CCDC 11 Contractor Qualification Statement for Ontario Owners
CCDC 11 – 2019 is the Contractor’s Qualification Statement: a standard form, published by the Canadian Construction Documents Committee, that a contractor fills in to tell an owner about its company, its capacity, its people and its experience before it’s invited to bid. The owner, or a consultant acting for the owner, asks for it. The contractor completes it. CCDC describes it as a form for prequalifying contractors and subcontractors “with or without a formal pre-qualification process”, so it works for a three-firm invited tender as well as a public request for qualifications.
It isn’t a contract and it isn’t free. It’s sold per copy through CCDC’s document outlets, electronic only, with a copyright seal that shows the copy hasn’t been altered. The current edition on ccdc.org on November 9, 2026 is still 2019.
The form collects the facts but doesn’t say which answers matter for your building or how to check them. This guide covers what each part of CCDC 11 asks, how to read a completed one, a sample way to score it, and how prequalification sits inside an Ontario tender. This is general guidance rather than legal advice. A public body, or anyone running a large competition, should have a lawyer review the documents.
What CCDC 11 is and when you’d ask for it
| Full name | CCDC 11 – 2019 Contractor’s Qualification Statement |
| Who fills it in | The contractor (or a subcontractor, if you’re prequalifying trades) |
| Who asks for it | The owner, or the consultant, owner’s rep or construction manager running procurement |
| What it covers | Company information, key personnel, and three lists of projects |
| What it costs | A per-copy price from a CCDC document outlet (provincial and local construction associations, RAIC) |
| Companion guide | CCDC 29 – 2016, A Guide to Pre-Qualification |
You’d ask for CCDC 11 any time you want to decide who gets the drawings before the prices come in. Common cases:
- An invited tender on a private project. You want three to five builders who can all carry the job, so that the lowest compliant bid is one you’d be glad to accept.
- Choosing a construction manager or a design-builder. Here the qualification decides more of the outcome than the fee does, so the form is the start of the evaluation, followed by interviews.
- A two-stage process. CCDC 29 is written as a framework for selecting prequalified proponents to take part in a second-stage request for proposals, for any delivery method and contract form.
- Prequalifying key trades. Mechanical, electrical, curtain wall or elevators on a construction management job, where the owner holds the trade contracts under CCDC 17.
The Ontario Association of Architects’ practice tip on prequalification of contractors (PT.18, May 2020) says the CCDC form “should be used as a primary source of pre-qualification information.” It also notes that on one project a CCDC 11 may be all that’s needed, while another calls for advertisements, a full request for qualifications and a scoring report. Size the process to the job.
CCDC 11, CCDC 29 and an RFQ
These three get mixed up. CCDC 11 is the form the contractor fills in. CCDC 29 is the guide for the owner on running prequalification: deciding whether it’s needed, choosing between unlimited prequalification, short-listing and a source list, writing the request for qualifications, evaluating, interviewing, notifying and debriefing. Its appendices include an example advertisement, invitation letter and evaluation form. A request for qualifications (RFQ) is your own document, the instructions that say what you want submitted, how it’ll be scored and how many firms go through. A good RFQ asks for a completed CCDC 11 plus anything specific to your project.
What the CCDC 11 form asks, section by section
CCDC sells the form rather than posting it, but full public copies circulate in municipal tender packages. We read the City of Surrey’s posted copy, which carries a 2018 copyright and matches the first page CCDC shows in its own 2019 one-page summary. CCDC announced the update for December 2019, which is why both dates appear. Check the details against the sealed copy you buy.
The cover page and confidentiality
The first page names the project (title, number, location), who it’s submitted to and who it’s submitted by. Then comes a confidentiality clause that’s easy to skim past: everything in the form is submitted in confidence and can’t be disclosed without the contractor’s written consent. If the owner gets a request for it, including under freedom of information law, the owner must tell the contractor promptly and give it a chance to object before anything is released.
Handle the forms as confidential business information. Public owners should know in advance how their access-to-information rules treat them.
Company information
Six numbered parts:
- Legal structure. Year established; corporation, partnership, joint venture, registered sole proprietor or other; the names and titles of officers, partners or principals.
- Financial reference. The contractor’s bank, with a contact person.
- Bonding or other contract security reference. The surety company and a contact.
- Insurance references. Whether the contractor carries general liability of $5,000,000 or more, automobile liability of $5,000,000 or more, and broad form contractors’ equipment insurance, each with insurer and broker contacts.
- Health and safety. Whether it holds a Certificate of Recognition (COR), an equivalent, or (failing both) details that show its safety plan works. Then three calendar years of workers’ compensation figures: industry classification code, industry base rate, the company’s own experience rate, fatalities, lost-time incident frequency (LTIF) and total recordable incident frequency (TRIF), both based on 200,000 hours.
- Value of construction work. Projected for the current year and actual for each of the past four.
Qualifications and experience of personnel
Two lists, each with résumés attached: key office personnel proposed for this submission (the form’s examples are project executive, project director and project manager) and key site personnel (superintendent, health and safety officer).
Project experience and the declaration
Unless your RFQ says otherwise, the contractor lists five projects in each of three appendices:
- Appendix A: key construction projects completed in the past five years.
- Appendix B: comparable projects completed, “similar type, size and complexity”.
- Appendix C: key projects underway on the date of the submission.
Each project entry asks for location, substantial completion date, completion date, value at completion, the project manager and superintendent, the owner and consultant with a contact person for each, the contract type (design-bid-build, construction management, design-build, prime contractor or subcontractor) and a description of the scope.
The form closes with a declaration, signed by the contact person, that the information is “true and correct to the best of my knowledge.” A space on each page takes the CCDC 11 copyright seal, which the form says shows the parties intend it to be an accurate and unamended version.
How to read and verify a completed CCDC 11
Most contractors who answer an RFQ are capable builders. The form’s job is to show you which of them suit this project, at this size, with this team, right now. Read each one with that question in mind, and verify the answers that would change your shortlist.
- Legal structure and principals. Check the legal name matches the one that’ll sign the contract and give the bid bond. A joint venture should say who the partners are and which one leads. Look up the corporation in the Ontario Business Registry if anything looks off.
- Years established. A young company isn’t a weak one; often it’s experienced people under a new name. Read it alongside the résumés.
- Annual volume, four years plus current. Compare your job with a typical year. A $12M project for a firm doing $15M a year is most of its business; for a firm doing $150M it’s one job among many. Neither is wrong, but they’re different relationships. A sharp drop or spike deserves a question.
- Work underway (Appendix C). Add up what’s on the books and compare it with annual volume and your timing. If your job would start when three large projects are in full swing, ask who’d be available.
- Comparable projects (Appendix B). Look for your building type, size, site conditions and contract form. A firm with ten good office towers and no occupied renovations may be the wrong fit for a phased retrofit, and the reverse holds too.
- The named project manager and superintendent. These are the people you’ll deal with daily. Check that the same names appear on the projects listed, and get your RFQ to say whether the people proposed must be the people assigned.
- References. Call the owner and the consultant on two or three projects, not the ones the contractor picks for you. Questions below.
- Financial reference. With the contractor’s permission, a bank reference will usually confirm the relationship and that it’s in good standing. For a larger job, ask for financial statements in the RFQ, reviewed under a confidentiality undertaking.
- Bonding. Ask for a letter from the surety confirming the contractor’s single-project and aggregate capacity, and that it would bond this project. More on this below.
- Insurance. The form asks whether limits are $5M or more. CCDC 41 – 2020, the insurance schedule CCDC 2 – 2020 points to, asks for $10M general liability and $10M automobile liability. Ask for the actual limits and a certificate from the broker, and check them against the contract you’ll sign.
- WSIB. Ask for a current WSIB clearance certificate. Under the Workplace Safety and Insurance Act, a person who directly retains a construction contractor can be held liable for its unpaid premiums unless it has a clearance before work begins. Clearances are valid for up to 90 days, so at prequalification it’s a check of good standing, not the one you’ll rely on at contract.
- COR. In Ontario construction, the Certificate of Recognition is administered by the Infrastructure Health & Safety Association (IHSA), which publishes a list of certified members. Under IHSA’s COR program guidelines, certification is valid for three years provided the employer passes internal maintenance audits in years two and three, and a Letter of Good Standing is issued for each of those years. Ask for the certificate and the current letter and check the dates.
Reading the safety numbers
LTIF and TRIF “based on 200,000 hours” are rates per 100 full-time workers a year (100 people × 40 hours × 50 weeks). They let a 40-person firm and a 400-person firm be compared on the same scale. Read three years together and look at the trend; a small firm’s rate can swing a long way on one incident. Ask what happened and what changed.
The form’s “industry base rate” and “company’s experience rate” come from the older way of setting workers’ compensation premiums. In Ontario, the WSIB moved to a new rate framework in 2020. Each class has a class rate based on its collective risk, and each business is placed in a risk band above or below it, using six years of insurable earnings, claims costs and allowed claims. So for an Ontario contractor, read the form’s two rate lines as the class rate and the company’s own premium rate. A company rate below its class rate means its claims history is better than its peers’. Ask the contractor to say which figures it’s given you.
Calling the references
Make these calls yourself; they’re the most useful part of the exercise. Ask the past owner, in plain words:
- Did they finish when they said they would? If not, why?
- How did they price changes? Did the final cost surprise you?
- Who ran the job, and would you want the same people again?
- How did they handle a problem they caused?
- Were the trades paid on time? Any liens?
- How long did the deficiency list take to close?
- Would you hire them again for the same kind of project?
If the answer to the last question is anything other than a clear yes, ask why.
Scoring CCDC 11 submissions and shortlisting contractors
The OAA’s advice in PT.18 is to build a point system to suit the project’s priorities, keep it “as clear and simple as practical, minimizing discretionary ratings,” get the owner’s agreement to the weights first, and tell the respondents in the instructions how the list will be chosen: for example, the top five scores, or everyone above a set mark. The consultant reports the results; the owner makes the decision.
A workable structure has two parts.
Pass or fail first. Set a few mandatory requirements that a firm either meets or doesn’t: a complete, signed, sealed CCDC 11; a surety letter for a project of this size; insurance that meets your contract; a current WSIB clearance; COR or an equivalent, if you require it. Keep the list short, so no capable firm is ruled out on a technicality.
Then score. Here’s an example of how an owner might weight a private mid-size office or residential project. It’s a sample to adapt, not a rule.
| Criterion | What you’re scoring | Example weight |
|---|---|---|
| Comparable experience | Appendix B projects of similar type, size, complexity and delivery method | 30 |
| Proposed project manager and superintendent | Their own record on similar jobs; whether they’re committed to yours | 25 |
| Capacity | Annual volume and work underway against your size and start date | 15 |
| References | Structured calls with past owners and consultants | 15 |
| Health and safety | COR or equivalent; three-year trend in LTIF and TRIF | 10 |
| Company stability | Years established, financial reference, surety relationship | 5 |
| Total | 100 |
Weights should follow what makes your project hard. On an occupied hospital renovation, safety and phasing experience would carry more. On a straightforward warehouse, capacity and price competitiveness matter more than design complexity. Write down what each score means (what earns a 5 out of 5 on comparable experience, what earns a 2) before anyone opens a submission, and score every firm against the same sheet.
Interviews and the short list
For a construction manager or design-builder, add an interview with the people who’d run the job, after the paper scoring. Give every firm the same questions and the same time. For a stipulated price tender they’re optional.
How many to shortlist is covered in our guide to the construction tender process in Ontario. The short version is enough firms for a real comparison and few enough that good contractors think it’s worth the cost of bidding.
Bonding capacity in CCDC 11 versus the bonds at tender
CCDC 11 asks only for a bonding reference: the surety’s name and a contact. That tells you the contractor has a surety relationship. It doesn’t tell you the size of it. Sureties underwrite each contractor for a limit on a single project and a limit on all the bonded work it carries at once, and a contractor near its aggregate limit may not be able to bond your job even if it’s done larger ones.
So the prequalification stage is where you confirm capacity: a letter from the surety, on its letterhead, saying it would expect to provide bonds for a project of your size and type, subject to its usual underwriting at the time.
The bonds themselves come later, at tender and contract:
| Stage | What you ask for | What it does |
|---|---|---|
| Prequalification (CCDC 11) | Bonding reference and a surety capacity letter | Confirms the contractor can be bonded for a job your size |
| Bid | Bid bond (CCDC 220 – 2024) or other bid security, plus an agreement to bond | Backs the bidder’s promise to sign and provide the contract security if chosen |
| Contract | Performance bond (CCDC 221) and labour and material payment bond (CCDC 222) | Backs completion of the work and payment of the trades |
A bid bond doesn’t guarantee the performance bond will follow, which is why many instructions to bidders also ask for a surety’s consent or agreement to bond with the bid. Our guide to performance bonds in Ontario covers when to require bonds, what the forms say and what happens if one is called. On public contracts of $500,000 or more, the Construction Act requires performance and payment bonds; on private work it’s your choice. If you won’t require bonds at contract, a capacity letter at prequalification is still a useful sign of a firm’s financial standing.
CCDC 11 inside a tender: invited, open and prequalified routes
Prequalification changes how a tender behaves legally, so it pays to set it up deliberately.
Open tender. Anyone can bid. You can still ask every bidder to submit a CCDC 11 with its bid and set minimum qualifications in the instructions. A bid that fails a mandatory qualification can be rejected, but only on criteria that were written in the documents before the bids came in.
Invited tender. You choose who bids. Even when you invite firms you already know, a CCDC 11 from each gives you the same information in the same order, and a record of how the contractor was chosen.
Prequalified tender. A formal RFQ produces the list, and only firms on it receive the bid documents. This is where the legal expectations sharpen. In Canada a formal tender creates a contract with every compliant bidder, “Contract A”, the moment its bid is submitted; our tendering guide explains the Supreme Court cases behind that. The OAA’s PT.18 adds a specific warning for prequalification: despite a privilege clause that lets you pass over the lowest bid, a prequalification process “creates legal expectations that the award will go to the lowest bid from a pre-qualified bidder.” Owners should get their own legal advice on that.
In practice that means:
- Apply the criteria as written. If the RFQ says the top five scores go through, the top five go through. If you need to change a criterion, change it by addendum to everyone before submissions close.
- Don’t re-run the qualification at the bid stage. Once a firm is on the list, its bid should be judged on the tender’s terms, not on a second look at its experience. If you have a real concern about a prequalified firm, deal with it before the tender is issued, with advice.
- Treat every respondent the same. Same documents, same deadlines, same answers to questions, same debrief offer.
- Keep the record. Each evaluator’s scores, the reference call notes and the reasons for the list. If anyone challenges the result, that record is your answer.
- Tell everyone the outcome. OAA’s procedure ends with informing all proponents of the results. A short, honest debrief is also how a good firm decides to answer your next RFQ.
Prequalification also suits the contract you’re tendering. For a stipulated price job under CCDC 2, it’s what lets the price decide. For a construction manager under CCDC 5A or 5B, where the CM advises during design and the price comes later, the qualifications and interview carry most of the selection, and the CCDC 11 is the starting point for both.
Public owners and CCDC 11
Municipalities, school boards, hospitals, universities, colleges and other public bodies run prequalification inside rules they don’t write themselves.
Broader public sector organizations follow Ontario’s Broader Public Sector Procurement Directive (effective April 13, 2026). On prequalification it sets out several mandatory requirements:
- A Request for Supplier Qualification (RFSQ) is the tool for prequalifying suppliers, for an immediate need or ahead of future competitions, and its terms must disclaim any obligation to call on a prequalified supplier.
- A response to a request for information or expressions of interest must not be used to prequalify a supplier.
- Evaluation criteria must be approved before the process starts, the documents must set out the mandatory and rated criteria with the weight of each, and criteria can be changed only by addendum.
- An evaluation team rates the submissions, each member signs a conflict-of-interest declaration and a non-disclosure agreement, completes an evaluation matrix, and the scores are kept for audit.
- The documents must include a bid dispute procedure, and on procurements of $139,000 or more, unsuccessful suppliers are entitled to a debriefing.
A CCDC 11 fits neatly inside that structure as the submission form, with the RFSQ supplying the weights and procedure.
Municipalities are required by the Municipal Act, 2001 (s. 270) to adopt and maintain a policy on their procurement of goods and services. Each one’s procurement by-law sets its own thresholds, whether and how it prequalifies, and how it records vendor performance. If you’re a municipal project manager, the by-law comes first and CCDC 11 is a form you can use within it. The Buy Ontario directives, in force since 2026, can add requirements on capital infrastructure; our tendering guide summarizes them.
The CCDC 11 confidentiality clause matters most here. Public bodies in Ontario are subject to freedom of information law, and the clause commits the receiving party to notify the contractor and let it make submissions before disclosing. Make sure your procurement team knows the clause is there and how your own access-to-information process handles third-party commercial information.
Frequently asked questions
What is a CCDC 11?
CCDC 11 – 2019 is the Contractor’s Qualification Statement, a standard Canadian form a contractor fills in to describe its company, finances, bonding and insurance references, safety record, annual volume, key people, and three lists of five projects each. Owners and consultants use it to prequalify contractors and subcontractors before a tender. It’s sold through CCDC document outlets and carries a copyright seal.
Is CCDC 11 mandatory?
No law requires it. A private owner can prequalify any way it likes, or not at all. Public owners must follow the BPS Procurement Directive or their own procurement by-law, which set the process but generally don’t name a form. Many owners and consultants ask for CCDC 11 because every contractor already knows it, and the OAA recommends it as the primary source of prequalification information.
What’s the difference between CCDC 11 and an RFQ?
The RFQ is your document: what you’re building, what to submit, how it’ll be scored and how many firms go through. CCDC 11 is the standard form the contractor fills in as part of its response. Most RFQs ask for a completed CCDC 11 plus project-specific items, such as a surety capacity letter, proposed staff commitments, a safety program summary or financial statements.
How many contractors should you prequalify?
Enough for a real price comparison and few enough that each firm thinks it’s worth bidding. On private work three to five is a common short list. Ontario’s BPS Directive defines an invitational procurement as asking at least three qualified suppliers. Decide the number, or the pass mark, before you score, and say so in the RFQ.
Where to start
If you’re a few months from tender, decide now whether you’ll prequalify and how. Write a short RFQ: what the project is, the timing, a completed and sealed CCDC 11, a surety capacity letter, the named project manager and superintendent, and the mandatory requirements. Set out the scoring, agree the weights with your consultant team, then issue it and leave enough time for reference calls before the tender goes out.
If you’ve already collected the forms, work through the twelve checks above with each one in front of you, call the references, and score every firm on the same sheet. The result should be a list where any bidder could build your project well.
We’ve spent more than 20 years on office, residential, retail and industrial projects across BC, Alberta, Ontario and Quebec, with experience built at PCL Constructors and Oxford Properties. Building a short list, running the RFQ and checking the answers is part of our preconstruction planning, from shortlist to tender. If you’d like an experienced hand beside you while you choose your contractor, that’s where to start.