November 3, 2026

Demising Wall Rules in Ontario, From Fire Rating to Who Pays

A demising wall is the wall between your leased space and the space next door: another tenant’s unit, or a common corridor. It marks where your premises end, which is where the word comes from (a lease “demises” premises to a tenant). In Ontario, the thing that matters most about a demising wall is whether the Building Code requires it to be a fire separation with a fire-resistance rating. For a store or a restaurant it usually does, most often at 45 minutes or one hour. Between two offices, the code doesn’t ask for one. That one answer sets how the wall is built, what it costs, and who has to sign off on it.

Demising wall, partition wall or firewall?

“Demising wall” is a leasing word, not a Building Code term. The code talks about suites and fire separations, and the requirements attach to those, so the first step is translating.

A suite, in the code, is a room or series of rooms of complementary use operated under a single tenancy. Your leased unit is a suite. A fire separation is an assembly that acts as a barrier against the spread of fire. It may or may not need a fire-resistance rating, which is the time in minutes or hours the assembly has been shown to hold back a standard fire. A firewall is a specific, much heavier kind of fire separation that divides one building into what the code treats as separate buildings.

Demising wallPartition wallFirewall
What it doesDivides one tenancy from another, or from a common corridorDivides rooms inside one tenancyDivides a building into separate buildings for code purposes
Is it a code term?No, a leasing termNo, a general termYes, defined in the Ontario Building Code
Fire ratingOften 1 h or 45 min; sometimes none (see below)Usually none, unless it encloses an exit, a service room or similar2 h or 4 h
ConstructionUsually steel studs and Type X gypsum board in a tested assembly, carried to the structure aboveUsually studs and gypsum board to the ceilingMasonry or concrete, with limited exceptions up to 2 h
Ends atThe underside of the floor or roof deck above, when ratedOften just above the ceilingThe full height of the building, and stays standing in a fire

Is a demising wall a fire wall?

Almost never. A firewall under Article 3.1.10.2 of the Ontario Building Code needs a 4-hour rating where it separates floor areas containing a Group E (mercantile) or Group F, Division 1 or 2 (industrial) occupancy, and a 2-hour rating otherwise. It must be noncombustible, its rating must generally come from masonry or concrete, and it has to stay standing if the structure on one side collapses.

A demising wall is an ordinary fire separation, when it’s rated at all: usually steel studs with fire-rated gypsum board on both sides, built to a tested design. If someone calls your demising wall a firewall, they almost certainly mean “fire-rated wall”. It’s worth asking, because a real firewall is a different order of cost.

Some government tenants need a demising wall built to a security specification, such as the RCMP’s secure demising wall guide (G1-302). That’s about forced entry, not fire, and applies only if your lease or client requires it.

What the Ontario Building Code requires between tenancies

The current code is O. Reg. 163/24, in force since January 1, 2025. It adopts the National Building Code of Canada 2020 with Ontario’s amendments, published together as the 2024 Building Code Compendium, which is where the article numbers below come from. Your designer confirms how they apply to your building.

Which part of the code applies

Division A, Article 1.3.3.3 sends small buildings to Part 9: three storeys or less, a building area of 600 m² or less, and used for residential, business and personal services, mercantile or medium- and low-hazard industrial occupancies. A one-storey strip plaza is often a Part 9 building. Office towers, malls and most mixed-use buildings fall under Part 3. The two parts say much the same about tenancies, with different ratings.

The code also sorts uses into occupancy groups. The ones that matter for leased space are Group D (business and personal services: offices, banks, salons, clinics), Group E (mercantile: stores) and Group A, Division 2 (assembly, which includes restaurants).

The general rule: separate each suite

In a Part 3 building, Sentence 3.3.1.1.(1) requires each suite, other than a business and personal services suite, to be separated from adjoining suites by a fire separation with a fire-resistance rating of at least 1 hour. Sentence (2) lets that drop to 45 minutes where the floor assembly above the floor area (or below it, if there’s nothing above) is itself permitted to have less than a 1-hour rating.

In a Part 9 building, Sentence 9.10.9.15.(1) sets the same rule at 45 minutes.

The exceptions that change the answer

The corridor side of the unit

The wall between your unit and a common corridor is a demising wall too, and it has its own rule. Article 3.3.1.4 requires a public corridor to be separated from the rest of the storey by a fire separation with a 45-minute rating. If the storey is sprinklered throughout, no rating is required (unless the corridor serves care, detention or residential uses), and in some sprinklered arrangements no fire separation is required at all. Part 9 says much the same in Article 9.10.9.17, with conditions on how the sprinkler system is monitored. In an unsprinklered building, the corridor wall is often rated even when the wall to the neighbouring office isn’t.

What “rated” means on site

A rating comes from testing. Under Article 3.1.7.1 it comes from a fire test to CAN/ULC-S101, or from the assemblies listed in the province’s Supplementary Standard SB-2. Interior fire separations must be rated for fire on each side (Sentence 3.1.7.3.(2)). In practice your designer picks a tested or listed wall design and the drawings name it, down to the stud gauge, board type and layers. Then the code adds four things that matter as much as the wall itself:

  1. Continuity to the structure above. A fire separation must be a continuous element (Article 3.1.8.1). Where a ceiling space sits above it, that space has to be divided at the wall by an equivalent fire separation (Sentence 3.1.8.3.(1)). In plain terms, a rated demising wall stops at the underside of the floor or roof deck above, not at the suspended ceiling.
  2. Firestops at the edges. Where a rated wall meets the floor, the deck or another rated wall, the joint is sealed with a firestop system tested to CAN/ULC-S115 (Sentences 3.1.8.3.(2) and (3)), with an exception for certain gypsum board joints that are built to stop flame and smoke.
  3. Firestops at every penetration. Each pipe, duct, cable and conduit that passes through a rated wall needs a tested firestop with an F rating at least equal to the wall’s rating (Article 3.1.9.1). Sprinkler pipes can pass through with a metal escutcheon plate, and ducts usually need fire dampers installed to NFPA 80.
  4. Rated doors and openings. A door in a fire separation is a closure and has its own rating under Table 3.1.8.4: a 45-minute door in a 45-minute or 1-hour wall, a 1.5-hour door in a 2-hour wall. That includes the frame, the hardware and a closer.

Penetrations are where most inspection comments on a demising wall land. They’re also what a later tenant’s trades disturb, which is why the lease checklist below deals with them.

Sound between tenants

The code’s sound rules apply to dwelling units and hotel suites (Article 9.11.1.1 and Article 3.3.4.6). They don’t apply between commercial tenants. If you’re a therapist next to a gym, or a law office next to a music school, the code gives you no minimum. Whatever sound performance you need has to be written into the lease or work letter as a sound transmission class (STC) for the wall, with insulation in the cavity and the wall carried to the deck.

Landlord’s work or tenant’s work: who builds it and who pays

Most commercial leases divide the physical work into landlord’s work, built at the landlord’s cost before handover, and tenant’s work, which is everything else. Demising walls sit on the line between the two, so pin down early which side they fall on.

When the landlord usually builds it

In a new building, or a unit the landlord is creating, demising walls are commonly landlord’s work: they define the rentable premises, and the landlord needs them in place to deliver the unit. Our guide to building out a retail store in Toronto lists demising walls in the landlord’s work checklist with the standard to ask for: built to full height, fire separated where needed, finished on your side.

Read “finished on your side” closely. A landlord may deliver the rated board in place but not taped, sanded or primed. That’s a fair split if both sides know it.

When it becomes tenant’s work

The demising wall becomes your cost in a few common situations:

When the work is yours, the cost can usually be charged against your tenant improvement allowance, if the lease allows it. How the allowance is paid and what it typically covers is in our guide to tenant improvement allowances in Ontario.

Who pays later

Every time a tenant on either side runs a duct, pipe or cable through the wall, someone has to firestop it. The lease should say each party seals its own penetrations to the original rating, at its own cost. If yours is silent, ask the landlord to add it.

Who owns it at the end

A demising wall built into the building is a leasehold improvement. Unless the lease says otherwise, improvements attached to the building become the landlord’s when they’re installed, as Daoust Vukovich LLP explains in its note on removal and restoration. Whether you must remove a wall you built or moved at lease end is a restoration clause point, covered in our guide to leasehold improvements in Ontario.

Splitting a unit to re-let it

When a big tenant leaves, landlords often divide the unit. The new wall is the visible part; the code consequences of turning one suite into two are usually bigger, and they’re a landlord cost because they create the rentable space:

The use matters too. If a new tenant will use the space differently than before, say a clinic or a restaurant where there was a store, the permit may be a change of use. Under section 10 of the Building Code Act, changing the use of all or part of a building in a way that increases the hazard needs a permit even if no construction is proposed. Zoning also has to permit the new use. In Toronto, the City won’t commit to a review time for a building permit application that lacks a Zoning Applicable Law Certificate, according to its building permit review streams page.

Before committing to a split, get a short test fit and code review from an architect: where the line goes, where each unit’s exit and services come from, and which uses the new walls will allow.

Permits and inspections in Toronto

Does a demising wall need a permit?

Yes. Building a new demising wall, moving one or opening a door in one is construction, and section 8 of the Building Code Act says no one may construct a building, or cause it to be constructed, without a permit from the chief building official. In practice the wall is rarely a permit on its own. It’s part of the permit for the landlord’s base building work or for your fit-out.

The City of Toronto’s guide to non-residential interior alterations asks for floor plans showing existing and proposed wall assemblies and fire separations, sections that detail the fire separations, and specifications for every wall assembly. That’s where the rated design gets named, and why the drawings need to show the wall going to the deck. Toronto measures the permit fee area to the centre line of demising walls. From January 1, 2026, the fee for interior alterations is $12.45/m² for Groups A, B and D and $11.53/m² for Groups C, E and F, measured on the area receiving work.

How long the City takes

For a complete application, Toronto’s targets are 15 business days in the small building stream, 20 for large buildings and 30 for complex ones. Express Services reviews interior alterations to Group D and E occupancies of up to 600 m² within three business days, as long as there’s no change of use or patron area and no active permit for the building shell. An office or store fit-out that includes a new demising wall can often qualify. A unit split that adds a restaurant, or new retail in a condominium podium still under its shell permit, won’t.

Inspections

The building inspector usually looks at a rated wall at the stages where its rating can still be seen: framing and the board layers before the wall is closed, and firestopping at penetrations and the head of the wall before ceilings go in. Ask your contractor which inspections the City has attached to your permit and when they’re booked, because a missed one can mean opening a finished wall.

What drives the cost and the schedule

There’s no published Toronto cost for a demising wall. Altus Group’s 2026 Canadian Cost Guide prices whole office fit-outs ($110 to $150 per square foot for Class B space in the GTA, $160 to $265 for Class A, before HST) and prices retail as shell, but it doesn’t break out a single wall. So rather than a per-foot number, here’s what moves the price, roughly in order of weight.

DriverWhy it moves the cost
Height to the deckA rated wall goes to the structure above. In a high retail or warehouse unit that’s far more wall, scaffold and framing.
RatingA 2-hour wall has more layers of board than a 1-hour wall, and doors, dampers and firestops step up with it.
PenetrationsEvery duct, pipe, conduit and cable tray crossing the line needs a tested firestop or a fire damper. In an existing building with years of services above the ceiling, this can cost more than the wall.
Services to reworkSplitting a unit means re-zoning HVAC, moving sprinkler heads and adding fire alarm devices, often by contractors the landlord names.
Access and hoursWork in an occupied building is often limited to evenings and weekends by the landlord’s rules. In Toronto, noisy work before 7 a.m. or after 7 p.m. on weekdays, before 9 a.m. or after 7 p.m. on Saturdays, or any time on Sundays and holidays needs a noise exemption under Chapter 591. Premium time costs more.
Existing conditionsIn older buildings, an asbestos report has to be prepared and given to bidders before alteration work is tendered under O. Reg. 278/05. If materials need removing at the head of the wall or around the old ceiling, that comes first.
Sound or security upgradesInsulation, extra board and resilient framing for sound, or a security specification, add materials and labour.

Two quotes for “a demising wall” can be far apart for these reasons. Ask each bidder what height, which tested design and how many penetrations they’ve allowed for, and level the bids on the same basis. Our guide to reading a construction estimate walks through how to compare line items.

Where the wall sits in the schedule

The demising wall is early work. It usually has to be framed, boarded on the rated side, inspected and firestopped before the ceilings close, and on a split it often comes before either tenant’s fit-out can start, because sprinklers, ductwork and the fire alarm are laid out to the new line. If the landlord is building it as landlord’s work, ask for the date it’ll be complete and inspected, and tie your fixturing period or rent start to that date rather than to a calendar day.

Before you sign: a demising wall checklist for the lease

Settle these in the lease or work letter before you sign.

  1. Who builds it. Name the demising walls in landlord’s work or tenant’s work, wall by wall if the unit has more than one neighbour or a corridor side.
  2. To what standard. State the fire-resistance rating, that it runs to the underside of the deck, and that it’s a tested or listed assembly. If your use might need a higher rating than the base building provides, agree who pays the difference.
  3. Finish. Say whether the wall is delivered taped, sanded and primed on the tenant’s side, or board only.
  4. Sound. If it matters to your business, set an STC for the wall and confirm insulation in the cavity. The code won’t set one for you.
  5. Doors and openings. If you need a door into a corridor or between units you lease, confirm the rated door, frame and hardware are included.
  6. Completion date. Tie your fixturing period or rent start to the wall being complete, inspected and firestopped, not to a fixed date.
  7. Penetrations later. Each party firestops its own penetrations to the original rating at its own cost, and makes good any damage from the neighbour’s side.
  8. Moving the line. If the premises may grow or shrink, agree how a relocated wall is paid for and how rent and area are adjusted.
  9. Restoration. Say whether you must remove a wall you built or moved at lease end. Ask the landlord to decide at drawing approval rather than at the end, as our leasehold improvements guide recommends for all improvements.
  10. Existing conditions. In an older building, ask for the asbestos report and confirm who removes anything disturbed when the wall is built.

Frequently asked questions

What is a demising wall?

It’s the wall separating one tenant’s premises from the next tenant’s space or a common corridor, marking the boundary of the premises in the lease. In Ontario the Building Code often requires it to be a rated fire separation, typically 1 hour in larger buildings and 45 minutes in small Part 9 buildings. Office suites side by side are the main exception.

Is a demising wall a fire wall?

No. A firewall is a Building Code term for a noncombustible wall, usually masonry or concrete, rated 2 or 4 hours, that divides a building into separate buildings. A demising wall is usually a steel stud and fire-rated gypsum board fire separation built to a tested design, rated 45 minutes, 1 hour or 2 hours depending on the uses each side, or not rated at all.

Who pays for a demising wall?

The lease decides. In a new or newly created unit the landlord commonly builds them as landlord’s work, because they define the premises. The tenant usually pays when it takes space as is, when its use needs a higher rating, or when it asks for the wall to be moved, often against the improvement allowance.

Does a demising wall need a permit in Toronto?

Yes. A new or relocated demising wall is construction, and the Building Code Act requires a permit first. It’s normally part of the landlord’s base building permit or the tenant’s fit-out permit, with drawings showing the fire separations and wall assemblies. Inspectors check the wall and its firestopping before it’s closed in.

What’s the difference between a demising wall and a partition wall?

A demising wall divides one tenancy from another, or from a corridor, and is often fire-rated and carried to the structure above. A partition wall divides rooms inside one tenancy, usually stops just above the ceiling and normally needs no rating. Partitions are the tenant’s cost; demising walls follow the lease.

What to do next

If you’re about to sign a lease or split a unit, get the demising walls onto the drawings and into the work letter before anything else is priced: rating, height, penetrations and who builds them.

We’ve spent more than 20 years on construction projects across four sectors, with experience built at PCL Constructors and Oxford Properties, including tenant fit-ups across Cadillac Fairview’s downtown office towers. Through our construction project management service we can read the lease and the landlord’s work schedule with you, walk the space with the designer and trades, line up the permit and run the fit-out through to occupancy.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada