CCDC 4 Unit Price Contract Explained for Ontario Owners

CCDC 4 is the Canadian standard unit price contract between an owner and a contractor. You agree a price for each unit of work (a cubic metre of excavation, a metre of pipe, a tonne of asphalt), the work is measured as it goes, and you pay the unit price times the quantity actually built. The total at signing is an estimate. The current edition is CCDC 4 – 2023, and it suits work where the quantities can’t be known when you tender: site servicing, earthworks, paving, utilities and remediation.

This guide is for Ontario owners deciding whether a unit price contract fits their project, or running one: what’s in the 2023 form, how it compares with CCDC 2 and CCDC 3, the 15% quantity rule, measurement and payment, and setting up the tender. It isn’t legal advice; have a construction lawyer review the supplementary conditions before you sign.

What is a CCDC 4 contract?

The Canadian Construction Documents Committee describes CCDC 4 – 2023 as a standard prime contract “to perform the required work for a pre-determined, fixed amount for each specified unit of work performed. The total price is determined by multiplying the unit price by the actual, measured quantity of work performed for each specified unit.” It’s sold in electronic format only.

The 2023 edition was published on November 29, 2023, alongside new editions of CCDC 2MA and the CCDC 18 civil works contract, revised, per the Ontario Association of Architects, to carry over the CCDC 2 – 2020 changes such as Ready-for-Takeover and early occupancy. The 2011 edition was kept on sale for a one-year transition. As of November 2026, CCDC’s documents list shows only the 2023 edition, and no CCDC guide to it.

Supplementary conditions written for CCDC 4 – 2011 need updating before you reuse them, as WeirFoulds (September 2024) also notes.

How the price is worked out

Article A-4 says unit prices are the basis for payment and the quantities in the Schedule of Prices are estimated. The form defines the final Contract Price as “the sum of the products of the actual final quantities that are incorporated in or made necessary by the Work, multiplied by the appropriate Unit Prices stated in the Schedule of Prices, plus lump sums and allowances, if any.”

The Schedule of Prices is the heart of the contract. It lists each item of work, its unit of measure, the estimated quantity and the unit price. A short one for a site servicing package might look like this. The figures are illustrative only, not market rates.

ItemUnitEstimated quantityUnit priceExtended amount
Mobilization and demobilizationLump sum1$60,000$60,000
Common excavationm³6,000$22$132,000
Rock excavationm³400$140$56,000
Granular A basetonne3,500$38$133,000
300 mm storm sewer, installedm450$520$234,000
Disposal of contaminated soiltonne800$95$76,000
Asphalt, base and surfacetonne1,200$160$192,000
Estimated Contract Price$883,000

If the excavation finds 550 cubic metres of rock instead of 400, you pay for 550. If the storm sewer run is shortened in the field to 420 metres, you pay for 420. You carry the risk of how much work there is; the contractor carries the risk of what each unit costs to do.

What’s in CCDC 4 – 2023 and how it differs from CCDC 2

CCDC publishes the table of contents of CCDC 4 free. Set beside the CCDC 2 – 2020 table of contents, the headings are the same with three exceptions: CCDC 4 adds two defined terms, Schedule of Prices and Unit Price, and one general condition, GC 6.7 Quantity Variations. The thirteen parts otherwise carry the same headings, from Part 1 General Provisions to Part 13 Indemnification and Waiver.

The form itself is sold, but a full copy of CCDC 4 – 2023 appears in a public tender package from the Regional District of Central Kootenay, and the clause references below come from that text. Inside the shared headings, the unit price logic shows up in a handful of places.

WhereWhat CCDC 4 – 2023 saysWhat it means for you
A-4.1Unit prices are the basis for payment; quantities are estimated; the stated Contract Price is the estimated totalThe number you sign is a forecast, not a cap
DefinitionsContract Price is actual final quantities × unit prices, plus lump sums and allowancesYou can mix lump-sum items with unit price items
GC 2.2.2.3The Consultant visits the site to “verify quantities of Work performed” where unit prices are the basis for paymentMeasurement is part of the Consultant’s job, so budget for it in their fee
GC 5.2.3–5.2.4Each claim is actual quantities × unit prices, plus a share of lump-sum items (billed against a schedule of values), plus products deliveredThe claim is built from measurement, not percentage complete
GC 5.2.6.2Each claim includes “quantity measurements and other evidence as requested by the Consultant for each Unit Price item”You decide, in the specifications, what evidence that is
GC 5.3.2Quantities in progress payments are estimates until the item is completeMid-job payments can be corrected later; the final measurement settles each item
GC 6.2.2A change can be priced from the Schedule of Prices, from unit prices deduced or extrapolated from it, by quotation, or on cost plusThe tendered rates price most changes
GC 6.7Either party can ask to adjust a unit price when the actual quantity is more than 15% above or below the estimateThe one clause with no CCDC 2 equivalent

The CCDC 2 – 2020 text has none of this. Its GC 2.2.2 has the Consultant visiting site for progress and conformity only, its GC 6.2 lists no valuation methods, and the word “quantity” doesn’t appear in its general conditions. Everything else in our CCDC 2 guide carries over, from Change Directives and allowances to Ready-for-Takeover, insurance and dispute resolution.

When does a unit price contract suit a project?

A unit price contract makes sense when you can describe the kind of work exactly but can’t know how much of it there will be until the work is done. If the quantities can be measured off complete drawings, a lump sum is usually simpler to run.

WorkUnit prices usually suit it?Why
Earthworks, cut and fillYesVolumes depend on ground conditions between boreholes
Rock excavationYesThe rock line is an estimate until you dig
Site servicing (storm, sanitary, watermain)YesLengths, depths and bedding change with field conditions
Roads, paving, curbsYesMeasured by tonne, m² or m, with common field adjustments
Contaminated soil removal and disposalYesVolumes and disposal categories are found during excavation
Piles, anchors, patch repairsOftenThe count is unknown until the structure is opened or tested
A new building on complete drawingsRarelyQuantities can be taken off the drawings; a lump sum under CCDC 2 is the usual form
A whole building where design isn’t finishedNoUnit prices can’t price undesigned work; look at cost plus or construction management

Many projects use both: a CCDC 4 servicing contract can carry lump sums for mobilization and setup. On sites like Scarborough Junction and Bellwoods House, two projects our team worked on at PCL Constructors and Oxford Properties that both needed full environmental remediation, the volume of soil that has to be removed and its classification are exactly the kind of quantity no one can promise at tender.

Unit prices inside a CCDC 2 contract

Owners searching “unit price contract” are sometimes looking at something different: a lump-sum CCDC 2 contract with a schedule of unit prices attached. Those unit prices don’t set the contract price. They’re agreed rates for pricing changes, such as an extra cubic metre of rock. The City of Waterloo’s supplementary conditions to CCDC 2 – 2020, for example, apply the tender unit prices wherever a change includes equivalent items. Our article on how change orders work covers this. Under CCDC 4, by contrast, every unit price item is paid on measurement from day one.

CCDC 4 or CCDC 18 for civil work

CCDC also publishes CCDC 18 – 2023 Civil Works Contract, for “roads, bridges, dams, underground utilities, etc.” Its table of contents has its own Schedule of Prices and GC 6.7, with separate payment clauses for unit price and lump-sum work. For pure civil infrastructure, ask your consultant which form fits. For a site package tied to a building project, CCDC 4 lines up with the CCDC 2 contract for the building.

CCDC 4 vs CCDC 2 vs CCDC 3

The three forms share most of their general conditions; the price and the risk split differ.

CCDC 4 – 2023 (unit price)CCDC 2 – 2020 (stipulated price)CCDC 3 – 2016 (cost plus)
How the price is setUnit prices × measured quantities, plus any lump sumsOne fixed sum for the defined scopeActual cost of the work plus a fee
Who carries quantity riskYouThe contractor, for the defined scopeYou
Who carries unit cost riskThe contractorThe contractorYou
What you have to manageMeasurement, quantities against the estimate, unit price adjustmentsChanges and claimsCost records, the budget, the fee
How changes are valuedFrom the Schedule of Prices first, then quotation or cost plus (GC 6.2.2)Agreed by Change Order, or by Change Directive at cost plus feeAs more cost of the work, with the fee
Best fitMeasurable work with uncertain quantitiesComplete design, defined scopeUndefined scope or urgent start

For the detail of the other two, see our CCDC 2 stipulated price guide and our guide to how a cost-plus contract works.

The 15% rule: what happens when quantities move

A contractor prices 400 cubic metres of rock with mobilization and overhead spread across those units. If the quantity doubles or halves, the rate may no longer be fair to either side. GC 6.7 deals with this.

Under GC 6.7.1, the owner or the contractor “may request an adjustment to a Unit Price contained in the Schedule of Prices provided that the actual quantity of the item in the Schedule of Prices exceeds or falls short of the estimated quantity by more than 15%.” Three points follow from the wording:

  1. Nothing changes automatically. Inside the 15% band either way, the tendered rate stands. Outside it, either party may ask. If no one asks, the original rate still applies.
  2. On an overrun, only the excess is repriced. GC 6.7.2: an adjusted price “shall apply only to the quantity that exceeds 115% of the estimated quantity.” The first 115% is paid at the tendered rate.
  3. On an underrun, the adjusted rate is capped. GC 6.7.3: the adjusted price can’t exceed the price that “would cause the extended amount to equal the original extended amount.” If the quantity drops, the contractor can recover fixed costs spread over fewer units, but you never pay more for the smaller quantity than you’d have paid for the estimate.

GC 6.7.4 requires both parties to make “all reasonable efforts” to agree a revised price, recorded in a Change Order. If you can’t agree, GC 6.7.5 sends it to the dispute resolution process in Part 8, and in the meantime the work is paid at the unrevised unit price.

Worked examples

Take the rock excavation line from the sample schedule above: 400 m³ estimated at $140, an extended amount of $56,000. These numbers are illustrative.

ScenarioActual quantityWhat the form allowsPaid
Within the band440 m³ (110%)No adjustment; tendered rate440 × $140 = $61,600
Overrun600 m³ (150%)First 460 m³ (115%) at $140; the 140 m³ above it at an adjusted rate, if either party asks460 × $140 = $64,400, plus 140 m³ at the agreed rate
Underrun250 m³ (63%)An adjusted rate if requested, capped at $56,000 ÷ 250 = $224Somewhere between $35,000 (250 × $140) and $56,000

On a large overrun, the contractor’s fixed costs are already recovered, so the right rate for the excess may be lower than the tendered one, and you’re entitled to ask. On an underrun, the contractor will usually ask, and the discussion is about fixed costs it couldn’t avoid, such as mobilizing the rock breaker.

A 15% band is generous on a well-surveyed item and tight on a guessed one, so a proper geotechnical investigation, environmental sampling and a site survey before tender keep GC 6.7 in the background.

Measurement, progress claims and payment in Ontario

On a unit price job, every dollar paid traces back to a quantity someone measured, so it pays to decide in advance who measures, how, and what record backs each claim.

Who measures

The form gives the Consultant (your architect or engineer) the job of verifying quantities, helped by one or more project representatives on site if you and the Consultant agree (GC 2.2.3). In practice the contractor measures and claims, and the Consultant checks. On earthworks and paving, the usual records include:

The measurement rule for each item belongs in the specifications: whether excavation is paid by neat-line volume or by measured volume, whether pipe length is measured through maintenance holes, what happens to over-excavation the contractor chose to do.

The most useful habit is agreeing quantities daily or weekly, while the evidence is still visible, since work that has been backfilled or paved over can’t be measured again.

Building the monthly claim

Under GC 5.2, claims are monthly and go to you and the Consultant at the same time, with the quantity evidence the Consultant has asked for and, after the first claim, a CCDC 9A statutory declaration and workers’ compensation evidence (GC 5.2.8). Our schedule of values guide covers the lump-sum side.

GC 5.3.2 matters here: progress quantities “shall be considered estimate until all Work required by that Unit Price item is complete.” If the Consultant certifies 3,000 cubic metres of excavation in month two and the final survey shows 2,850, the difference comes off a later payment. The contract expects that correction, so it needn’t become a dispute.

The Ontario payment clock

CCDC 4 – 2023 builds in the Construction Act’s prompt payment rules. Under GC 5.3.1, the Consultant certifies within 10 calendar days of receiving the claim, and you pay within 28 calendar days of receiving it, “and in any event, in compliance with Payment Legislation.” The Construction Act sets the frame:

RuleWhereWhat it means on a unit price job
Proper invoices are monthly unless the contract says otherwises. 6.3(1)Matches GC 5.2
From 2026, an invoice missing information is deemed proper unless you give notice within 7 dayss. 6.1(2)If the quantity evidence is missing, say so within a week
Pay within 28 days of a proper invoices. 6.4(1)Applies to the measured quantities as invoiced
To withhold, give a notice of non-payment within 14 days, with reasonss. 6.4(2)A disputed measurement needs this notice, or the full amount falls due
Amounts not covered by the notice are still due in 28 dayss. 6.4(3)Pay the undisputed quantities on time

Because the invoice can’t be made conditional on the Consultant’s prior certification (s. 6.3(2)), the Consultant’s quantity check has to fit inside the 14-day notice window. If measurement records arrive late each month, that’s the first thing to fix.

A measurement dispute that can’t be settled on site can go to adjudication (GC 8.2), which since 2026 covers changes to the contract price among other matters (Pallett Valo via Mondaq, March 2026).

Holdback

You retain 10% of each payment as the lien holdback under s. 22(1) of the Act, as on any other contract. From January 1, 2026, accrued holdback must be released annually, with notice due within 14 days of each contract anniversary (s. 26). Our guide to construction liens and holdback in Ontario covers the release rules. Substantial performance under CCDC 4 runs through GC 5.4, with the Consultant certifying within 20 calendar days of the contractor’s application; see our article on substantial performance.

Setting up a unit price tender

Most of what makes a CCDC 4 contract run well is decided in how the Schedule of Prices is written. The general process is in our guide to how the construction tender process works; the points below are specific to unit prices.

Writing the Schedule of Prices

  1. Break the work into items a person can measure. Each item needs a unit that can be counted or surveyed without argument: m³, tonne, m, m², each. “Site grading” as one item invites a dispute; cut, fill and topsoil as three items doesn’t.
  2. Base the estimated quantities on investigation. Boreholes, test pits, environmental sampling and a topographic survey. The better the estimate, the less GC 6.7 comes into play.
  3. Write the measurement rule for every item in the specifications. Neat line or actual, in place or loose, compacted or delivered, and what’s included in the rate (dewatering, shoring, bedding, reinstatement).
  4. Use lump sums for fixed costs. Mobilization, bonds, site setup and traffic management don’t vary with quantity, and as lump sums they aren’t spread across unit rates.
  5. Separate items with different risk. Rock separate from common excavation; contaminated soil separate from clean, and by disposal category if the environmental assessment suggests more than one.
  6. Add provisional items for work that may not happen at all, such as additional rock removal below a certain depth or extra dewatering, with an estimated quantity so they’re priced in competition.
  7. Check the estimated quantities against the budget. The extended total is your expected cost, so a realistic quantity matters more than a low one. Add a contingency for quantity movement above that (see how much contingency is enough).

Unbalanced bids and how to spot them

Because you pay the rate on the actual quantity, a bidder who expects certain quantities to overrun can price those items high and others low, and still submit the lowest total. Stephen Bauld, writing on municipal procurement in the Journal of Commerce (2018), describes an unbalanced bid as one that “places an unreasonable high price on certain items in a unit price contract” and low prices on others, and advises saying in the tender terms that bids will be assessed for unbalancing before award.

In Municipalité de Piedmont v. Uniroc Construction Inc., 2020 QCCA 329, the tender priced rock excavation on an estimated 8,700 m³ and prohibited unbalanced bids. A bidder who thought the volume was overstated priced the rock low, the municipality rejected the bid, and the Quebec Court of Appeal held that a public owner must reject a bid whose unit prices are unbalanced, to keep bidders on an equal footing (Langlois, April 2020). It’s a Quebec decision, persuasive rather than binding in Ontario, and it turned on the tender’s own prohibition, which is the clause worth copying.

When the bids come in, the practical checks are:

Most contractors price unit rates fairly, and an unusual rate often has a simple answer, such as equipment already on a nearby job.

Managing the risks as the owner

A unit price contract moves one risk to you: how much work there is. That’s a reasonable split when you control the investigation and the contractor controls productivity, and each of the risks below can be planned for.

The final price is unknown until the work is measured. Present the estimated Contract Price to your lender as a forecast, hold a contingency for the items most likely to move, and track measured quantities against the estimate item by item every month.

Changes and quantity variations aren’t the same thing. If you redesign the storm sewer, that’s a change under GC 6.1, valued under GC 6.2 (usually from the Schedule of Prices). If the sewer is built as designed but the ground needed more bedding than estimated, that’s a quantity variation, paid at the unit rate and, past 15%, open to GC 6.7. Keep the two separate in your records.

Concealed conditions still apply. GC 6.4 Concealed or Unknown Conditions is in CCDC 4 as in CCDC 2. More rock is a quantity issue; rock of a kind no one anticipated may be a concealed condition, judged against the geotechnical report in the tender.

Close out each item when it finishes. Measurement disputes usually trace back to unwritten rules, missing records or quantities left to the end. Because progress quantities are estimates until each item is complete (GC 5.3.2), agree the final quantity for each item as it’s completed, so the final certificate under GC 5.5 is a sum of agreed numbers.

Frequently asked questions

What is a CCDC 4 contract?

CCDC 4 – 2023 is the Canadian Construction Documents Committee’s standard unit price contract between an owner and a contractor. The contractor is paid an agreed price per unit of work (a cubic metre, a tonne, a metre of pipe) multiplied by the quantity actually measured, plus any lump-sum items. It’s used most on site works, servicing, paving and remediation.

What’s the difference between a unit price and a lump sum contract?

Under a lump sum (stipulated price) contract such as CCDC 2, the contractor agrees to build a defined scope for one fixed price and carries the risk of how much work it takes. Under a unit price contract such as CCDC 4, you agree rates per unit, the work is measured, and you pay for the quantity built.

Who carries the risk in a unit price contract?

The owner carries quantity risk: if there’s more rock or contaminated soil than estimated, you pay for it at the agreed rate. The contractor carries unit cost risk: labour, equipment and productivity. CCDC 4’s GC 6.7 shares the risk of large swings, letting either party ask to adjust a rate when the actual quantity is more than 15% above or below the estimate.

Is CCDC 4 used for building construction?

Rarely for a whole building. A building on complete drawings can be measured in advance, so a lump sum under CCDC 2 is the usual choice, or cost plus or construction management when design isn’t finished. CCDC 4 is commonly used alongside a building contract for the site package: excavation, servicing, remediation and paving.

Where to start

If you’re about to tender site work, servicing or remediation, start with the investigation that sets your quantities, then decide the form: can the work be measured in units, can the quantities be fixed from the drawings, and who will measure on site?

Helping owners choose the contract form and set up how it’s administered is part of our construction consulting work: our experience was built over 20+ years and $3B+ of projects at PCL Constructors and Oxford Properties, and we can help you write the Schedule of Prices, review the bids and set up the measurement routine.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.