How ODACC Construction Adjudication Works for Ontario Owners

ODACC (Ontario Dispute Adjudication for Construction Contracts) is the body Ontario has designated to run construction adjudication under Part II.1 of the Construction Act. Adjudication is a fast, interim decision on a payment dispute: either party to a construction contract can start one without the other’s consent, a certified adjudicator decides it within 30 days of receiving the claimant’s documents unless the parties agree to more time, and the amount decided has to be paid within 15 days. It is binding until a court, an arbitrator or a written agreement between the parties says otherwise. For an owner, it is a process you can handle calmly if your contract, invoices, notices and change records are in order.

Most of what’s written about ODACC is for lawyers and contractors starting a claim. This guide is for the owner. It isn’t legal advice. When a notice arrives, your construction lawyer advises on that notice; your job, and ours if we’re working with you, is to have the record ready.

What ODACC is and what adjudication does

The Construction Act lets the Minister designate an Authorized Nominating Authority (s. 13.2). ODACC holds that role. It trains and certifies adjudicators, keeps the public registry of them and appoints one when the parties can’t agree (s. 13.3). The parties pay the adjudicator’s fee through ODACC (O. Reg. 264/25, s. 23), and every adjudication runs through its online system. ODACC doesn’t decide disputes itself; the adjudicator does.

Adjudicators come from the industry. ODACC’s 2026 Annual Report says each has at least 10 years of construction experience, and lists project managers (27), engineers (23) and lawyers (20) as the largest groups on the registry, with arbitrators, quantity surveyors, mediators, architects and an accountant making up the rest. The person reading your file is likely to understand a schedule of values and a change order log without having them explained.

Three features set adjudication apart from anything else in your contract:

Adjudication sits on top of prompt payment, which came into force on October 1, 2019 together with Part II.1. If your contract was signed before then, or the procurement started before then, neither prompt payment nor adjudication applies to it (s. 87.3(4)).

What disputes can go to adjudication, and what changed in 2026

On January 1, 2026, amendments to the Construction Act came into force and O. Reg. 264/25 replaced the old adjudication regulation, O. Reg. 306/18. The list of matters that can be adjudicated moved out of the Act and into section 19 of the regulation. Some summaries describe the new scope as “any dispute about the contract”. The regulation is narrower than that, so it’s worth reading the list itself.

The matters you can adjudicate

Under s. 19(1) of O. Reg. 264/25, a party can refer:

  1. The valuation of services or materials provided under the contract.
  2. Payment under the contract, including for a change order, approved or not, or a proposed change order.
  3. A dispute that is the subject of a notice of non-payment under Part I.1 (prompt payment).
  4. Amounts retained as set-off by a trustee (s. 12) or as lien set-off (s. 17(3)).
  5. Payment of holdback under s. 26, which now includes the mandatory annual release.
  6. The scope of work, a request for a change in the contract price, or a request for an extension of time, if resolving it is reasonably necessary to decide one of the matters above.

The parties can also agree to adjudicate anything else (s. 13.5(1)). The same list applies between a contractor and its subcontractors (s. 19(2)).

Item 6 is the real expansion: scope, price changes and time extensions are in, but only as the route to a payment decision. A stand-alone claim for an extension of time, with no money attached, isn’t on the list unless both parties agree to it.

What owners actually see adjudicated

ODACC’s 2026 report (fiscal year August 1, 2025 to July 31, 2026) breaks down the 130 determinations made after the new rules took effect:

Matter (s. 19(1), O. Reg. 264/25)Determinations, Jan 1 – Jul 31, 2026
Payment under the contract, including change orders66
Valuation of services or materials51
Notice of non-payment disputes5
Scope, price change or time, as needed for another matter5
Holdback payment under s. 263
Set-off, or a matter agreed by the parties0

About nine in ten were about what the work is worth and whether it should be paid. Our guide to change orders in Ontario covers how to keep changes priced and agreed before they reach an invoice.

The other 2026 changes that affect owners

How an adjudication runs, day by day

The Act sets the clock. Here it is in order, with the section for each step. “Days” are calendar days unless your contract says otherwise.

  1. Day 0: notice of adjudication. The claimant gives the other party a written notice naming the parties, describing the dispute and how and when it arose, the redress sought, a proposed adjudicator, and any earlier adjudications on the same contract (s. 13.7(1)). A copy goes to ODACC electronically the same day (O. Reg. 264/25, s. 20).
  2. By day 4: the adjudicator agrees, or ODACC is asked. If the proposed registry adjudicator hasn’t consented within four days, the claimant must ask ODACC to appoint one (s. 13.9(4)). It must also ask straight away if there’s no prospect of agreement (O. Reg. 264/25, s. 22).
  3. Within 7 days of the request: ODACC appoints. ODACC must appoint a registry adjudicator, with their consent, no later than seven days after the request (s. 13.9(5)). There’s no ODACC fee for appointing one.
  4. Within 5 days of appointment: the claimant’s documents. The claimant sends the adjudicator the notice, and sends the adjudicator and you the contract and every document it intends to rely on, all on the same day (s. 13.11; O. Reg. 264/25, s. 24). The adjudicator confirms in writing the date these arrived. That date starts the 30-day clock.
  5. Your response, by the date the adjudicator sets. You may respond in writing (s. 13.11.1). There’s no fixed statutory number of days; the adjudicator specifies the date, and the response goes to the adjudicator and the claimant on the same day (O. Reg. 264/25, s. 25). If you object that the matter isn’t adjudicable, say so here (s. 13.12.1).
  6. The process the adjudicator sets. Some adjudications are on documents only; others add a video hearing, an in-person hearing or a site visit. ODACC publishes four suggested pre-designed processes, three of them in writing only, that the parties can recommend (ODACC, Adjudication Process). The adjudicator can ask questions, draw inferences from how the parties behave, inspect the site and bring in an expert such as a quantity surveyor or engineer (s. 13.12(1)).
  7. Day 30 after documents: the determination. It must be written, with reasons (s. 13.13(1), (6)). It can be extended by up to 14 days at the adjudicator’s request with both parties’ written consent, or longer by written agreement of the parties (s. 13.13(2)). A determination made late has no effect (s. 13.13(5)).
  8. Within 7 days: the certified copy. The adjudicator sends an electronic copy, then a certified copy within seven days (O. Reg. 264/25, s. 30).
  9. Within 5 days: corrections, if there’s an arithmetic slip or an oversight (s. 13.17.1).
  10. Within 15 days of the decision: payment. Whoever has to pay, pays (s. 13.19(2)). The amount is still subject to holdback (s. 13.19(1)). Late amounts carry interest at the prejudgment rate or the contract rate, whichever is higher (s. 13.19(3)).
  11. Within 35 days: judicial review, if at all. It needs leave of the Divisional Court, on narrow grounds such as bias, fraud, or a matter outside adjudication (s. 13.18). It doesn’t stop the payment unless the court orders it (s. 13.18(7)).

If every step takes its full statutory time and nobody extends anything, that’s about six and a half weeks from notice to decision. Extensions are common and usually agreed. In ODACC’s 2026 fiscal year, 55% of determinations came within the 30 days and the other 45% within a deadline the parties had agreed to extend. Every one was on time under the Act.

Of the 396 adjudications started that year, 117 were ended early by agreement, 54 of them because the parties settled (s. 13.14).

What adjudication costs, and who pays

Each side pays its own costs, including its own lawyer or consultant (s. 13.16). The adjudicator’s fee is split equally (s. 13.10(3)). The adjudicator can depart from both rules only if a party has acted in a way that’s frivolous, vexatious, an abuse of process or in bad faith (s. 13.17).

The adjudicator’s fee

The fee is usually agreed between the parties and the adjudicator; ODACC’s report says that happens in about 90% of its cases. If it can’t be agreed, ODACC sets it from its Schedule of Fees, approved October 1, 2025:

Amount claimed in the noticeAdjudication fee set by ODACC (plus HST)
Up to $9,999$1,300
$10,000 to $24,999$1,700
$25,000 to $34,999$2,700
$35,000 to $49,999$3,700
$50,000 to $249,999$300 an hour
$250,000 to $499,999$450 an hour
$500,000 to $1,000,000$600 an hour
Over $1,000,000$850 an hour

Disbursements are charged at cost. ODACC can ask for the estimated total up front as a retainer and refunds any overpayment (O. Reg. 264/25, s. 23). If the parties agree to end a smaller adjudication (under $50,000) within 15 days of the appointment, they pay half the fee; after that, all of it. Above $50,000, they pay for the hours the adjudicator has spent.

ODACC’s own fees

For scale, ODACC’s report gives a median claim of about $215,000 in the 2026 fiscal year, and a median award (where something was payable) of about $85,000. For an owner the bigger cost is usually time: your team pulling the record together inside a few weeks, and your lawyer reviewing it.

Adjudication compared with liens, arbitration, court and your contract

Adjudication doesn’t replace the other routes. It runs beside them, and a party can refer a dispute to adjudication even while a court action or arbitration on the same dispute is underway, until that’s finally decided (s. 13.5(5)).

Adjudication (Part II.1)Lien action (Part VIII)Arbitration (CCDC 40 / Arbitration Act, 1991)Court action
Who decidesODACC-certified adjudicatorSuperior Court of JusticeArbitrator the parties appointSuperior Court of Justice
Who can start itEither party to the contract, without consentAnyone with lien rights who supplied the improvementOnly where the contract or a later agreement provides for itEither party
Speed30 days from documents, plus agreed extensionsMonths; the lien must be preserved and perfected on statutory deadlinesMonths, set by the arbitrator and the partiesTypically the longest
CostAdjudicator fee split equally, each party’s own costsLegal costs; costs can be awardedArbitrator’s fees plus legal costsLegal costs; costs can be awarded
BindingInterim: binding until a court, arbitrator or agreement decides otherwiseFinal, subject to appealFinal, with limited appealFinal, subject to appeal
What it coversThe matters in s. 19, O. Reg. 264/25, or what’s agreedThe lien claim against the property and holdbackWhatever the arbitration agreement coversAnything
Effect on the propertyNone directlyClaim registered on titleNone directlyNone directly

A few points about how they interact:

How adjudication fits CCDC 2, 5A and 5B

CCDC 2 – 2020 has a dispute ladder in Part 8. Under GC 8.1 the Consultant makes findings first, and gives instructions to keep the work moving while a dispute is unresolved (GC 8.1.3). Under GC 8.3 a party that disagrees with a finding gives notice within 15 Working Days, then the parties negotiate, then go to a Project Mediator under CCDC 40, and then either party can refer the dispute to arbitration within 10 Working Days after the mediation ends. If neither party requires immediate arbitration, it’s held until Ready-for-Takeover, termination or abandonment (GC 8.3.8).

GC 8.2 sits in the middle of that ladder and says the contract doesn’t affect either party’s right to adjudicate. In practice, that means:

Our guide to the CCDC 2 stipulated price contract walks through Part 8 in context. If you’re on a construction management form, CCDC 5A, 5B or 17, read its dispute resolution part the same way: the statute applies whatever the form says, and under 5A you may have a separate contract, and a separate adjudication right, with each trade. Our comparison of CCDC 5A and 5B covers who contracts with whom.

Getting your records ready and keeping the job moving

An adjudicator has about a month and works mostly from documents. The claimant chooses when to start, and you’ll have the time the adjudicator gives you to respond, so the project file needs to be in order before any notice arrives.

What the adjudicator will want to see

RecordWhat it showsWhere it comes from
The signed contract, with supplementary conditions and all amendmentsWhat was agreed, including payment termsYour contract file
The schedule of values and every progress claimWhat was claimed, when, against which linesContractor’s monthly claims
Consultant’s payment certificatesWhat was assessed as owingConsultant
Proper invoices, with the date you received eachWhen the 28-day clock startedYour accounts payable log
Notices of non-payment (Form 1.1), with dates givenWhat you disputed and why, within 14 daysYour payment file
Change order log, Change Orders, Change Directives, quotes and backupWhat was changed, priced and approvedConsultant or owner’s rep
Site instructions, RFIs and responsesWho instructed what, and whenConsultant
The schedule and updates, and delay noticesTime claims and their timingContractor and consultant
Meeting minutes and site photosWhat was said and seen on siteSite meetings, site reviews
Holdback ledger and annual release noticesHoldback retained, released and outstandingOwner, owner’s rep or payment certifier

Five habits that make it manageable

  1. Date-stamp every invoice on arrival. The Act’s 14 and 28 day periods run from the day you receive a proper invoice, so keep a record of that date to show your notice of non-payment went out in time.
  2. Make every notice of non-payment complete. It must state the amount not being paid and “all of the reasons” (s. 6.4(2)). An adjudicator will read it closely, so put every reason in the notice itself.
  3. Keep the change log current. Each change should have an instruction, a price or a basis for one, and a signature. Payment under the contract, including change orders, was the largest category of adjudications decided in 2026.
  4. Write down decisions made on site. When a site conversation changes the work, send a short email the same day confirming what was agreed.
  5. Keep one file. Contracts, claims, certificates, notices and changes in one place, in date order.

Our guide to the schedule of values and progress claims shows how to set up the monthly claim review so this record is kept as you go.

Why a notice of non-payment can lead to adjudication

When you give a notice of non-payment, your contractor has to decide what to do about its subcontractors whose work was in that invoice. If it relies on your non-payment to withhold from them, its notice to those subs must include an undertaking to refer the matter to adjudication within 21 days (s. 6.5(5)). So a notice of non-payment can lead to an adjudication within weeks. That’s how the Act is meant to work, so write each notice expecting that an adjudicator may read it.

Keeping the project moving while it runs

Frequently asked questions

Is adjudication binding in Ontario?

Yes, on an interim basis. The determination binds both parties until a court decides the matter, an arbitrator decides it under the Arbitration Act, 1991, or the parties agree something else in writing (s. 13.15). The amount must be paid within 15 days, and the determination can be filed with the court and enforced like a court order (s. 13.20). Judicial review needs leave and doesn’t stop payment.

How long does construction adjudication take?

The adjudicator must decide within 30 days of receiving the claimant’s documents, extendable by up to 14 days with consent or longer by agreement (s. 13.13). With the steps before that, appointment and document delivery, expect roughly six to seven weeks from notice to decision if nobody extends. In ODACC’s 2026 fiscal year, 55% of decisions came within 30 days and the rest within agreed extensions.

How much does an adjudication cost?

The adjudicator’s fee is usually agreed. If it isn’t, ODACC sets it from $1,300 for claims under $10,000 up to $850 an hour for claims over $1 million (October 2025 schedule, plus HST). The parties split it equally and each pays its own legal and consulting costs. Claims of $50,000 or more also carry a $600 referral fee for the claimant and a $120 certification fee, split.

Can an owner start an adjudication?

Yes. Any party to the contract can refer a prescribed matter (s. 13.5(1)), so an owner can adjudicate against its contractor, for example over the valuation of work, an overpayment or a set-off. It isn’t only a contractor’s tool. Settling a valuation question early can keep it from becoming part of a larger disagreement at closeout.

What to do next

If you’ve received a notice of adjudication, call your construction lawyer today and note the date the documents arrive, because that starts the 30 days. Then gather the record in the table above, in date order, and decide who on your team will own it for the next month. If you’re just setting up a project, build the record now: an invoice log, a notice of non-payment routine that meets the 14 days, and a change log that stays current. Our guide to construction liens and holdback has the payment calendar to go with it.

We’ve spent more than 20 years on office, residential, retail and industrial projects, with experience built at PCL Constructors and Oxford Properties, and we’ve run the payment, change and claims records that disputes are decided on. If you’d like an experienced hand to set up that record, review claims each month or prepare the project file with your lawyer when a notice arrives, that’s part of our construction consulting work.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada