October 29, 2026

Performance Bonds in Construction: A Guide for Ontario Owners

A performance bond in construction is a promise from a surety company that if your contractor defaults, the surety will step in to get the work finished or pay toward the extra cost of finishing it, up to the bond amount. In Ontario it usually comes as a pair with a labour and material payment bond, which promises that the contractor’s subcontractors and suppliers will be paid. On public contracts of $500,000 or more, the Construction Act requires both, each for at least 50% of the contract price. On a private project they’re your choice, and you make it when you write the tender.

This guide is for owners deciding whether to ask for bonds, what to ask for, and what happens if you ever have to call on one. It’s practice, not legal or insurance advice: your lawyer reads the bond wording and your broker can tell you how a surety will see your project.

The three construction bonds, side by side

Every construction bond has three parties. The principal is the contractor whose promise is being backed. The surety is the insurance company that backs it. The obligee is the party the bond protects, which on a general contract is you, the owner.

A surety bond isn’t insurance for the contractor. The surety expects to be repaid by the contractor for anything it pays out, and contractors sign an indemnity agreement to that effect before a surety will bond them. That’s why a surety looks hard at a contractor’s finances, work on hand and track record before issuing a bond, and why bondability itself tells you something about a bidder.

The standard Canadian forms are the CCDC 220, 221 and 222 – 2024 bond forms, published on 21 May 2024 and the first update since 2002, according to the Surety Association of Canada.

Bid bondPerformance bondLabour and material payment bond
Standard formCCDC 220 – 2024CCDC 221 – 2024 (Form 32 on Ontario public contracts)CCDC 222 – 2024 (Form 31 on Ontario public contracts)
What it guaranteesThe winning bidder signs the contract and provides the contract bondsThe contractor performs the contractThe contractor pays its subcontractors and suppliers for labour and material on the project
Who can claimYou, as ownerYou, as ownerSubcontractors and sub-subcontractors who weren’t paid
Typical amountCommonly 10% of the bid50% of the contract price50% of the contract price
When it’s givenWith the bidOn signing, before work startsOn signing, before work starts
If it’s calledSurety pays up to the bond amount, generally the gap between the defaulting bid and the next oneSurety completes, arranges completion, or pays, up to the bond amountSurety pays valid claims, up to the bond amount

Sources: SAC webinar on the CCDC 2024 bond forms (June 2024); O. Reg. 304/18 s. 12.1 for the 50% figure on public contracts.

Alongside the bid bond, most tenders also ask for an agreement to bond (also called a consent of surety): the surety’s undertaking that it will issue the performance and payment bonds if this bidder wins. Our article on how the construction tender process works covers bid security in the context of the whole tender.

What “a 50% performance bond” means

The percentage is the bond amount as a share of the contract price. On a $6 million contract, a 50% performance bond has a bond amount of $3 million. That’s the most the surety will ever pay under it, however much the default costs. Within that cap, the surety covers the cost of completing the contract beyond what you still owe, until the $3 million is used up.

What Ontario law requires, and where

Public contracts

Since 1 July 2018, section 85.1 of the Construction Act has required a contractor on a public contract to give the owner both a labour and material payment bond and a performance bond on entering into the contract. A public contract is one where the owner is the Crown, a municipality or a broader public sector organization (school boards, hospitals, colleges and the like). The details:

Section 85.2 gives the right to sue on each bond: you on the performance bond if the contractor defaults, and any unpaid party the payment bond guarantees, directly against the surety. The surety never owes more than the bond amount (s. 85.2(3)).

Private contracts

Nothing in the Act requires a private owner to ask for bonds. If you want them, the tender documents and the contract have to say so: which bonds, what amount, which form and when they’re due. If the tender is silent, nobody prices them, and asking after award is a change to the deal.

Private owners can still borrow the public rules: sureties and contractors know the 50% figures and the CCDC forms. If your project has a lender, read the loan agreement before you tender; some lenders set bonding conditions of their own.

Ontario public contract ≥ $500,000Private contract
Bonds required?Yes, by s. 85.1Only if your tender and contract require them
AmountAt least 50% each (owner-set above $500M)Whatever you specify; 50% is the norm
FormForm 31 (payment) and Form 32 (performance)Usually CCDC 221 and 222 – 2024
SuretyLicensed in Ontario for surety and fidelitySpecify it; the same rule is sensible

The CCDC 2024 forms were built from Ontario’s Forms 31 and 32, with the Ontario-specific references taken out, so the claim process below is much the same under either.

How a performance bond claim works

A performance bond is conditional. The surety’s duty to act starts only once certain conditions are met, and the forms set out a timetable for what happens next. What follows is from CCDC 221 – 2024 (from the SAC specimen copy) and Ontario’s Form 32, which run in step.

What you have to have done first

The surety has no liability until all four conditions precedent are met (CCDC 221 s. 8.1):

  1. The contractor is in default under the contract, and you’ve declared it to be.
  2. You’ve given the contractor whatever notice of default the contract requires.
  3. You’ve performed your own obligations under the contract, which mostly means you’ve paid what was properly owed, when it was owed.
  4. You’ve agreed to pay the balance of the contract price to the surety, or as it directs.

The third and fourth conditions are where owners lose bond protection. The surety’s exposure is measured against the balance of the contract price: everything still payable to the contractor under the contract, less valid payments already made. If you paid ahead of the work, released holdback early or paid for work that wasn’t done, that money isn’t available to finish the job.

The timeline once you give notice

  1. Pre-notice meeting (optional). If you’re considering declaring a default, you can ask the surety for a meeting with you and the contractor. The surety proposes one within 7 business days. It’s without prejudice, and it’s often where a problem gets fixed before it becomes a claim.
  2. Notice. You give written notice to the surety on the form’s Schedule A, with a copy of the default notice you gave the contractor. Nothing else starts the surety’s obligations.
  3. Acknowledgement, within 4 business days. The surety confirms receipt and asks for the information it needs: the contract and changes, schedules, invoices, payments, holdback and correspondence.
  4. Post-notice conference, within 5 business days. You and the surety agree what work has to carry on while it investigates.
  5. Surety’s position, within 20 business days. The surety either accepts liability and names how it will deal with the default, declines with specific reasons, or says it can’t yet tell and may propose a way to keep the work moving.

While the investigation runs, you can carry out necessary interim work to keep the site safe or protect the work, telling the surety within 3 business days. You can also do mitigation work to keep critical activities going, paying for it first and keeping separate records, then recovering it once the surety’s liability is settled.

What the surety can do

Under CCDC 221 – 2024 the surety picks one of four options:

OptionWhat it means for you
Remedy the defaultThe surety works with the contractor to put the problem right, often with financing or support. The original contractor stays on.
Complete the contractThe surety takes over completion, usually by hiring a completion contractor it manages.
Tender the completionThe surety obtains bids, you and the surety agree the lowest responsible bidder, you sign with them, and the surety funds the gap between their price and the balance of the contract price.
PayThe surety pays the lesser of the bond amount and your completion cost plus direct expenses, less the balance of the contract price.

Ontario’s Form 32 gives the surety the same four options. Under both, the surety also covers your reasonable direct expenses caused by the default: extra professional and legal fees to complete, out-of-pocket costs, the cost of the extended period, and the interim and mitigation work. It doesn’t cover liquidated damages, financing costs, lost profit or other indirect losses unless everyone agrees otherwise. Delay is covered only through those direct costs of the longer period.

The time limit

Under Form 32, you have to start a lawsuit on the bond within two years of the earlier of substantial performance and the surety receiving your notice. CCDC 221 – 2024 changes the start date for CCDC contracts that use Ready-for-Takeover: the two years run from the earlier of Ready-for-Takeover and 180 days after substantial performance, but only if you send the surety a copy of the Ready-for-Takeover confirmation within 10 business days of it being issued. Otherwise the clock runs from substantial performance. Under both, an earlier notice date wins (s. 12.1). Our article on substantial performance in Ontario covers both milestones.

Labour and material payment bonds, liens and holdback

Who it protects

The payment bond protects the people below the contractor. Under CCDC 222 and Form 31, a claimant is anyone with a direct contract with the contractor for labour or material on the project (a subcontractor), or a direct contract with one of those subcontractors (a sub-subcontractor). A union or workers’ trust fund can claim wages and benefits for its members. Suppliers further down the chain aren’t claimants.

You’re the obligee, but you aren’t the one who claims, and Form 31 says you’re not obliged to take any action on a claimant’s behalf. What the bond does for you is indirect: the people most likely to register a lien on your property have someone solvent to collect from.

How a payment bond claim works

From Form 31 (rev. November 2025) and SAC’s summary of CCDC 222 – 2024:

StepTiming
Claimant gives a notice of claim to the surety, copied to the contractor and youWithin 120 days after the claimant last supplied labour or material (for holdback: within 120 days after it should have been paid in full)
Surety acknowledges and asks for information3 business days
Surety’s position to a subcontractorThe earlier of 10 business days after the information arrives and 25 business days after the notice
Surety’s position to a sub-subcontractorThe earlier of 15 and 35 business days
Surety pays the amounts it doesn’t dispute10 business days after its position
Claimant starts any lawsuit on the bondWithin 1 year after the contractor last performed work, including warranty work

If a claimant or the contractor starts an adjudication under the Act on the same dispute, the surety’s obligations pause until the adjudicator decides. Since 1 January 2026, adjudication can cover payment bond claim disputes directly, as Pallett Valo noted in March 2026.

Make sure the trades know there’s a bond

In Valard Construction v. Bird Construction, 2018 SCC 8, the Supreme Court of Canada held that the obligee under a payment bond, holding it as trustee for claimants, had a duty in those circumstances to tell an unpaid trade the bond existed, and breached that trust when the trade learned of it only after the claim deadline had passed (Law Times summary). The 2024 CCDC 222 responds by limiting the obligee’s role to a bare trust that carries no duty to notify claimants, and in Ontario s. 85.2 gives claimants their own right to sue the surety.

The practical answer costs nothing: post a copy of the payment bond in the site office, say in the contract that the contractor must tell its subcontractors about it, and keep a copy ready. A lien claimant can ask you in writing for a copy of any payment bond, and you have up to 21 days to give it (s. 39(1)).

Why it doesn’t replace holdback

A payment bond and holdback do different jobs, and you need both.

Under Form 32, the balance of the contract price you hold is applied first to the surety’s loss on the performance bond and then to the payment bond. That’s one more reason to keep payments in line with the work.

What bonds cost, and who pays

The contractor buys the bonds, and the premium is part of the bid price. So you pay for them, the same way you pay for the contractor’s insurance.

Sureties don’t publish rate cards, and premiums depend on the contractor as much as the project. As one published reference point, Ontario surety broker Roughley Insurance wrote in July 2025 that the combined premium for a performance bond and a labour and material payment bond “typically runs between 0.5% and 1.5% of the total contract amount including HST” for qualified contractors, with higher-risk contractors paying more. On a $5 million contract, that range works out to roughly $25,000 to $75,000. It’s one broker’s figure, not a survey.

What moves the premium:

There’s a second cost that doesn’t appear on the bid form. Every contractor has a bonding limit, both for a single job and for all the bonded work it carries. Require bonds on a large job and you’ve limited the field to contractors with that capacity. On a small private project, a bonding requirement can rule out capable local firms that simply don’t carry a surety facility. Prequalification is the place to check capacity: our guide to the CCDC 11 contractor’s qualification statement covers the bonding reference and the surety letter to ask for.

Should you require bonds on a private project?

Bonds earn their cost when a contractor default would be expensive and hard to recover from. Ask yourself what happens to your budget, your lender and your schedule if the contractor stops work halfway.

Bonds usually make sense when…Other security may be enough when…
The contract is large relative to the contractor’s own balance sheetThe contract is small, short, and well within the contractor’s means
Your financing depends on the project finishing on a fixed dateA delay would be inconvenient but not costly
You don’t know the bidders well, or the tender is openYou’re negotiating with a contractor you know, with a track record you’ve checked
The work is sequential and hard to hand over mid-stream (structure, envelope, major mechanical)The work is easy to re-tender in pieces (finishes, a fit-out with standard trades)
Many subcontractors with real lien exposureFew trades, little exposure above holdback
Your lender asks for them

On a construction management job, the same reasoning applies trade by trade: bond the large, high-risk packages and leave the small ones. Our article on CCDC 17 trade contracts covers security on trade packages.

The alternatives

The choice isn’t all or nothing. A performance bond without a payment bond, a lower percentage, or a letter of credit on a mid-sized fit-out are all reasonable, depending on what you’re protecting. We’ve made this call with owners on projects of very different sizes, and the answer usually comes from the same few questions: how big is the job relative to the contractor, how hard would it be to finish without them, and what does a delay cost you.

Writing bonds into the tender: a checklist

Bonds have to be in the tender documents, or nobody prices them. If you’re using CCDC 2, set bond requirements in the supplementary conditions (our CCDC 2 contract guide walks through them).

  1. Bid security. State the bid bond amount (commonly 10% of the bid) and the form, CCDC 220 – 2024, in the instructions to bidders. Set a bid validity period that matches your approval process.
  2. Agreement to bond. Require it with every bid, so the surety has committed before you award.
  3. Performance bond. State the amount (50% of the contract price is standard) and the form, CCDC 221 – 2024, or Form 32 on a public contract.
  4. Payment bond. State the amount and the form, CCDC 222 – 2024, or Form 31 on a public contract.
  5. Surety. Require a surety licensed in Ontario to write surety and fidelity insurance. Some owners also set a minimum financial rating; your broker can suggest one.
  6. Unaltered forms. Say the forms must be used as published. SAC notes that changes to the text risk the bond being treated as non-compliant.
  7. Delivery. Bonds before the contract is signed or before the first payment, with the original kept by you.
  8. Lender. If your lender wants to be named, ask your lawyer about adding it as a co-obligee, and settle it before tender.
  9. Pricing. Ask bidders to show the bond premium as a separate line, so you can see what security costs you.
  10. Subcontractor bonds. If you want the contractor to bond its major trades, say so and say which.
  11. Notice on site. Require the payment bond to be posted in the site office, and the contractor to tell its subcontractors it exists.
  12. Closeout. Add sending the Ready-for-Takeover confirmation to the surety within 10 business days to your closeout list.

Frequently asked questions

What is a 50% performance bond?

It’s a performance bond whose bond amount is half the contract price. On a $4 million contract, the surety’s maximum liability is $2 million. If the contractor defaults, the surety covers the cost of finishing the contract above the balance you still owe, plus your direct expenses, up to that $2 million.

Who pays for a performance bond?

The contractor buys the bond from its surety, and the premium is built into its bid, so the owner pays for it through the contract price. One Ontario broker puts the combined premium for performance and payment bonds at 0.5% to 1.5% of the contract amount for qualified contractors (Roughley Insurance, 2025).

Are bonds required on private projects in Ontario?

No. The Construction Act requires performance and labour and material payment bonds only on public contracts of $500,000 or more, where the owner is the Crown, a municipality or a broader public sector organization. Private owners decide for themselves, and have to put the requirement in the tender documents and contract so bidders price it.

What’s the difference between a performance bond and a labour and material payment bond?

A performance bond protects you, the owner, if the contractor fails to perform: the surety arranges completion or pays toward it. A labour and material payment bond protects the contractor’s subcontractors and their suppliers if the contractor doesn’t pay them, which reduces lien pressure on your project. Both are usually 50% of the contract price and are given together.

Where to start

If you’re about to tender, decide now whether the project needs bonds, which ones and at what percentage, and write them into the instructions to bidders and supplementary conditions before the package goes out. If a contractor is struggling on a bonded job, read the bond’s notice provisions, check your payments against the work, and talk to your lawyer before you declare a default.

We’ve spent more than 20 years on office, residential, retail and industrial projects, with experience built at PCL Constructors and Oxford Properties. Setting contract security, and administering payments so the bond keeps its value, is part of our construction consulting work on tendering and contract set-up.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada