How the Work Letter in a Commercial Lease Works in Ontario

A work letter is the part of a commercial lease that says who builds what before you open. It’s usually a schedule attached to the lease, sometimes called the construction schedule or Schedule C, and it lists the landlord’s work, the tenant’s work, the standard each has to meet, how plans get approved, who pays, and how the construction dates connect to the date rent starts. Most work letters take one of three shapes: turnkey, where the landlord builds the space for you; allowance, where you build it with some of the landlord’s money; and as-is, where you build it and pay for it.

The work letter decides your fit-out budget and schedule before you’ve hired a designer or a contractor. It’s also the part of the lease most tenants sign without anyone from construction reading it. Your lawyer drafts and reviews the lease, and nothing here is legal advice. This article is the construction side: what each clause means once the drawings start and the trades show up, and what to settle while the deal is still an offer to lease.

Turnkey, allowance or as-is

Every work letter answers one question first: who is building the space, and with whose money.

Turnkey: the landlord builds it

In a turnkey deal the landlord designs and builds the space to an agreed plan and hands you the keys to a finished premises. You approve the layout and the finishes; the landlord hires the designer and the contractor and carries the construction risk.

Turnkey suits a tenant who doesn’t want to run a construction project, has a fairly standard layout, and would rather pay for the build through the rent than up front.

The trade-off is visibility: you don’t see the contractor’s prices, so you can’t easily tell what a change should cost. The landlord’s idea of “building standard” finishes may not match yours, and anything above standard comes back to you as an extra. And because the landlord runs the schedule, the work letter has to say clearly what happens if they’re late.

Allowance: you build it with the landlord’s help

In an allowance deal the landlord delivers the space in a stated condition and gives you a sum of money, usually per square foot, toward your own fit-out. You hire the designer and the contractor, you carry the construction risk, and the landlord pays the allowance on the terms the lease sets out. How allowances are paid, what they cover and where the shortfall usually comes from is its own subject, covered in our guide to tenant improvement allowances in Ontario. In the work letter, the allowance is one clause among many.

This shape suits a tenant with a specific design or a brand standard to meet. You see every price and every change, and you own every overrun above the allowance.

As-is: you build it and pay for it

An as-is deal gives you the space in its current condition with no landlord’s work and no allowance. The landlord usually reflects that in the rent or in a longer rent-free period. As-is can be a good deal where the last tenant’s layout suits you, and an expensive one where their walls, ceilings, ductwork and wiring all have to come out first. A walk-through with a builder before signing matters most here.

Comparing the three

TurnkeyAllowanceAs-is
Who designsLandlord’s designer, to your approved planYour designer, with landlord approvalYour designer, with landlord approval
Who hires the contractorLandlordYouYou
Who carries cost overrunsLandlord, except for your changes and upgradesYou, above the allowanceYou
Who carries schedule riskMostly the landlordMostly youYou
How you payThrough the rent, plus any extrasUp front, then the allowance comes backUp front
What you can seeThe finished space, not the pricesEvery priceEvery price
Most important clauseThe plan and spec you approve, and the delay remediesThe allowance terms and the landlord’s workThe condition of the space on the day you sign

Many leases blend these, with base building items as landlord’s work and an allowance for the rest. The labels matter less than the list of who does each item.

Landlord’s work vs tenant’s work

The heart of every work letter is two lists. Landlord’s work is what the landlord does, at their cost, before or while you build. Tenant’s work is everything else, usually described simply as any work not listed as landlord’s work, done by you at your cost with the landlord’s approval.

Most landlord’s work lists start from the phrase base building condition. The phrase has no fixed meaning, so the lease has to supply one. In practice it usually means the structure and envelope are complete, the main building systems are in place and working to a point at or near your space, and the space is code-compliant as a shell. What “to a point” means is where most of the argument happens, which is why each item needs to be written down rather than covered by a phrase.

The table below is the split we see most often in office and multi-tenant retail space, and the item on each line that most often turns out to be ambiguous. Your lease will differ.

ItemUsually landlord’s workUsually tenant’s workWhere it’s usually unclear
Structure, roof, envelopeAll of itNothing, except openings you ask forNew openings for exhaust, storefronts or equipment
Demising wallsBuilt to full height between unitsFinishes on your side, any upgradesFire rating, sound, and who builds a new wall when a unit is split
HVACA unit or a main supply sized for the space, capped at the unitDistribution ductwork, diffusers, thermostats, zoningCapacity per square foot, the age of the unit, and whether “distributed” means anything
SprinklersMains and heads in a standard patternRelocating heads to suit your ceiling and wallsWho pays for relocation and the sprinkler contractor the building requires
Fire alarmBase building panel, devices to code for an open shellNew devices for your layout, connection to the panelWhether the building’s own trade must do the connection, and at what rate
ElectricalA panel of stated amperage in or near the spaceDistribution, lighting, power, dataWhether the service is enough for your equipment
WashroomsBase building washrooms on multi-tenant floors; a stub or rough-in for single unitsIn-suite washrooms, and barrier-free upgrades if the building has noneWhether existing washrooms meet current barrier-free rules
Floor and ceilingLevel slab, ceiling grid on some office floorsFinishes, ceiling where none is providedLeftover adhesive, floor levelling, and old ceilings that don’t meet code
Hazardous materialsAsbestos report, removal of known materials in the shellAnything your work disturbs that wasn’t knownWho pays for what’s found behind walls once work starts

A few items need more than a line in a table.

HVAC. “HVAC in good working order” and “HVAC sized for office use at a stated load and distributed to suit the tenant’s layout” are very different promises. Ask for the capacity in writing and for the age of the equipment serving your space. If a rooftop unit is near the end of its life, settle now whether the landlord replaces it as landlord’s work or whether it becomes yours the first summer it fails. A recent building condition assessment is the fastest way to find out.

Demising walls. Whether the walls between you and the next unit need a fire rating depends on what’s on each side and whether the building is sprinklered, and the rating and who pays are set in the lease. Our guide to demising walls in Ontario sets out the Building Code rules and the usual split.

Hazardous materials. Ontario’s O. Reg. 278/05 requires the owner to have an asbestos report prepared before alteration work is tendered and to give it to the bidders. In an older building, ask the landlord for the report before you sign, and put removal of known materials on the landlord’s list.

If you’re leasing a store, our guide to building out a retail store in Toronto goes further into shell, warm shell and vanilla box condition and the items specific to retail units.

The clauses that move the budget and the schedule

Beyond the two lists, a work letter is a set of procedures: how drawings get approved, who’s allowed to build, how the money moves, and how the construction dates connect to rent. These are the clauses we’d read first, and what each one means on the ground.

Plans approval

Almost every work letter requires your drawings to be approved by the landlord before you apply for a building permit or start work. Look for three things: how many days the landlord has to respond, what standard they apply (“acting reasonably”, or at their sole discretion), and how many rounds of comments you should expect. Build that review into the design schedule, because the clock on your fixturing period may already be running.

Design standards and approved trades

Most multi-tenant buildings have a tenant design criteria manual or a building standards document that the work letter makes part of the lease. It covers ceiling heights, lighting, materials, storefront systems, sign criteria and the rules for work on base building systems. Read it during the deal: a required ceiling tile, light fixture or storefront system is a cost.

Look too for a list of trades you must use. It’s common for a landlord to require its own sprinkler, fire alarm, roofing and building automation contractors for any work that touches those systems. That makes sense for the landlord, who has to keep the building’s systems working and their warranties intact. It also means those prices aren’t tendered, so ask for the rates or a price on your layout before you sign.

Supervision and review fees

Many work letters charge the tenant a fee for the landlord’s review of drawings and oversight of the tenant’s work, often a percentage of the construction cost, and sometimes deducted from the allowance. Ask what the fee is, what it’s a percentage of (hard cost only, or the whole project), whether it has a cap, and whether it’s charged on landlord’s work done at the tenant’s cost. In a turnkey deal, ask the same about the landlord’s construction management fee on your extras.

The construction schedule and the fixturing period

The fixturing period is the time after you get possession when you’re building but not yet paying base rent. You’ll usually still pay utilities and carry insurance. What matters is how the period is measured: a fixed number of days from possession, or until you open, whichever comes first, is the common form.

The trouble usually comes from the trigger for possession. A 2024 Ontario Superior Court decision, 720443 Ontario Inc. v. 2682543 Ontario Inc., 2024 ONSC 5802, shows how this works. The restaurant lease gave the tenant a 120-day fixturing period starting on the date the landlord’s work was “completed to a stage sufficient to permit Tenant to commence fixturing.” The tenant refused to start until all of the landlord’s work was finished. The court read the lease as a whole and found that the landlord only had to reach that stage, that the two could be working in the space at the same time, and that the tenant had breached the lease by not taking possession. Disputes about the state of the landlord’s work were to be decided by the landlord’s architect, a process the tenant never used.

The construction lesson is that the possession trigger, the notice you get before it, and who decides whether the space is ready should all be read together and checked against your own schedule. If the fixturing period can start while the landlord is still working, the two sets of trades have to share the space, and your contractor’s price should assume it.

Rent commencement and “substantial completion”

Rent usually starts on the earlier of the end of the fixturing period and the day you open. In a turnkey deal it’s often tied to substantial completion of the landlord’s work, and that phrase needs a definition in the lease.

The Ontario Court of Appeal’s decision in Paletta International Corporation v. Liberty Freezers London Ltd. (2021 ONCA 383) turned on exactly this. As Daoust Vukovich summarised it in 2022, the lease of a refrigerated warehouse started on “substantial completion of the landlord’s work”, and that work had to meet Canadian Food Inspection Agency requirements. The trial judge took the date the engineers certified the building ready for occupancy. The Court of Appeal found that occupancy readiness under the Building Code wasn’t the same as completion to the food-safety standard the lease called for, so the lease hadn’t started on the date the landlord relied on. The same commentary notes that the Construction Act’s “substantial performance” is a different test again, and that a lease shouldn’t assume the statutory meaning applies.

For the work letter, define substantial completion in terms you can check on the day: the items on the landlord’s list are complete except minor deficiencies that won’t stop your work, the space has whatever occupancy or inspection sign-off it needs, and a joint walk-through has produced a deficiency list with a date to finish it.

Delays on either side

A good work letter treats delay symmetrically. Landlord delay is anything that holds up your work because the landlord’s work is late, the landlord is slow to approve drawings, or the landlord’s required trades don’t show up. The usual remedy is that your fixturing period and rent commencement move by the same number of days. Some leases add a day of free rent per day of delay after a grace period, and an outside date after which you can walk away.

Tenant delay is the mirror: late drawings, changes you ask for in a turnkey build, long-lead items you chose, or your contractor holding up the landlord’s work. The usual consequence is that rent starts on the date it would have started without your delay.

The parts that cause arguments are the notice requirements (a delay is often only counted if notice was given in writing within a few days), whether delays overlap and net against each other, and what counts as beyond either party’s control. The notice clause only works if someone keeps a delay log from the first week.

Changes

In an allowance deal, a change to your design after approval goes back to the landlord for approval and is otherwise your business with your contractor. In a turnkey deal, every change you ask for is a change to the landlord’s contract, priced by their contractor. Ask for the process in writing: who prices a change, how quickly, the landlord’s markup, and whether it extends the schedule or counts as tenant delay. Our article on where change orders come from explains why most of them start at the design stage.

Permits and inspections

The work letter usually makes you responsible for the building permit for your work and for the inspections and sign-offs that follow, after the landlord has approved the drawings. In Toronto, the City’s review streams aim to complete the first review of a complete application in 15 business days for small buildings, 20 for large and 30 for complex ones. Small office and retail interiors may qualify for Express Services, a review within three days for interiors up to 600 square metres with no change of use. If the landlord’s work needs its own permit, that should be on the landlord’s side of the list, and your permit may depend on theirs being in place.

As-built drawings and closeout

Most work letters require as-built drawings, permit closeout and warranties at the end of the job, often as conditions of the allowance. Your contract with your builder should require the same documents on the same timeline.

Restoration at lease end

The work letter or the lease will say what you may be asked to remove when you leave. A restoration clause is a cost at the far end of the lease that no allowance covers. The best time to settle it is when the landlord approves your drawings, by asking them to name the items they’ll want removed. Our guide to leasehold improvements in Ontario covers who owns what at the end and how Ontario courts read these clauses.

What to settle at the LOI stage

The letter of intent or offer to lease is where the work letter’s terms are cheapest to change. Once the lease is signed, the landlord’s work, the allowance and the dates are fixed, and anything left vague will be settled by whoever has to pay for it. These are the construction points we’d want in writing at offer stage.

  1. The shape of the deal. Turnkey, allowance, as-is, or a blend, and which items fall under each.
  2. A test fit. A preliminary layout from your designer, priced by a builder, before you agree the numbers. It tells you whether the space works and how far the allowance goes.
  3. The landlord’s work, item by item. HVAC capacity and distribution, electrical service, sprinklers, fire alarm, washrooms, demising walls, floor and ceiling condition, and hazardous materials.
  4. The definition of complete. What “substantially complete” or “ready for fixturing” means, how it’s confirmed, and who decides if you disagree.
  5. The fixturing period. How long, from what trigger, how much notice before it starts, and whether it extends for landlord delay.
  6. Rent commencement. The trigger, and what happens if you open early or late.
  7. Delay remedies. Day-for-day extension for landlord delay, any free rent after a grace period, an outside date, and the notice rules for both sides.
  8. Early access. Access before possession for measuring, investigation and long-lead coordination, at no cost.
  9. Approvals. Landlord response times for drawings and the standard they’ll apply.
  10. Required trades and fees. Which trades are mandatory, their rates, and any review or supervision fee and its cap.
  11. The allowance, if there is one. Amount, eligible costs, how and when it’s paid, and whether it’s plus HST. The detail is in our allowance guide.
  12. Turnkey extras. How upgrades and changes are priced, and the markup.
  13. Restoration. What you’ll be asked to remove, settled now or at drawing approval.

Not every point needs to be in the LOI. The ones that move the money are 1, 3, 5, 6 and 11; the rest can wait for the lease if the LOI says the work letter will cover them. Landlords want the same things settled: a vague landlord’s work list becomes an argument at possession for them too, and a fixturing period that’s too short gives them a tenant who starts the lease behind.

Ontario rules that sit behind the work letter

A work letter is a private agreement between landlord and tenant, but three sets of Ontario rules apply to the work it describes whatever the lease says.

The Construction Act applies to the tenant’s work

When you hire a contractor to build your space, you’re the “owner” of that improvement under Ontario’s Construction Act. You hold back 10% of each payment, you pay proper invoices within 28 days unless you give notice of non-payment within 14, and the people working on your fit-out have lien rights. Our guide to construction lien holdback in Ontario sets out how that works.

Under section 19(1) of the Act, where the landlord pays for all or part of the tenant’s improvement under the lease, the landlord’s interest in the property is subject to liens up to 10% of that payment. That’s why many landlords hold back part of the allowance until the lien period on your job has expired, and ask for a statutory declaration that your trades have been paid before releasing it. Expect it, and plan your cash flow around it. Under a turnkey deal the landlord is the owner of the work and handles holdback with its own contractor.

HST on the allowance

The Canada Revenue Agency treats a landlord’s cash payment toward a tenant’s improvements as consideration for a taxable supply the tenant makes to the landlord (GST/HST Memorandum 19.4.1). In practice, the tenant charges HST on the allowance. If the work letter says nothing, the landlord may read the allowance as HST-included, and the tenant then remits the 13% Ontario HST out of it. Say “plus HST” in the LOI and have your accountant confirm the treatment for your business.

The Building Code and the City

The Ontario Building Code (O. Reg. 163/24, in force since January 1, 2025) applies to both lists of work. Fire separations, exits, barrier-free access, sprinklers and fire alarm all have to meet the code for your use of the space, whoever builds them. A space delivered code-compliant for an office may need more to suit a restaurant or a clinic, and the work letter needs to say whose cost that is.

Frequently asked questions

What is a work letter in a lease?

A work letter is a schedule to a commercial lease that sets out the construction needed before the tenant opens. It lists the landlord’s work and the tenant’s work, the standards each must meet, how drawings are approved, any allowance and how it’s paid, and how construction dates connect to the fixturing period and rent commencement. It may also be called the construction schedule, or simply a schedule to the lease.

Who pays for leasehold improvements?

The tenant usually pays for the work inside the unit, often with help from a landlord’s allowance, while the landlord pays for the base building items in the landlord’s work list. In a turnkey deal the landlord pays up front and recovers the cost through the rent, with the tenant paying for upgrades and changes. The work letter is where the split is written down, item by item.

What is a turnkey build-out?

A turnkey build-out is a lease arrangement where the landlord designs and builds the tenant’s space to an agreed plan and hands over a finished premises. The tenant approves the layout and finishes but doesn’t hire the contractor. It’s simpler for the tenant, but you don’t see the build costs, upgrades cost extra, and the delay clauses matter more because the landlord runs the schedule.

What is the landlord’s work?

The landlord’s work is the list of construction the landlord agrees to do, at its own cost, before or while the tenant builds. It usually covers base building items: structure, envelope, demising walls, HVAC to a point, sprinkler mains, electrical service and washrooms.

What to do next

At the offer-to-lease stage, the most useful step is to have someone who builds read the work letter against the space: walk the unit with the landlord’s work list in hand, price a test fit, and check the possession, fixturing and rent dates against a realistic schedule. A gap found at offer stage can still be negotiated.

Our 20+ years of experience was built at PCL Constructors and Oxford Properties, a contractor and a landlord, so we read a work letter knowing how each side will price and schedule it. Our fit-out project management work starts at that stage: reading the work letter, setting the budget and schedule, and running the design, permit and build so you open on the date the lease assumes. If you’re planning an office move, our guide to planning an office renovation in Toronto covers the steps that come after the lease is signed.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada