility: what changes on the drawings

The accessibility pillar is worth 20 or 30 points. It’s often the cheapest to earn when the design starts with it, and among the most expensive to retrofit once the floor plans are set.

Every unit has to be visitable

At both levels, every unit in the building, not only the designated accessible ones, has to be “visitable” to CSA B651:23, and every common area has to be barrier-free to the same standard. CMHC quotes the CSA definition: a visitable dwelling lets a visitor who uses a wheeled mobility aid, an older visitor or someone with a temporary disability enter safely, move independently through the visitable level, and use the toilet.

On the drawings, that usually means a step-free entrance to each suite, enough clear width in doorways and corridors, and a washroom on the entry level with room to turn. The Ontario Building Code has its own barrier-free rules; your accessibility consultant can tell you where B651 asks for more. Flats off a corridor usually work. A step at the door, a split-level entry or the only washroom upstairs needs rethinking.

Level 1 and Level 2

Level 1 (20 points) adds one of three options: at least 15% of units fully accessible to CSA B651:23; at least 15% of units built to universal design; or a Rick Hansen Foundation Accessibility Certification v4.0 score of 60% to 79%.

Level 2 (30 points) asks for more: 15% accessible units plus 85% universal design units; or 100% universal design; or 100% accessible units; or RHF v4.0 Gold (80% or better).

A fully accessible unit usually needs more room at the bed, kitchen and washroom, which affects the unit mix and rentable area per floor, so settle the count before the floor plate is fixed. Universal design is often easier to apply across every unit than carving out a share of larger accessible ones.

Who signs, and when to bring them in

At application, an architect or designated accessibility consultant signs CMHC’s accessibility attestation, with a summary of the features and a sample unit design. The 60-day attestation after the last advance covers accessibility too.

Bring the accessibility consultant in at concept, before the unit layouts are drawn: the commitment is made on plans and confirmed on the finished building. For Rick Hansen certification, have the rating professional review the design as it develops.

How MLI Select changes the design, budget and schedule

The points are chosen early and carried through every stage until a signed attestation closes them out. Here’s the sequence as we’d plan it:

StageWhat happens with MLI SelectWhat the development manager does
FeasibilityTest the site with and without each pillarRun the pro forma at 50, 70 and 100 points; price the affordability gap; confirm eligibility
Concept designSet a points target in the design briefBrief the architect, modeller and accessibility consultant together; fix the unit mix
Schematic designFirst energy model and accessibility reviewCheck the margin over the target; have the measures priced
ApprovalsZoning and site plan control as normalKeep the points stable through design changes the City asks for
Lender applicationAttestations, energy report and pro forma rent roll submittedAssemble the budget, schedule, contract and reports with the broker
Before first advanceLoan documents with the social outcome covenant signedCheck the contract and specification carry the measures
ConstructionDraws reviewed by the lender’s cost consultantTrack substitutions that touch the model or accessible units
After the last advanceEnergy and accessibility attestations within 60 daysHave the consultants confirm the as-built building
OperationAnnual affordability certificate with the rent rollHand the property manager the covenant and the CPI limit

Construction draws, briefly

The loan mechanics are in our guide to construction financing in Ontario. For the building side, what matters is this. CMHC’s fact sheet says a new construction loan under MLI Select may be advanced up to 95% of costs during construction, and a rental achievement holdback may apply. CMHC’s older reference guide for its standard rental product has the lender’s quantity surveyor review costs, asks for a fixed price or construction management contract, and has CMHC approve the first and last advances (CMHC, Reference Guide, 2017). Confirm with your lender which of those still apply to your loan.

The energy and accessibility measures need to be visible in the contract, specification and cost breakdown, and any substitution (a different window, heat pump or ERV) should go past the energy modeller before it’s approved. Our guide to reading a construction estimate covers what to ask for in that breakdown.

Budget for CMHC’s application fee too: with more than two advances, $200 per unit for the first 100 units and $100 after, up to $55,000, plus $350 per advance from the third.

What the premium discount is worth, as arithmetic

On construction financing above 90% loan to value, CMHC’s base premium for standard rental is 7.00%, and only MLI Select loans can go that high. A surcharge of 0.25% applies for every five years of amortization beyond 25, and the MLI Select discount comes off the base premium plus surcharges. On a hypothetical $20 million loan, at the longest amortization each level allows:

PointsAmortizationPremium rate after surcharge and discountPremium on $20M
5040 years(7.00% + 0.75%) × 0.90 = 6.975%about $1,395,000
7045 years(7.00% + 1.00%) × 0.80 = 6.40%about $1,280,000
10050 years(7.00% + 1.25%) × 0.70 = 5.775%about $1,155,000

That’s our arithmetic on CMHC’s May 2025 schedule, not a quote; your lender calculates the actual premium. The longer amortization changes annual debt service far more than the premium does.

Programs that sit beside MLI Select

Choosing your points: a checklist

Most of these can be answered at feasibility, before any drawings exist.

  1. Does the project clear the basic tests? Units, commercial share, experience, net worth and the guarantee.
  2. What does each amortization do to the pro forma? Run debt coverage at 40, 45 and 50 years. If 40 works, 50 points may be enough.
  3. What’s the affordability gap? Market rent minus the cap, times the designated units, times the years, with the cap growing by CPI.
  4. Is the building already close to an energy level? If heat pumps and ERVs were planned anyway, ask where the first model lands. Energy Level 3 alone is 50 points.
  5. Can the suites be visitable without changing the plan? Corridor flats usually can; stacked townhouses and split-level suites usually can’t.
  6. Which points survive value engineering? Ask what happens to the score if the most expensive measure is cut.
  7. Who will sign? Name the energy modeller and accessibility consultant before the application.
  8. What if the target is missed? Ask your lender how a shortfall would be handled, and keep a margin in the design.

We’d make the points choice at the same meeting as the unit mix, while the budget is still being set. Our article on why the first budget matters most covers that stage.

Frequently asked questions

What are the requirements for MLI Select?

A rental project of at least five units (50 for retirement homes), non-residential space under 30% of floor area and lending value, a borrower with five years of rental management experience or a professional property manager, net worth of at least 25% of the loan, and at least 50 points from affordability, energy efficiency or accessibility. A CMHC-approved lender makes the application.

How many points do I need for a 50-year amortization?

At least 100 points. On new construction, that needs an affordability commitment, because energy and accessibility together reach only 80. The simplest routes are 25% of units at the affordable rent (100 points), or 10% of units at the affordable rent plus energy Level 3 (50 plus 50). A 20-year affordability commitment adds 30 points.

Does MLI Select apply to new construction?

Yes. MLI Select covers new construction and existing buildings, with separate points tables. For new construction, the affordability levels ask for a smaller share of units (10%, 15% or 25%) than for existing buildings, the energy levels compare the design with the 2020 national codes, and the loan can be advanced up to 95% of cost.

Can I lose MLI Select points after completion?

CMHC doesn’t publish a penalty schedule. The energy and accessibility points are confirmed by attestation within 60 days of the last advance; if the building falls short, the lender reports the circumstances to CMHC. Affordability is certified every year with the rent roll for the full commitment. Design with a margin and ask your lender how a shortfall would be handled.

Where to start

Start with the pro forma. Before you call a broker, know which points the site can earn cheaply and what the affordability gap costs. Bring the energy modeller and accessibility consultant in at concept, write the points target into the design brief, and carry it into the contract.

If you’d like an experienced hand to test a rental site against MLI Select and carry the points through design and construction, talk to us about development management. Our team’s experience was built at PCL Constructors and Oxford Properties, across more than 30 major projects in residential, office, retail and industrial buildings.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada