October 29, 2026
CCDC 41 Insurance Requirements Explained for Ontario Owners
CCDC 41 is the one-page schedule of insurance requirements that most Canadian standard construction contracts point to. The current edition is CCDC 41 – 2020, published on December 14, 2020, and it’s free from CCDC. It sets the minimum limits and deductibles for the policies your contractor buys: general liability and automobile liability at $10 million, builder’s risk (“broad form” property) at 1.1 times the contract price, plus boiler and machinery, contractors’ equipment, pollution liability, and aircraft, watercraft and drone liability where they’re used. Your contract, usually CCDC 2 – 2020, then says who holds each policy, for how long, and who pays a deductible.
This guide reads CCDC 41 from the owner’s side: what each policy is for, what changed in 2020, when cover ends, what you still insure yourself, and how to check the certificate. Your broker sets the insurance program and your lawyer drafts the supplementary conditions; this is what to read and ask about before they do.
Where CCDC 41 sits in your contract
CCDC 41 isn’t a contract on its own. Nobody signs it. It’s a schedule that the contract incorporates by reference, so the numbers in it become contract terms without being printed in your agreement.
In CCDC 2 – 2020, the standard stipulated price contract, the link is GC 11.1.1. The contractor “shall provide, maintain and pay for the following insurance coverages, the requirements of which are specified in CCDC 41 ‘CCDC Insurance Requirements’ in effect at the time of bid closing” (CCDC 2 – 2020 text). Three things follow from that sentence:
- The contractor pays. The premiums are in its price. Under a cost-plus or construction management contract they become a reimbursable cost instead, which is how CCDC 3 and similar cost-plus contracts treat them.
- The edition is fixed at bid closing. If CCDC publishes a new CCDC 41 mid-project, GC 11.1.6 to 11.1.8 deal with it: a reduction is discussed before the contractor’s policy renews, an increase can be requested by Change Order, and a Change Directive can’t be used to force either.
- Your supplementary conditions can change any of it. Many public owners replace GC 11.1 entirely. More on that below.
The same schedule sits behind other CCDC forms. Aon’s overview of the 2020 amendments lists CCDC 5B, CCDC 14 and CCDC 17 among the contracts that reference CCDC 41, along with some provincial subcontract forms. So if you’re comparing CCDC 5A and 5B for a construction management project, or a CCDC 14 design-build contract, the insurance minimums start from the same page. The newer forms have moved the timing, which we cover in the section on when coverage ends.
The policies CCDC 41 requires
CCDC 41 – 2020 has eight numbered items. The table puts each in plain words, quoting the limits and deductibles as the form states them (CCDC 41 – 2020). The “named on it” and “how long” columns come from GC 11.1.1 of CCDC 2 – 2020.
| # | Policy | What it covers, in plain words | Minimum limit | Deductible | Named on it (CCDC 2) | How long (CCDC 2) |
|---|---|---|---|---|---|---|
| 1 | General liability | Injury to people and damage to other people’s property caused by the contractor’s work, including after you move in (completed operations) | $10,000,000 per occurrence; $10,000,000 aggregate per policy year for completed operations | Not more than $10,000, unless you agree to more | Contractor, with you and the Consultant as insureds for liability arising from the contractor’s operations | From the start of work to 1 year after Ready-for-Takeover; completed operations for 6 years after it |
| 2 | Automobile liability | The contractor’s own and leased vehicles | $10,000,000 per occurrence | Not stated | Contractor | Start of work to 1 year after Ready-for-Takeover |
| 3 | Manned aircraft and watercraft liability | Helicopters, barges and boats, if any are used for the work | $10,000,000 per occurrence; $10,000,000 aircraft passenger hazard | Not stated | Contractor | When used |
| 4 | Unmanned aerial vehicle liability | Drones used for the work, the contractor’s or a hired operator’s | $5,000,000 per occurrence, or more if the law requires | Not stated | Contractor | When used |
| 5 | ”Broad form” property (builder’s risk) | Physical loss or damage to the building under construction and the materials for it | 1.1 × Contract Price, plus the full value of products and design services you’re supplying | Not more than $10,000, unless you agree to more | Contractor, you and the Consultant jointly; all subcontractors as insureds | Start of work to the earliest of three triggers (see below) |
| 6 | Boiler and machinery | Boilers, pressure vessels and similar equipment in the work, including hot testing and commissioning | Replacement value of those objects | Not stated | Contractor, you and the Consultant jointly; subcontractors as insureds | From first use of the equipment to 10 days after Ready-for-Takeover |
| 7 | Contractors’ equipment | The contractor’s own cranes, lifts, tools and machinery, on an “all risks” basis | In a form acceptable to you | Not stated | Contractor; no subrogation against you | Start of work to 1 year after Ready-for-Takeover |
| 8 | Contractors’ pollution liability | Injury and property damage from pollution caused by the work | $5,000,000 per occurrence | Not stated | Contractor | Not listed in GC 11.1.1 |
A few of these need more than a table cell.
General liability
This is the policy that answers when a passer-by is hurt or a neighbour’s foundation cracks during excavation. CCDC 41 sets the floor at the standard Insurance Bureau of Canada wording (IBC Form 2100) and lets the contractor reach $10 million with an umbrella or excess policy on top of a smaller primary one, so on the certificate the limit often appears as two lines that add up.
The detail owners miss is completed operations. Under GC 11.1.1.1 the contractor keeps liability cover for its completed work for six years after Ready-for-Takeover. A leak or a falling piece of cladding in year three is still a claim against the contractor’s policy, as long as the policy is kept in force. Ask for a certificate showing it each year, or at least at the one-year mark when the main liability period ends.
”Broad form” property, or builder’s risk
Builder’s risk insures the work itself: the half-built structure, materials on site and the temporary works. The limit is 1.1 times the contract price, so a $10 million contract carries at least $11 million of cover. If you’re supplying products or design services that go into the work, their full value is added on top. CCDC 41 requires cover at least as broad as IBC Forms 4042 and 4047, the standard builder’s risk wordings.
Under CCDC 2 the policy is in the joint names of the contractor, you and the Consultant, and it pays “as their respective interests may appear” (GC 11.1.1.6). In plain terms, after a fire the contractor adjusts the loss with the insurer on your behalf, rebuilds, and is paid for your share of the restoration through the normal progress payment process. It also gets a reasonable extension of time.
The smaller items
Boiler and machinery cover must include hot testing and commissioning, when a chiller or boiler is first run under load. Contractors’ equipment insurance can’t allow the insurer to come after you (no subrogation) if a lift is damaged on your site, and you can waive it if the contractor proves it can self-insure. Pollution liability matters on any site with fuel storage, contaminated soil, designated substances in an existing building, or dewatering. GC 11.1.1 of CCDC 2 – 2020 doesn’t name pollution liability in its list, though CCDC 41 does and Aon reads it as required; if you want it, say so in your supplementary conditions.
What CCDC 41 doesn’t include
There’s no professional liability item: designers carry their own under their own agreements, including on design-build. There’s no wrap-up item either (covered below), and no workers’ compensation. Under CCDC 2 – 2020 that’s a separate obligation in GC 10.4: WSIB evidence before work starts and with every application for payment, and from the second application on, the CCDC 9A statutory declaration goes in with it.
Deductibles and the 2020 changes
What changed from 2008 to 2020
The 2020 edition increased the minimums and added two policies. Aon’s overview of the changes and Osler’s January 2021 summary agree on the main points:
| Item | CCDC 41 – 2008 | CCDC 41 – 2020 |
|---|---|---|
| General liability limit | $5,000,000 | $10,000,000 |
| General liability deductible | $5,000 | Not more than $10,000 |
| Automobile liability | $5,000,000 | $10,000,000 |
| Manned aircraft and watercraft | $5,000,000 | $10,000,000 |
| Unmanned aerial vehicle (drone) | Not separately required | $5,000,000 |
| Builder’s risk deductible | $5,000 | Not more than $10,000 |
| Contractors’ pollution liability | Not required | $5,000,000 per occurrence |
Aon makes a fair point about the higher liability limit: it reflects a view that $5 million had become inadequate on most projects, not that every project needs $10 million or more. On a small fit-out a lower limit may be reasonable, and on a tower next to occupied buildings it may be too low. That’s a decision for you and your broker before tender, written into the supplementary conditions so every bidder prices the same thing.
Who pays the deductible under CCDC 2
Two separate questions get confused here: how big the deductible can be, and who pays it.
How big. CCDC 41 caps the general liability and builder’s risk deductibles at $10,000. You can agree to a higher deductible “subject to satisfactory proof of financial capability by the Contractor.” Contractors often ask for this, because their corporate program may carry a larger deductible than $10,000. Agreeing is reasonable when the contractor’s finances support it; ask your broker what they’d want to see.
Who pays. CCDC 2 – 2020, GC 11.1.3: “The parties shall pay their share of the deductible amounts in direct proportion to their responsibility in regards to any loss for which the above policies are required to pay, except where such amounts may be excluded by the terms of the Contract.” So if the contractor’s crew causes a fire, the contractor bears the deductible. If your own separate contractor causes the loss, you bear it. If both contributed, it’s split.
CCDC 14 – 2026, the design-build form, uses the same proportional rule with one addition: where the responsible party isn’t bound by the contract, such as one of your own separate contractors, the owner pays the deductible (Fasken via Mondaq, June 2026).
When a Change Directive is valued at cost, losses that fall within a deductible or exceed the policy limits count as part of the contractor’s cost (CCDC 2 – 2020, GC 6.3.7.13). That’s a narrow case on a stipulated price job. On a cost-plus contract, check how the cost of the work treats deductibles: where they’re reimbursable, a higher deductible is partly your money.
The wrap-up option
A wrap-up is a single general liability policy that the owner buys for the whole project, covering the owner, the contractor, every subcontractor and the consultants for liability arising from the work. It replaces item 1 of CCDC 41 for the project, while the contractor keeps its own automobile, equipment and other policies.
Owners choose a wrap-up on larger projects so that one policy and one adjuster answer when something goes wrong, with no gaps between trades’ policies. The owner buys and administers it, and the contractor’s price should come down by the liability premium it no longer needs.
There’s no wrap-up clause in CCDC 41 or CCDC 2, so it’s written into the supplementary conditions. British Columbia’s government publishes its owner-controlled provisions for CCDC 2 – 2020 (BC Risk Management Branch, revised March 2023) as a worked example: the owner’s wrap-up is $10 million per occurrence and $20 million aggregate, covers the owner, contractor, subcontractors and consultants but excludes professional services, and the contractor keeps its own general liability for any period when the wrap-up isn’t in force. It’s another province’s set, so borrow the structure and get the wording from an Ontario broker and lawyer.
When coverage starts and ends
Every policy runs from the commencement of the work. The end dates are tied to Ready-for-Takeover, the contractual milestone that CCDC 2 – 2020 added after substantial performance. Our guide to substantial performance and takeover in Ontario explains how the two differ and what Ready-for-Takeover requires.
The builder’s risk triggers
Builder’s risk is the policy whose end date matters most, because the day it stops, the building becomes yours to insure. GC 11.1.1.4 keeps it in place until the earliest of:
- 10 calendar days after the date of Ready-for-Takeover;
- the start of use or occupancy of any part of the work, unless the use is for construction, habitational, office, banking, a convenience store under 465 square metres, parking, or installing, testing and commissioning equipment that forms part of the work;
- the work being left unattended, or construction activity stopping, for more than 30 consecutive calendar days.
The second trigger catches owners out. If you move retail tenants or a restaurant into part of the building before Ready-for-Takeover, that use isn’t on the list, and the builder’s risk policy can end on that day. Early occupancy under GC 12.2 needs a call to both brokers first. The third trigger matters if a project is paused for financing or a permit problem: a month of inactivity and the policy can lapse.
CCDC explained the 10-day window in Bulletin 27 (August 2024). Once the project reaches Ready-for-Takeover it’s no longer “in the course of construction,” and the 10 days give the owner time to place its own property insurance. If the contractor damages the building while fixing deficiencies afterwards, CCDC notes you still have recourse against its general liability insurance.
The other end dates
| Policy (CCDC 2 – 2020) | Ends |
|---|---|
| General liability | 1 year after Ready-for-Takeover |
| Completed operations cover | 6 years after Ready-for-Takeover |
| Automobile liability | 1 year after Ready-for-Takeover |
| Builder’s risk | Earliest of the three triggers above |
| Boiler and machinery | 10 days after Ready-for-Takeover |
| Contractors’ equipment | 1 year after Ready-for-Takeover |
Two related dates move with Ready-for-Takeover too: the indemnity claim period of six years in GC 13.1 and the waiver of claims in GC 13.2.
The 2025 and 2026 forms
The newer construction management and design-build forms follow the same pattern. In CCDC 5A, 5B and 17 – 2025, Ready-for-Takeover replaces substantial performance as the trigger for insurance timelines, along with the warranty, the indemnification period and the waiver of claims (Miller Thomson, 2025). In CCDC 14 – 2026 the warranty and the waiver of claims run from Ready-for-Takeover, while holdback is still released from substantial performance under the Construction Act (Osler, July 2026). Your closeout schedule needs both dates.
What the owner insures
CCDC 41 is about the contractor’s insurance. You still have some of your own to arrange, and the gaps are where owners get surprised.
Your existing building in a renovation
Builder’s risk under CCDC 41 covers “the Work”: what the contractor is building, valued at 1.1 times the contract price. It doesn’t insure the existing building around it. On a renovation, an addition or a fit-out in a building you already own, the existing structure, its contents and your loss of income stay on your own property policy throughout.
Tell your property insurer about the project before work starts. Policies commonly ask to be told about major construction, and some restrict cover while it’s under way. Your broker can confirm how your own policy and the contractor’s builder’s risk fit together, and whether it makes more sense for you to extend your own policy to cover the work instead.
Other contractors you hire directly
If you bring in your own trades or suppliers alongside the general contractor, CCDC 2 GC 3.2.2.3 requires you to make sure they carry insurance “to the same requirements as are called for in GC 11.1” and to coordinate it with the contractor’s. In practice that means giving every direct contractor the same CCDC 41 schedule and collecting their certificates.
After Ready-for-Takeover
From 10 days after Ready-for-Takeover, or sooner if a trigger above applies, you insure the completed building. Call your broker when the contractor applies for substantial performance, not when the certificate arrives.
A tenant fit-out
If you’re a tenant building out leased space, your lease usually sets insurance requirements of its own for the work: the landlord named as an additional insured, specific limits, and certificates delivered before you start. Those requirements sit beside CCDC 41, not inside it. Give your contractor the landlord’s list along with CCDC 41 at tender, so the price covers both. Our article on leasehold improvements in Ontario covers the rest of the landlord approval process.
Supplementary conditions owners add
Public and institutional owners often replace GC 11.1 with their own wording. Reading one published set is the quickest way to see what owners change and why.
The York Region District School Board’s supplementary conditions to CCDC 2 – 2020 (version May 2022) delete GC 11.1 and replace it. Among the changes:
- Deductibles move to the contractor. The new 11.1.2 makes the contractor responsible for deductibles, except where the protection-of-work and toxic substances clauses (GC 9.1 and 9.2) say otherwise. That replaces the shared-by-responsibility rule.
- Builder’s risk runs longer. Cover is maintained until 10 days after the final certificate of payment, rather than 10 days after Ready-for-Takeover, and the policies must allow partial or total occupancy.
- Some limits change. General liability stays at $10 million with the owner and Consultant as additional insureds. Automobile liability is set at $5 million and aircraft and watercraft at $2 million, below the CCDC 41 – 2020 figures.
- Notice of cancellation. Policies are endorsed to give the owner at least 30 days’ written notice before cancellation or any change that restricts coverage.
- Pollution cover is expanded to include clean-up and remediation costs for work on municipal land and highways.
- Insurance goes into the payment package. A current certificate of insurance, if the owner asks for it, is listed among the documents for an application for payment.
Thirty days’ notice of cancellation and a current certificate with payment applications cost the contractor almost nothing and are worth copying on a private project. Other changes need care. CCDC’s own Bulletin 27 cautions that extending builder’s risk past Ready-for-Takeover “may not be permitted by the insurer” and can add cost or create a compliance problem if the insurer refuses. Moving all deductibles to the contractor will be priced into the bids. The point of reading a public owner’s set is to see the levers, then pick the ones that fit your project with your broker.
Other common changes: a higher limit on a large or high-risk site, and your lender or landlord added as additional insureds. GC 11.1.2 already gives you the right to a certified copy of the policies “if required.”
If you’re writing supplementary conditions before a tender, settle the insurance section early, because it affects every bid. Our guide to the construction tender process in Ontario covers the rest of the tender package.
Checking the certificate of insurance
GC 11.1.2 requires the contractor to give you confirmation of coverage before the work starts, and again whenever any of the insurance is placed, renewed, amended or extended. That confirmation is usually a certificate of insurance from the contractor’s broker. A certificate is a summary, not the policy, so it’s worth reading slowly against CCDC 41 and your own supplementary conditions.
- Named insured. The contractor’s legal name matches the name on your contract exactly.
- Project. The certificate names your project and address, or the contractor’s blanket policy covers all its projects and says so.
- You and the Consultant. Shown as additional insureds on the general liability policy, and as joint named insureds on builder’s risk and boiler and machinery. Add your lender or landlord if your agreements require it.
- General liability limit. $10 million per occurrence, or your supplementary conditions’ figure. If it’s a primary policy plus an umbrella, both appear and add up.
- Completed operations. Shown as included, with an aggregate of at least $10 million.
- Automobile liability. $10 million, or your figure, covering owned and leased vehicles.
- Builder’s risk limit. At least 1.1 times your contract price, plus anything you’re supplying. Recheck it after large Change Orders raise the price.
- Deductibles. Not more than $10,000 on general liability and builder’s risk, unless you’ve agreed in writing to more.
- Pollution, drone, aircraft and watercraft. Present where the work uses them. Pollution liability at $5 million per occurrence; check whether it’s written on an occurrence or a claims-made basis.
- Boiler and machinery. Present if the work includes boilers or pressure vessels, with hot testing and commissioning included.
- Contractors’ equipment. Present, or your written waiver is on file.
- Insurer. Licensed in Ontario, which GC 11.1.5 requires for the Place of the Work.
- Dates. Every policy is in force on the day work starts, and you have a diary date for each renewal. Ask for a new certificate before the old one expires, not after.
- Cancellation notice. If your supplementary conditions require notice before cancellation, the certificate or an endorsement says so.
If something’s missing, send it back before the contractor mobilizes; it’s usually an oversight the contractor’s broker fixes quickly. If it comes to that, GC 11.1.4 lets you buy the missing insurance yourself and recover the cost from the contractor.
Frequently asked questions
What is CCDC 41?
CCDC 41 – 2020 is the Canadian Construction Documents Committee’s schedule of insurance requirements. CCDC 2 and other standard contracts incorporate it, so its limits become contract terms. It sets the minimums for the contractor’s general liability, automobile, aircraft, watercraft, drone, builder’s risk, boiler and machinery, equipment and pollution insurance. It’s free on ccdc.org, and the edition that applies is the one in effect when bids closed.
Who pays the insurance deductible under CCDC 2?
Under CCDC 2 – 2020 GC 11.1.3, the owner and contractor pay their share of a deductible in direct proportion to their responsibility for the loss, unless the contract says otherwise. CCDC 41 caps the general liability and builder’s risk deductibles at $10,000 unless the owner agrees to more. Many public owners’ supplementary conditions move all deductibles to the contractor.
Does the owner need builder’s risk insurance?
Under CCDC 2 the contractor buys builder’s risk, in the joint names of the contractor, the owner and the Consultant, for at least 1.1 times the contract price. The owner doesn’t buy a separate policy for the new work, but does keep insuring any existing building and must insure the completed project from 10 days after Ready-for-Takeover, or sooner if the policy ends early.
What insurance should a contractor have in Ontario?
On a project under CCDC 2 – 2020, the contractor carries the CCDC 41 policies with insurers licensed in Ontario: $10 million general and automobile liability, builder’s risk, and the other policies where the work calls for them. WSIB coverage is a separate legal requirement. Your supplementary conditions can raise or lower the limits, and your broker should confirm they suit the project.
Where to start
If you’re about to tender, decide on the insurance before the documents go out: whether CCDC 41 – 2020 as written suits the project, whether you want a wrap-up, what your lender or landlord requires, and how you’ll handle your existing building. Put it in the supplementary conditions so every bidder prices the same thing. If the contract is signed and work is about to start, use the checklist above on the first certificate and put the renewal and Ready-for-Takeover dates in your calendar.
Our experience of contracts and closeout was built over 20+ years at PCL Constructors and Oxford Properties, across $3B+ of office, residential, retail and industrial projects. If you’d like an experienced hand to set up the insurance requirements with your broker and lawyer, review certificates as they come in, or plan the handover from builder’s risk to your own policy, that’s part of our construction consulting work.