November 17, 2026
How ODACC Construction Adjudication Works for Ontario Owners
ODACC (Ontario Dispute Adjudication for Construction Contracts) is the body Ontario has designated to run construction adjudication under Part II.1 of the Construction Act. Adjudication is a fast, interim decision on a payment dispute: either party to a construction contract can start one without the other’s consent, a certified adjudicator decides it within 30 days of receiving the claimant’s documents unless the parties agree to more time, and the amount decided has to be paid within 15 days. It is binding until a court, an arbitrator or a written agreement between the parties says otherwise. For an owner, it is a process you can handle calmly if your contract, invoices, notices and change records are in order.
Most of what’s written about ODACC is for lawyers and contractors starting a claim. This guide is for the owner. It isn’t legal advice. When a notice arrives, your construction lawyer advises on that notice; your job, and ours if we’re working with you, is to have the record ready.
What ODACC is and what adjudication does
The Construction Act lets the Minister designate an Authorized Nominating Authority (s. 13.2). ODACC holds that role. It trains and certifies adjudicators, keeps the public registry of them and appoints one when the parties can’t agree (s. 13.3). The parties pay the adjudicator’s fee through ODACC (O. Reg. 264/25, s. 23), and every adjudication runs through its online system. ODACC doesn’t decide disputes itself; the adjudicator does.
Adjudicators come from the industry. ODACC’s 2026 Annual Report says each has at least 10 years of construction experience, and lists project managers (27), engineers (23) and lawyers (20) as the largest groups on the registry, with arbitrators, quantity surveyors, mediators, architects and an accountant making up the rest. The person reading your file is likely to understand a schedule of values and a change order log without having them explained.
Three features set adjudication apart from anything else in your contract:
- It’s a statutory right. Any party to a contract or subcontract can refer a dispute about a prescribed matter (s. 13.5(1)). Your consent isn’t needed, and the contract can’t take the right away. CCDC 2 – 2020 says so directly in GC 8.2: nothing in the contract affects the parties’ rights to adjudication under legislation.
- It’s fast by design. The adjudicator must decide within 30 days of receiving the claimant’s documents unless the parties agree to more time (s. 13.13).
- It’s interim. The decision binds the parties now, but the merits can still be decided by a court or an arbitrator later (s. 13.15). So money changes hands during the project, and any larger argument about the merits can be dealt with later.
Adjudication sits on top of prompt payment, which came into force on October 1, 2019 together with Part II.1. If your contract was signed before then, or the procurement started before then, neither prompt payment nor adjudication applies to it (s. 87.3(4)).
What disputes can go to adjudication, and what changed in 2026
On January 1, 2026, amendments to the Construction Act came into force and O. Reg. 264/25 replaced the old adjudication regulation, O. Reg. 306/18. The list of matters that can be adjudicated moved out of the Act and into section 19 of the regulation. Some summaries describe the new scope as “any dispute about the contract”. The regulation is narrower than that, so it’s worth reading the list itself.
The matters you can adjudicate
Under s. 19(1) of O. Reg. 264/25, a party can refer:
- The valuation of services or materials provided under the contract.
- Payment under the contract, including for a change order, approved or not, or a proposed change order.
- A dispute that is the subject of a notice of non-payment under Part I.1 (prompt payment).
- Amounts retained as set-off by a trustee (s. 12) or as lien set-off (s. 17(3)).
- Payment of holdback under s. 26, which now includes the mandatory annual release.
- The scope of work, a request for a change in the contract price, or a request for an extension of time, if resolving it is reasonably necessary to decide one of the matters above.
The parties can also agree to adjudicate anything else (s. 13.5(1)). The same list applies between a contractor and its subcontractors (s. 19(2)).
Item 6 is the real expansion: scope, price changes and time extensions are in, but only as the route to a payment decision. A stand-alone claim for an extension of time, with no money attached, isn’t on the list unless both parties agree to it.
What owners actually see adjudicated
ODACC’s 2026 report (fiscal year August 1, 2025 to July 31, 2026) breaks down the 130 determinations made after the new rules took effect:
| Matter (s. 19(1), O. Reg. 264/25) | Determinations, Jan 1 – Jul 31, 2026 |
|---|---|
| Payment under the contract, including change orders | 66 |
| Valuation of services or materials | 51 |
| Notice of non-payment disputes | 5 |
| Scope, price change or time, as needed for another matter | 5 |
| Holdback payment under s. 26 | 3 |
| Set-off, or a matter agreed by the parties | 0 |
About nine in ten were about what the work is worth and whether it should be paid. Our guide to change orders in Ontario covers how to keep changes priced and agreed before they reach an invoice.
The other 2026 changes that affect owners
- A longer window. Before 2026, adjudication couldn’t start once the contract was completed unless the parties agreed. Now a notice can be given up to 90 days after the contract is completed, abandoned or terminated (s. 13.5(3)). For subcontracts, it’s 90 days after the earliest of that date, the subcontract’s certified completion, or the sub’s last supply (s. 13.5(3.1)).
- Private adjudicators. The parties can agree on a private adjudicator outside the registry, but only with a written agreement signed by everyone and a fee of at least $1,000 an hour, however it’s charged (O. Reg. 264/25, s. 21). ODACC’s report says none were used in the 2026 fiscal year.
- Consolidation without agreement. Related adjudications under separate contracts can now be consolidated at one party’s request if the adjudicators agree (s. 13.8(2)), with notice given no later than five days after the documents reach the adjudicator (O. Reg. 264/25, s. 26(2)).
- Jurisdiction objections have a deadline. An objection that a matter can’t be adjudicated must be made in your first submissions (s. 13.12.1). Miss it and a court is unlikely to hear the point later (s. 13.18(5.1)).
- Payment within 15 days of the decision, and 35 days to file for leave to seek judicial review (ss. 13.19(2), 13.18(2)).
- Published decisions. For notices given on or after January 1, 2027, ODACC will publish every determination, anonymized on any party’s request (O. Reg. 264/25, s. 16).
How an adjudication runs, day by day
The Act sets the clock. Here it is in order, with the section for each step. “Days” are calendar days unless your contract says otherwise.
- Day 0: notice of adjudication. The claimant gives the other party a written notice naming the parties, describing the dispute and how and when it arose, the redress sought, a proposed adjudicator, and any earlier adjudications on the same contract (s. 13.7(1)). A copy goes to ODACC electronically the same day (O. Reg. 264/25, s. 20).
- By day 4: the adjudicator agrees, or ODACC is asked. If the proposed registry adjudicator hasn’t consented within four days, the claimant must ask ODACC to appoint one (s. 13.9(4)). It must also ask straight away if there’s no prospect of agreement (O. Reg. 264/25, s. 22).
- Within 7 days of the request: ODACC appoints. ODACC must appoint a registry adjudicator, with their consent, no later than seven days after the request (s. 13.9(5)). There’s no ODACC fee for appointing one.
- Within 5 days of appointment: the claimant’s documents. The claimant sends the adjudicator the notice, and sends the adjudicator and you the contract and every document it intends to rely on, all on the same day (s. 13.11; O. Reg. 264/25, s. 24). The adjudicator confirms in writing the date these arrived. That date starts the 30-day clock.
- Your response, by the date the adjudicator sets. You may respond in writing (s. 13.11.1). There’s no fixed statutory number of days; the adjudicator specifies the date, and the response goes to the adjudicator and the claimant on the same day (O. Reg. 264/25, s. 25). If you object that the matter isn’t adjudicable, say so here (s. 13.12.1).
- The process the adjudicator sets. Some adjudications are on documents only; others add a video hearing, an in-person hearing or a site visit. ODACC publishes four suggested pre-designed processes, three of them in writing only, that the parties can recommend (ODACC, Adjudication Process). The adjudicator can ask questions, draw inferences from how the parties behave, inspect the site and bring in an expert such as a quantity surveyor or engineer (s. 13.12(1)).
- Day 30 after documents: the determination. It must be written, with reasons (s. 13.13(1), (6)). It can be extended by up to 14 days at the adjudicator’s request with both parties’ written consent, or longer by written agreement of the parties (s. 13.13(2)). A determination made late has no effect (s. 13.13(5)).
- Within 7 days: the certified copy. The adjudicator sends an electronic copy, then a certified copy within seven days (O. Reg. 264/25, s. 30).
- Within 5 days: corrections, if there’s an arithmetic slip or an oversight (s. 13.17.1).
- Within 15 days of the decision: payment. Whoever has to pay, pays (s. 13.19(2)). The amount is still subject to holdback (s. 13.19(1)). Late amounts carry interest at the prejudgment rate or the contract rate, whichever is higher (s. 13.19(3)).
- Within 35 days: judicial review, if at all. It needs leave of the Divisional Court, on narrow grounds such as bias, fraud, or a matter outside adjudication (s. 13.18). It doesn’t stop the payment unless the court orders it (s. 13.18(7)).
If every step takes its full statutory time and nobody extends anything, that’s about six and a half weeks from notice to decision. Extensions are common and usually agreed. In ODACC’s 2026 fiscal year, 55% of determinations came within the 30 days and the other 45% within a deadline the parties had agreed to extend. Every one was on time under the Act.
Of the 396 adjudications started that year, 117 were ended early by agreement, 54 of them because the parties settled (s. 13.14).
What adjudication costs, and who pays
Each side pays its own costs, including its own lawyer or consultant (s. 13.16). The adjudicator’s fee is split equally (s. 13.10(3)). The adjudicator can depart from both rules only if a party has acted in a way that’s frivolous, vexatious, an abuse of process or in bad faith (s. 13.17).
The adjudicator’s fee
The fee is usually agreed between the parties and the adjudicator; ODACC’s report says that happens in about 90% of its cases. If it can’t be agreed, ODACC sets it from its Schedule of Fees, approved October 1, 2025:
| Amount claimed in the notice | Adjudication fee set by ODACC (plus HST) |
|---|---|
| Up to $9,999 | $1,300 |
| $10,000 to $24,999 | $1,700 |
| $25,000 to $34,999 | $2,700 |
| $35,000 to $49,999 | $3,700 |
| $50,000 to $249,999 | $300 an hour |
| $250,000 to $499,999 | $450 an hour |
| $500,000 to $1,000,000 | $600 an hour |
| Over $1,000,000 | $850 an hour |
Disbursements are charged at cost. ODACC can ask for the estimated total up front as a retainer and refunds any overpayment (O. Reg. 264/25, s. 23). If the parties agree to end a smaller adjudication (under $50,000) within 15 days of the appointment, they pay half the fee; after that, all of it. Above $50,000, they pay for the hours the adjudicator has spent.
ODACC’s own fees
- Referral fee: $600 plus HST, paid by the claimant, where the claim is $50,000 or more. Nothing below that.
- Certification fee: $120 plus HST for the certified determination where the claim is $50,000 or more, split between the parties.
- Appointment: no fee when ODACC appoints a registry adjudicator.
For scale, ODACC’s report gives a median claim of about $215,000 in the 2026 fiscal year, and a median award (where something was payable) of about $85,000. For an owner the bigger cost is usually time: your team pulling the record together inside a few weeks, and your lawyer reviewing it.
Adjudication compared with liens, arbitration, court and your contract
Adjudication doesn’t replace the other routes. It runs beside them, and a party can refer a dispute to adjudication even while a court action or arbitration on the same dispute is underway, until that’s finally decided (s. 13.5(5)).
| Adjudication (Part II.1) | Lien action (Part VIII) | Arbitration (CCDC 40 / Arbitration Act, 1991) | Court action | |
|---|---|---|---|---|
| Who decides | ODACC-certified adjudicator | Superior Court of Justice | Arbitrator the parties appoint | Superior Court of Justice |
| Who can start it | Either party to the contract, without consent | Anyone with lien rights who supplied the improvement | Only where the contract or a later agreement provides for it | Either party |
| Speed | 30 days from documents, plus agreed extensions | Months; the lien must be preserved and perfected on statutory deadlines | Months, set by the arbitrator and the parties | Typically the longest |
| Cost | Adjudicator fee split equally, each party’s own costs | Legal costs; costs can be awarded | Arbitrator’s fees plus legal costs | Legal costs; costs can be awarded |
| Binding | Interim: binding until a court, arbitrator or agreement decides otherwise | Final, subject to appeal | Final, with limited appeal | Final, subject to appeal |
| What it covers | The matters in s. 19, O. Reg. 264/25, or what’s agreed | The lien claim against the property and holdback | Whatever the arbitration agreement covers | Anything |
| Effect on the property | None directly | Claim registered on title | None directly | None directly |
A few points about how they interact:
- Liens keep their own clock. A trade that adjudicates against your contractor still has to preserve and perfect any lien on time. Your holdback obligations to lien claimants don’t change because an adjudication is running. Our guide to construction liens and holdback in Ontario covers the lien deadlines and what to do the day one is registered.
- An adjudicated amount counts for substantial performance. If an adjudicator decides money is payable, or overpaid, before substantial performance is certified, that amount is added to or deducted from the contract price for the substantial performance test (s. 2(2.1)).
- The decision is evidence later. The determination and reasons are admissible in court (s. 13.13(7)).
- On public projects, a trade owed money under a labour and material payment bond can adjudicate against the contractor and the surety (O. Reg. 264/25, s. 33). Our guide to performance and payment bonds explains how those bonds work.
How adjudication fits CCDC 2, 5A and 5B
CCDC 2 – 2020 has a dispute ladder in Part 8. Under GC 8.1 the Consultant makes findings first, and gives instructions to keep the work moving while a dispute is unresolved (GC 8.1.3). Under GC 8.3 a party that disagrees with a finding gives notice within 15 Working Days, then the parties negotiate, then go to a Project Mediator under CCDC 40, and then either party can refer the dispute to arbitration within 10 Working Days after the mediation ends. If neither party requires immediate arbitration, it’s held until Ready-for-Takeover, termination or abandonment (GC 8.3.8).
GC 8.2 sits in the middle of that ladder and says the contract doesn’t affect either party’s right to adjudicate. In practice, that means:
- The contract can add procedures but can’t override the Act. Extra adjudication procedures in your contract apply only where they don’t conflict with Part II.1 and the regulation (s. 13.6(2)). A clause that names a particular adjudicator in advance has no effect (s. 13.9(3)).
- The GC 8.3 notice deadlines still matter. If you disagree with a Consultant’s finding, the 15 Working Day notice under GC 8.3.2 protects your right to take the matter further later, whatever happens at adjudication.
- The contract’s interest rate can apply. Under s. 13.19(3), late payment of an adjudicated amount carries the higher of the prejudgment rate and the contract’s rate. CCDC 2’s Agreement sets 2% over prime for 60 days and 4% after that.
- Non-payment of an award is a default. GC 7.2.3 lists failure to pay amounts “awarded by adjudication” among the owner defaults the contractor can give notice of.
Our guide to the CCDC 2 stipulated price contract walks through Part 8 in context. If you’re on a construction management form, CCDC 5A, 5B or 17, read its dispute resolution part the same way: the statute applies whatever the form says, and under 5A you may have a separate contract, and a separate adjudication right, with each trade. Our comparison of CCDC 5A and 5B covers who contracts with whom.
Getting your records ready and keeping the job moving
An adjudicator has about a month and works mostly from documents. The claimant chooses when to start, and you’ll have the time the adjudicator gives you to respond, so the project file needs to be in order before any notice arrives.
What the adjudicator will want to see
| Record | What it shows | Where it comes from |
|---|---|---|
| The signed contract, with supplementary conditions and all amendments | What was agreed, including payment terms | Your contract file |
| The schedule of values and every progress claim | What was claimed, when, against which lines | Contractor’s monthly claims |
| Consultant’s payment certificates | What was assessed as owing | Consultant |
| Proper invoices, with the date you received each | When the 28-day clock started | Your accounts payable log |
| Notices of non-payment (Form 1.1), with dates given | What you disputed and why, within 14 days | Your payment file |
| Change order log, Change Orders, Change Directives, quotes and backup | What was changed, priced and approved | Consultant or owner’s rep |
| Site instructions, RFIs and responses | Who instructed what, and when | Consultant |
| The schedule and updates, and delay notices | Time claims and their timing | Contractor and consultant |
| Meeting minutes and site photos | What was said and seen on site | Site meetings, site reviews |
| Holdback ledger and annual release notices | Holdback retained, released and outstanding | Owner, owner’s rep or payment certifier |
Five habits that make it manageable
- Date-stamp every invoice on arrival. The Act’s 14 and 28 day periods run from the day you receive a proper invoice, so keep a record of that date to show your notice of non-payment went out in time.
- Make every notice of non-payment complete. It must state the amount not being paid and “all of the reasons” (s. 6.4(2)). An adjudicator will read it closely, so put every reason in the notice itself.
- Keep the change log current. Each change should have an instruction, a price or a basis for one, and a signature. Payment under the contract, including change orders, was the largest category of adjudications decided in 2026.
- Write down decisions made on site. When a site conversation changes the work, send a short email the same day confirming what was agreed.
- Keep one file. Contracts, claims, certificates, notices and changes in one place, in date order.
Our guide to the schedule of values and progress claims shows how to set up the monthly claim review so this record is kept as you go.
Why a notice of non-payment can lead to adjudication
When you give a notice of non-payment, your contractor has to decide what to do about its subcontractors whose work was in that invoice. If it relies on your non-payment to withhold from them, its notice to those subs must include an undertaking to refer the matter to adjudication within 21 days (s. 6.5(5)). So a notice of non-payment can lead to an adjudication within weeks. That’s how the Act is meant to work, so write each notice expecting that an adjudicator may read it.
Keeping the project moving while it runs
- Separate the dispute from the work. Keep the disputed item in its own lane. Pay everything that isn’t in dispute on time; the Act requires it, and it keeps the trades on site.
- Keep the Consultant’s instructions flowing. Under GC 8.1.3, the Consultant gives instructions to keep the work moving while a dispute is unresolved, and following them doesn’t prejudice anyone’s claim.
- Pay an award on time. If you’re told to pay and you don’t within 15 days, the contractor can suspend work until the amount, interest and its reasonable suspension costs are paid, and recover its reasonable costs of starting again (s. 13.19(5)–(6)).
- Keep talking. Exchanging documents often shows both sides where they actually stand, and you can settle at any point.
- Tell your lender if an adjudicated payment changes a draw.
Frequently asked questions
Is adjudication binding in Ontario?
Yes, on an interim basis. The determination binds both parties until a court decides the matter, an arbitrator decides it under the Arbitration Act, 1991, or the parties agree something else in writing (s. 13.15). The amount must be paid within 15 days, and the determination can be filed with the court and enforced like a court order (s. 13.20). Judicial review needs leave and doesn’t stop payment.
How long does construction adjudication take?
The adjudicator must decide within 30 days of receiving the claimant’s documents, extendable by up to 14 days with consent or longer by agreement (s. 13.13). With the steps before that, appointment and document delivery, expect roughly six to seven weeks from notice to decision if nobody extends. In ODACC’s 2026 fiscal year, 55% of decisions came within 30 days and the rest within agreed extensions.
How much does an adjudication cost?
The adjudicator’s fee is usually agreed. If it isn’t, ODACC sets it from $1,300 for claims under $10,000 up to $850 an hour for claims over $1 million (October 2025 schedule, plus HST). The parties split it equally and each pays its own legal and consulting costs. Claims of $50,000 or more also carry a $600 referral fee for the claimant and a $120 certification fee, split.
Can an owner start an adjudication?
Yes. Any party to the contract can refer a prescribed matter (s. 13.5(1)), so an owner can adjudicate against its contractor, for example over the valuation of work, an overpayment or a set-off. It isn’t only a contractor’s tool. Settling a valuation question early can keep it from becoming part of a larger disagreement at closeout.
What to do next
If you’ve received a notice of adjudication, call your construction lawyer today and note the date the documents arrive, because that starts the 30 days. Then gather the record in the table above, in date order, and decide who on your team will own it for the next month. If you’re just setting up a project, build the record now: an invoice log, a notice of non-payment routine that meets the 14 days, and a change log that stays current. Our guide to construction liens and holdback has the payment calendar to go with it.
We’ve spent more than 20 years on office, residential, retail and industrial projects, with experience built at PCL Constructors and Oxford Properties, and we’ve run the payment, change and claims records that disputes are decided on. If you’d like an experienced hand to set up that record, review claims each month or prepare the project file with your lawyer when a notice arrives, that’s part of our construction consulting work.