November 11, 2026
Warehouse Construction Cost in Ontario: 2026 GTA Numbers
In the Greater Toronto Area, warehouse construction cost runs $75 to $180 per square foot in 2026, according to the Altus Group 2026 Canadian Cost Guide. That is hard cost only, for a heated shell with a finished office component, on a level, open site with stable soil. It excludes site development, HST, land, development charges, design fees and financing. A modern distribution facility sits at $170 to $480 per square foot in the same guide. On a 100,000 square foot warehouse, the Altus range is $7.5 million to $18 million for the building alone, before anything outside the walls.
Where your building lands in that range depends on decisions you’ll make before anything is drawn: clear height, the slab, sprinklers, docks, the office and the site.
What a warehouse costs to build in the GTA in 2026
The 2026 Altus guide is priced as at January 31, 2026 and gives a low and high cost per square foot by building type in nine Canadian cities. The industrial types:
| Building type (Altus 2026) | GTA | Ottawa | Vancouver | Calgary | Montreal |
|---|---|---|---|---|---|
| Warehouse | $75–180 | $120–170 | $120–200 | $130–175 | $120–185 |
| Distribution facility | $170–480 | $165–445 | $200–485 | $155–475 | $170–460 |
| Urban storage facility | $90–195 | $105–195 | $120–175 | $145–195 | n/a |
All figures are dollars per square foot of gross floor area, hard construction cost, excluding GST and HST.
What the Altus number includes
- Warehouse is heated shell space, excluding mezzanines, with a finished office component included.
- Distribution facility covers modern e-commerce fulfilment centres and major retail distribution buildings.
- Urban storage facility means multi-level buildings on constrained sites.
- Every rate assumes a level, open site with no restrictions from neighbours, stable soil and average-quality finishes.
- Area is measured the way the Canadian Institute of Quantity Surveyors measures it: to the outside face of the exterior walls. Altus warns that using zoning floor area instead can understate cost by as much as 12%.
- The rates exclude site development, GST and HST, and all soft costs: land, legal, permits, development charges, consultants, contingency, insurance and interest.
- The 2026 figures don’t account for tariffs, upcoming Building Code revisions or labour agreement negotiations. Altus says to consider those separately.
The guide also prices two pieces of the site that a warehouse budget needs. Industrial site servicing in the GTA runs $165,000 to $252,300 per acre, assuming adequately sized municipal services at the property line. Surface parking runs $14 to $30 per square foot of paved area, including curbs, line painting, storm servicing and pole lighting. Neither is in the building rate.
Bringing the number up to date
The Altus figures are priced at January 31, 2026, so a budget set today should be carried forward. Statistics Canada publishes a building construction price index every quarter, and one of the six non-residential buildings it prices is a warehouse in Toronto. In the third quarter of 2026 the Toronto warehouse index stood at 114.7 (2023 = 100), up 2.3% since the first quarter and 4.0% on the year. Nationally, non-residential costs rose 1.2% in the quarter and 4.3% year over year, and Statistics Canada noted that the retaliatory tariffs effective September 8, 2026, including 50% on certain steel and aluminum products, added to pressure on materials.
The trades that move most in a warehouse moved most this year. From the third quarter of 2025 to the third quarter of 2026 in Toronto (table 18-10-0289-01):
| Toronto warehouse, by division | Change, Q3 2025 to Q3 2026 |
|---|---|
| Heating, ventilation and air conditioning | +6.8% |
| Metal fabrications | +6.2% |
| Utilities | +5.6% |
| Thermal and moisture protection (roofing, insulation) | +4.9% |
| Openings (doors, including overhead and dock doors) | +4.1% |
| Concrete | +3.3% |
| Fire suppression | +2.4% |
| All divisions | +4.0% |
Use the index to carry the guide’s January figure forward to your tender date, and show escalation as its own line in the budget.
What drives the cost per square foot
Each of these moves the number, so decide and price them before the design is drawn. The low end of the Altus range is a large, simple box with a small office and few docks on an easy site; the high end is smaller, taller or heavier, with more office.
| Driver | What it changes | Why it moves the cost |
|---|---|---|
| Building size and shape | The ratio of wall and foundation to floor area | A larger, squarer footprint spreads walls, footings and the office across more square feet, so cost per square foot usually falls as the building grows |
| Clear height | Wall height, column size, roof structure, sprinkler design | Taller walls and columns add steel and envelope, and stored height changes the sprinkler system it needs |
| Column grid and bay size | Structural steel, roof joists, racking layout | Wider bays use heavier members; the grid should be set around the racking and dock layout you intend |
| Slab | Thickness, reinforcement, joints, flatness and levelness | Racking loads, forklift traffic and very-narrow-aisle equipment can call for a thicker slab and tighter flatness (FF/FL) numbers, which cost more to place and finish |
| Dock doors and levellers | Number of doors, levellers, seals, depressed dock aprons | Each dock position adds a door, a leveller, a seal or shelter, bumpers, a concrete apron and often a canopy |
| Sprinklers | System type, water supply, fire pump | High-piled storage may need an ESFR system or in-rack sprinklers, and a site whose municipal water pressure can’t supply it may need a fire pump or tank |
| Office component | Finished area, washrooms, HVAC, ceilings | Office space costs far more per square foot than warehouse shell, so the percentage of office is one of the biggest single swings |
| Envelope and roof | Precast, tilt-up, insulated metal panel; membrane and insulation | Each wall system has its own cost, lead time and erection speed, and on a large single-storey building the roof is a big share of the envelope |
| Electrical service | Service size, transformers, lighting, EV and automation | Automation, charging for electric forklifts or trucks and future solar all need capacity planned at the start |
| Cold storage | Insulated panels, under-slab heating, refrigeration | Freezer and cooler space is a different building type inside the shell, priced separately |
| Multi-level and ramps | Upper truck court, ramps, structure for trailers | Putting trucks on an upper floor needs heavy structure and ramps, and sits at the far end of the distribution range |
| Site and soils | Earthwork, foundations, stormwater, paving | The Altus rates assume a level site with stable soil; fill, rock, high groundwater or contamination are extra |
Size, shape and the office
The two drivers owners most often underestimate are the size of the office and the shape of the building. Altus includes “a finished office component” in its warehouse rate but doesn’t give its size, so if your program calls for a large office, a showroom or a second-floor office over the docks, price that area on its own. For reference, the same guide puts Class B office interior fit-out in the GTA at $110 to $150 per square foot, on top of the base building. Shape works the other way: a long, narrow building has more wall per square foot of floor than a square one of the same area, and wall is one of the more expensive elements per unit.
Clear height, sprinklers and the slab
These three are set by how high and how heavily you plan to store. Ontario’s Building Code requires sprinkler systems to be designed to NFPA 13, and the design for a high-piled warehouse depends on the commodity, the storage height and the racking. Decide what you’ll store and how high before the structural and fire protection engineers start, and ask your designer to tell you, in writing, which storage configurations the building will and won’t support. A future tenant can then see what the building supports before they sign. If the walls are concrete, our guide to tilt-up construction compares tilt-up, precast and a steel frame with metal panels.
Multi-level industrial
Multi-level warehouses are now built in Canada, and they’re priced at the top of the distribution range because of the structure and ramps they need. Riverbend Business Park Building 5 in Burnaby, part of the experience built at Oxford Properties, was Canada’s first large-scale multi-level industrial building: 707,000 square feet over two full levels with heated-ramp trailer access to the upper floor, fully leased to Amazon and delivered by construction management in 2022.
Costs outside the building: land, charges, approvals and financing
Altus lists the soft costs it excludes, and on an Ontario industrial project several of them are large. Our guide to hard costs vs soft costs sets out how to build the soft side line by line; these are the lines a warehouse adds.
Site works and servicing
On a warehouse site, site development is a big line: grading, the truck court, trailer parking, car parking, curbs, fencing, landscaping, stormwater management and the services from the street. Use the Altus per-acre servicing rate and the surface parking rate for a first number, then replace them with quantities once the site plan is drawn.
Development charges
Industrial development charges in the GTA are charged per square metre or per square foot of floor area, by the region and the local municipality, with school board charges on top. They’re due at the first building permit unless an agreement says otherwise, so they come out of equity or an early draw, not at the end. Three examples on the day:
| Where | What applies to industrial | Rate |
|---|---|---|
| Mississauga (Peel Region) | Region of Peel $246.45/m², City of Mississauga $133.19/m², two school boards $16.15/m², effective August 1, 2026 to January 31, 2027 | $395.79/m² (about $36.77 per sq ft), plus a City stormwater charge of $5,960 per hectare of site |
| York Region | Region-wide industrial, office and institutional rate, effective May 21, 2026, before the local municipality’s charge and any education charge | $26.37 per sq ft of GFA |
| City of Toronto | ”Industrial uses, as defined” are exempt from City development charges under the City’s by-law | Exempt as defined; confirm your use qualifies |
Sources: City of Mississauga DC rates, August 1, 2026; Region of Peel DC rates, August 1, 2026; York Region DC rates, May 21, 2026; City of Toronto DC FAQ (updated January 26, 2026).
Here’s the arithmetic. A 100,000 square foot warehouse is about 9,290 square metres. In Mississauga, at $395.79 per square metre, that’s about $3.68 million in development charges, before the stormwater charge on the site area. Peel indexes its rates every February 1 and August 1, so a permit pulled in February 2027 will pay a different number.
Three things to check in any municipality. First, how the by-law measures floor area: Mississauga charges on total floor area, and each by-law defines its own area and what counts as industrial. Second, whether your use is industrial at all: a warehouse with a large retail showroom or a self-storage use may fall into a different class. Third, the rate freeze. Under section 26.2 of the Development Charges Act, the charge is generally set at the rate on the day of the site plan application, as long as the building permit follows within 18 months of that approval. Our guide to development charges in Ontario covers the freeze and the exemptions in full.
Parkland and other municipal charges
Under section 42 of the Planning Act, a municipality can require land for parks, or a payment instead, of up to 2% of the land for commercial or industrial development. Building permit fees, site plan application fees and securities, and engineering review fees are added by each municipality on its own schedule. Ask each municipality for its current fee schedule before you set the budget.
Site plan control
Most new warehouses go through site plan control, where the municipality approves layout, grading, servicing, access and landscaping before a building permit. Toronto, for example, exempts industrial buildings up to 2,000 square metres, but most warehouses are larger. Site plan is where many industrial costs get fixed: road widenings, turning lanes, stormwater ponds or tanks, landscaping and the securities posted to guarantee them. Our site plan control guide sets out the process and the fees.
It’s also where much of the schedule goes. A December 2024 survey Altus Group carried out for the Ontario Association of Architects reported an average of 34.6 months for non-residential site plan approvals, against 23 months across all types. The sample was small (31 responses), so treat it as a sign that site plan time should be planned for rather than as a forecast.
Conservation authority permits
Many GTA industrial sites sit near a creek, valley or wetland regulated by a conservation authority: TRCA, Credit Valley, Halton, Lake Simcoe and others. Development in a regulated area needs a permit under the Conservation Authorities Act. Under O. Reg. 41/24, you can ask the authority for a pre-submission consultation to confirm what a complete application needs, and once you apply the authority has 21 days to tell you whether it’s complete. Check the regulation mapping during due diligence. A setback from a regulated area can take developable land off a site, which changes the land price you should pay.
Hydro and other utilities
The electrical service is one of the longest-lead items on an industrial project, and it can come with a capital contribution. Ontario’s local distribution companies decide what a new connection costs the customer through an economic evaluation set out in the Ontario Energy Board’s Distribution System Code, Appendix B (revised August 14, 2025). Where the utility has to expand its system to serve you, the difference between the cost and the expected revenue can fall to the owner. Give the utility a realistic load early, including automation, charging and any future solar, and ask for an offer to connect before you fix the budget.
Land, consultants, financing and HST
Land is its own line and outside every cost guide. Consultants (architect, structural, mechanical, electrical, civil, landscaping, geotechnical, environmental and fire protection), legal, insurance, bonding, permits, a contingency and construction financing all sit on top of the hard cost. Interest is charged on drawn amounts, so a project that takes longer to approve costs more to carry. HST at 13% applies to construction and most soft costs; whether you can recover it depends on your own tax position, so ask your accountant how to carry it in the budget. Our guides to construction financing in Ontario and how much contingency is enough cover those two lines.
Design-build or tender? CCDC 14 vs CCDC 2
Industrial buildings are one of the building types that suit design-build best, because a warehouse can be described largely by what it has to do: area, clear height, slab loading, dock count, sprinkler design, office area and site layout. On a design-build contract you set those out in a Statement of Requirements, the design-builder designs and builds to it, and you get one price earlier. On a traditional tender, your own consultants design the building, contractors bid on a complete set of drawings, and you sign a stipulated price contract.
| Design-build (CCDC 14 – 2026) | Design-bid-build (CCDC 2 – 2020) | |
|---|---|---|
| Who designs | The design-builder, to your Statement of Requirements | Your consultants, under your own contract with them |
| When the price is fixed | At contract, often from an early design | At tender, from complete drawings |
| What you control | The requirements and what you approve at design reviews | Every design decision |
| Main risk to manage | A thin Statement of Requirements, so the design-builder chooses what you didn’t specify | A longer schedule and design changes after tender |
| Suits | A clear, repeatable building type with a decisive owner | An owner who wants to control the design, or a complex building |
CCDC publishes the current design-build form as CCDC 14 – 2026, a design-build contract for a single, pre-determined stipulated price. There is also a new progressive design-build form, CCDC 32 – 2026, where the price is agreed in stages as the design develops. Our guides to the CCDC 14 design-build contract and to design-build vs design-bid-build cover the forms and the choice in depth.
For a warehouse, the choice usually depends on how well you can describe what you need. An owner-user who knows their racking and dock count can write a tight Statement of Requirements; a landlord building on spec may want to control the design so it suits the widest range of tenants. Our own industrial experience covers both: Riverbend Business Park Building 3 in Burnaby, a large-format industrial building within Oxford Properties’ LEED-certified business park, was a lump-sum delivery in 2020, and Building 5 was delivered by construction management.
Two things apply whichever route you take. The Construction Act’s payment rules apply to design-build contracts as much as to any other: 10% holdback on each payment, proper invoices paid within 28 days, and annual holdback release on multi-year contracts since January 1, 2026. And get an independent estimate of your own before you compare proposals, so you can see which price covers your program and which leaves parts of it out. Our guide to reading a construction estimate explains the classes and the lines to check.
Stages from site plan to occupancy
How long a warehouse takes depends on the site, the municipality and the approvals, so plan it as stages, each with its own decision and spend. On most GTA industrial projects they run like this:
- Feasibility and due diligence. Zoning, official plan designation, servicing capacity, conservation authority mapping, a Phase One environmental site assessment, a geotechnical report, a survey and a first budget from the cost guide. This is where you decide whether to buy the land and at what price.
- Program and first estimate. Area, clear height, docks, slab, sprinklers, office, site layout and power. Price it as a Class D estimate, built from the program, before you sign with a design-builder or a design team.
- Pre-consultation with the municipality. Most GTA municipalities require it before a site plan application. It sets the list of studies and drawings the application needs.
- Site plan application and approval. Submission, circulation to departments and agencies, resubmissions, the site plan agreement and securities. The development charge rate is generally frozen on the day the application is made.
- Conservation authority permit, where the site is regulated, usually run alongside site plan.
- Contract. Tender or design-build proposal, an estimate to compare it against, and the contract signed, with supplementary conditions written for your project.
- Building permit. Development charges, permit fees and any parkland payment are paid at or before issue. Some municipalities allow an early permit for excavation and foundations.
- Construction. Monthly progress claims, 10% holdback, proper invoices paid in 28 days, changes priced before they’re built, and the utility connection scheduled from the start.
- Substantial performance, occupancy and takeover. The certificate of substantial performance, occupancy under the Building Code, commissioning, close-out documents and the deficiency list.
- Holdback release and warranty. Holdback paid once the lien period expires, and the warranty period started.
Stages 3 to 5 depend on other parties and most often run long, so start the utility, conservation authority and geotechnical work during stage 1.
A budget checklist before you commit to land or a design-builder
Before you sign an agreement of purchase and sale, a design-build contract or a construction contract, work through this list.
- Set the program in writing. Gross floor area measured the CIQS way, clear height, column grid, slab loading and flatness, dock doors and levellers, sprinkler design basis, office area and finishes, heating, power and car and trailer parking.
- Place your building in the published range. Start from the Altus GTA warehouse or distribution rate, decide where in the range you sit and write down why.
- Carry it forward. Move the January 2026 figure to your tender date with the Statistics Canada Toronto warehouse index, and carry escalation and tariff risk as named lines.
- Price the office separately if it’s more than a small component, using an office fit-out rate.
- Price the site on its own. Servicing per acre, the truck court, car parking, stormwater and landscaping, with the geotechnical report in hand.
- Get the development charges on the day. Regional, local and education charges from the current schedules, the floor area as the by-law measures it, and the indexing date that applies to your permit.
- Confirm the approvals. Site plan, conservation authority and any rezoning or minor variance, with the fees and securities each one needs.
- Ask the utility for a connection estimate with a realistic load, and confirm water and sanitary capacity.
- Build the soft side line by line. Consultants, legal, insurance, bonding, permits, financing and HST, from quotes and schedules rather than a single percentage.
- Set a contingency for design development and one for construction, and say what each is for.
- Choose the delivery route and the contract form, and get an independent estimate to compare the price against before you sign.
- Test the total against the business case. Rent per square foot or the operating saving for an owner-user, against the full project cost, land included.
Frequently asked questions
How much does it cost to build a warehouse per square foot in Ontario?
In the GTA, the Altus Group 2026 Canadian Cost Guide puts warehouse construction at $75 to $180 per square foot and distribution facilities at $170 to $480, priced at January 31, 2026. That’s hard cost for the building only, excluding HST, site development, land, development charges, consultants and financing. Outside the GTA, Altus’s only Ontario city is Ottawa, at $120 to $170 for a warehouse.
How long does it take to build a warehouse in Ontario?
Approvals, particularly site plan control and any conservation authority permit, often take longer than the build, and a 2024 Altus Group survey for the Ontario Association of Architects reported non-residential site plan approvals averaging 34.6 months, from a small sample. Plan the project in stages and start the utility, geotechnical and approvals work as early as you can.
Can I build a warehouse on a design-build contract?
Yes, and it’s a common route for industrial buildings. In Ontario the usual form is CCDC 14 – 2026, a design-build contract for a stipulated price, with CCDC 32 – 2026 for progressive design-build. The quality of the result depends on your Statement of Requirements: clear height, slab, docks, sprinklers, office and site, in writing, before the design-builder prices it.
Does a bigger warehouse cost less per square foot?
Usually, yes. Walls, foundations, the office and site overheads are spread across more floor area as a building grows, so the cost per square foot tends to fall. The total cost still rises, and a larger building can carry larger site, servicing and development charge bills. Price your own program rather than assuming the low end of the range.
Where to start
If you’re looking at a site, set the program and a first budget before you make an offer, using the checklist above, and test the total against what the building has to earn or save.
We’ve spent more than 20 years on office, residential, retail and industrial projects across BC, Alberta, Ontario and Quebec, with experience built at PCL Constructors and Oxford Properties, including the Riverbend Business Park buildings above. That experience also includes the Mississauga Transit Campus Expansion, a 466,000 square foot expansion of the city’s transit maintenance and storage campus. If you’d like an independent estimate before you commit to land, a design-builder or a contract, that’s where we start.