Integrated Project Delivery (IPD) and CCDC 30 for Ontario Owners

Integrated project delivery (IPD) is a way of building where the owner, the architect, the builder and often the key trades all sign one contract together, plan the project as one team, and share the risk and reward of how it turns out. The builder and designers are paid their actual costs, their profit goes into a shared pool, and that pool grows or shrinks depending on whether the team hits the cost and other goals everyone agreed at the start. In design-build one firm carries the price for you. In construction management you hire a builder early but each party still has its own contract. IPD puts everyone in one agreement, working to a shared target, and the parties waive most claims against each other. In Canada the standard form is CCDC 30, first published in 2018 and reissued as CCDC 30 – 2025.

IPD and CCDC 30 at a glance
What it isA multi-party contract for integrated project delivery covering “scope allocation, payments, changes, conflict management, termination, insurance and contract security, and liability allocation” (CCDC)
Who signsThe owner and the members of the design and construction team, in one agreement. Key trades can be parties too (Pallett Valo, January 2026)
Price basis”Cost plus with a target price.” The team’s profit sits in a pool that “remains at risk subject to the achievement of mutually agreed project objectives” (CCDC)
PhasesValidation, design and procurement, construction, warranty (CCDC)
Current editionCCDC 30 – 2025, released June 30, 2025, replacing the 2018 edition (BLG, July 2025). Electronic format only
Typical projectLarge, complex buildings where the owner can commit senior people to the team for the whole job

This article is written from the owner’s side of the table. It isn’t legal advice, and a construction lawyer should review any CCDC 30 agreement and its supplementary conditions before you sign.

How integrated project delivery works

Most delivery methods are chains of two-party contracts. IPD replaces them with one.

One contract, several parties

Under an IPD contract the owner, the design consultants and the builder are all parties to the same document, and on larger jobs the mechanical and electrical trades often sign as well. Pallett Valo’s summary of the 2025 CCDC forms describes IPD as a model where owners, consultants, contractors and key trades sign a single multi-party contract and share the risks and rewards, and notes that under CCDC 30 – 2025 all parties are bound from the start, through the validation phase.

The people who will build the project are at the table while it’s being designed, so the mechanical trade can price a duct route before it’s drawn.

The teams

CCDC 30 sets out a project management structure as well as a contract. The CCDC’s description of the 2025 form names three layers: a senior management team, a project management team and project implementation teams.

TeamWho sits on itWhat it does
Senior management team (SMT)A senior person from each party, including the ownerSets direction and settles what the project management team can’t
Project management team (PMT)The day-to-day leads from each partyRuns the project, makes most decisions, develops audit procedures
Project implementation teamsMixed working groups, often by system or areaDesign, price and plan specific parts of the work

The second and third columns are our plain reading. Gowling WLG’s summary of the 2025 form says disputes are worked out at the PMT level first and go to the SMT “only when necessary,” and that members of both teams should be people with the authority to make decisions and bind their organizations (Gowling WLG, July 2025). Your seat on the PMT has to be filled by someone who can say yes on the spot.

On the 2018 edition, BLG noted that the teams had to decide unanimously, with few exceptions, and that the standard terms gave no quick way to break a deadlock (BLG, July 2019). Check how the 2025 edition and your supplementary conditions handle a split decision before you sign.

Target cost and the profit pool

Under CCDC 30 the team is paid its actual costs as they’re incurred, as listed in the contract’s reimbursable costs. Overhead and profit are handled separately.

Two numbers anchor the job:

The team’s profit is set aside in a profit pool, which the 2025 edition renamed from risk pool (Gowling WLG). If the project comes in under target and meets the agreed objectives, the team earns the pool and can share in savings. If costs run over, the overrun comes out of the pool. Every party loses profit together when any part of the job goes badly, so there’s nothing to gain from passing a problem along.

Here’s the part owners need to understand clearly. On the 2018 form, BLG noted that once the risk pool is used up, the parties receive no profit, but “the owner is still responsible for all reimbursable costs” (BLG, 2019). Osler made the same point before the form was published: in IPD the owner generally pays the other parties’ actual costs “irrespective of the outcome” (Osler, November 2018).

So IPD doesn’t move cost risk away from the owner. What it does is give the whole team a shared reason to keep costs down, and a seat at the table early enough to act on it.

Added value incentive items

CCDC 30 – 2025 lets the team identify Added Value Incentive Items (AVIIs): improvements the owner wants that “cannot be funded within the base target cost” (Miller Thomson, September 2025). If the team finds savings elsewhere, you can spend them on these items instead of simply banking them. The 2025 edition lets the owner select AVIIs during construction as well as design (Gowling WLG). Agree the list early, in priority order.

The waiver of claims

In a conventional contract a design error becomes a change, and the change becomes a negotiation about who pays. Under IPD the parties largely waive claims against each other. Gowling describes it as a “no-fault approach” in which team members waive claims against one another when errors occur, so the team can focus on fixing the problem. On the 2018 form, BLG noted the waiver has exceptions, claims the contract specifically lists, and that those can still be subject to a limit on liability. Osler gave examples of the kind of claim usually carved out: intellectual property violations, failure to obtain insurance and wilful default.

The trade-off is fewer routes to recover a loss. A mistake costs the team’s profit through the pool, but you can’t usually pursue the architect or the builder for it as you could under separate contracts. Read the excepted claims closely, and ask your broker how the project’s insurance responds.

The Big Room and lean practices

Gowling WLG notes that CCDC 30 – 2025 mandates lean tools throughout the project, including the Big Room, which Miller Thomson describes as “a dedicated physical venue” where the project team meets regularly to work through issues. Pallett Valo notes it can be physical or virtual. The 2025 edition also lets the parties appoint an optional IPD Advisor, an individual or organization that coaches the team on IPD and lean principles, especially during validation (Gowling WLG).

CCDC 30: the Canadian IPD contract

From 2018 to 2025

The Canadian Construction Documents Committee published CCDC 30 in 2018 as the first Canadian standard form for integrated project delivery. It was reissued on June 30, 2025, in the same release as the construction management forms CCDC 5A and 5B and the trade contract CCDC 17 (BLG, July 2025). If an IPD proposal in front of you is drafted on the 2018 form, ask why.

How the 2025 form is organized

The 2025 edition splits the Articles of Agreement into three segments that follow the project’s life (Gowling WLG):

SegmentCoversWhat comes out of it
A: Validation PhaseCollaborative planning to test whether the project works within your budget and scheduleA Validation Report with the Base Target Cost, a Contract Tasks Matrix, a Milestone Schedule, a risk and contingency analysis and disclosure of profit and cost expectations. Then a decision: proceed or terminate
B: Project ExecutionFinal design, procurement, construction and warrantyThe Final Target Cost, the building, and Ready-for-Takeover
C: General provisionsContract documents, AVIIs, the profit pool, reimbursable costs, overhead, payment, interest, noticesThe rules that apply in both phases

What changed in 2025

The law-firm summaries of the 2025 edition agree on the main changes:

The clauses an owner should read closely

We’d read these parts of any CCDC 30 agreement before signing, along with your lawyer:

  1. Project objectives. The pool pays out against them, so make them specific and measurable.
  2. Validation terms. What the team is paid, what the report must contain, and what you owe if you stop.
  3. Schedule B. Whether each cost is reimbursable or comes out of the team’s overhead.
  4. The profit pool. Its size, when it’s paid, how savings are shared, what happens at termination.
  5. Decisions. How the PMT decides and what happens if the SMT can’t agree.
  6. The waiver. Which claims survive, and the limits on them.
  7. Records and audit. Your right to see the team’s costs.
  8. Holdback and payment under Ontario’s Construction Act (below).
  9. Insurance and security, including any bonds.
  10. Termination, at validation, for default and for convenience.

IPD compared with design-build, CM and stipulated price

For a fuller look at the traditional routes, see our guide to design-build and the traditional tendered route.

Stipulated price (CCDC 2)Design-build (CCDC 14)Construction management (CCDC 5A / 5B)Integrated project delivery (CCDC 30)
ContractsSeparate: you with the architect, you with the contractorOne with the design-builder, who hires the designersSeparate: you with the architect and with the CMOne, signed by you, the designers, the builder and often key trades
When price is setAt tender, on a finished designAt signing, against your Statement of RequirementsPackage by package (5A), or by GMP or stipulated price once design allows (5B)Never fixed in the basic model: a target cost at validation, refined during design
Who pays if it costs moreThe contractor, within the scope it pricedThe design-builder, within the scope it pricedYou under 5A; the CM within any GMP under 5BYou pay actual costs; the team’s profit pool absorbs overruns until it’s gone
Claims between partiesNormal contract claimsNormal contract claimsNormal contract claimsLargely waived, with listed exceptions
Owner’s roleApprove design, administer the contract through the consultantSet requirements, review the designMake decisions through design and trade tenderingA full member of the management teams for the life of the job
Typical useWell-defined buildings with a finished designOwners who want one point of responsibility and a fixed price earlyComplex or fast-track work where builder input during design pays offLarge, complex projects with an owner able to commit senior people

Sources: CCDC’s descriptions of CCDC 2, CCDC 14 – 2026, CCDC 5A, CCDC 5B and CCDC 30 – 2025. The owner’s role and typical use rows are our reading.

IPD vs design-build

Both bring the builder and designer together. The difference is who you’re contracted with and who carries the price. Under design-build you have one contract with one firm, the designers work for it, and it carries the risk that the building costs more than its price. Under IPD you’re a party to the same contract as the designers and the builder, there’s no fixed price, and you share the outcome with them through the profit pool. Design-build gives you price certainty early; IPD gives you a larger say in the design and needs you present for it. More on the fixed-price form in our article on the CCDC 14 design-build contract.

Progressive design-build: the nearest alternative

If what draws you to IPD is the early, collaborative pricing, look at progressive design-build first. You hire a design-builder on qualifications and a fee, develop the design and cost with it through a series of gates, and then agree a fixed price once the design is far enough along. You can stop at a gate, paying for the services and work done to that point. In Canada the form is CCDC 32 – 2026, which works in a project development phase before converting to a stipulated price (Fasken, June 2026). You get much of IPD’s early teamwork with a two-party contract and, eventually, a fixed number. Infrastructure Ontario uses progressive models on large public projects: it confirmed fixed pricing on the Peter Gilgan Mississauga Hospital through a development phase before awarding a $13.9 billion contract in July 2025 (Infrastructure Ontario, July 2025). That’s a progressive P3, not IPD.

Does your project suit IPD?

IPD earns its overhead where the hard problems are coordination problems: many systems in a tight building, an occupied site, design and construction that have to overlap. The CCA’s 2026 delivery methods report lists where it doesn’t suit: owners “unwilling to share decision-making,” teams unfamiliar with collaborative delivery, low-complexity projects that need “a fixed-price commitment at an early stage,” and projects where a validation phase is unlikely to pay off (CCA, June 2026). If you answer no to several of these, a simpler method will probably serve you better.

  1. Is the project complex enough? Hospitals, labs, occupied-building renovations and heavy mechanical and electrical work are the usual candidates. A warehouse shell isn’t.
  2. Is it large enough to carry the process? Validation, the Big Room and the extra management time are real costs that can outweigh the savings on a small job.
  3. Can you live without a fixed price? Your lender, board or investors may need one. IPD gives you a target.
  4. Can you staff the owner’s seats? Someone senior on the SMT, and someone with real authority on the PMT every week.
  5. Can you decide quickly? If decisions go to a committee that meets monthly, the team will wait on you.
  6. Is an experienced IPD team available? A first-time team and a first-time owner should at least budget for an IPD Advisor.
  7. Are your objectives measurable? Otherwise the profit pool has nothing firm to pay out against.
  8. Can you accept the waiver of claims? Your lender and insurer need to accept it too.
  9. Can you review open-book costs? In-house or through an adviser.
  10. Does your procurement allow it? Public and broader public sector owners must check their rules for choosing a team on qualifications. Our guide to construction tendering in Ontario covers those rules.

What IPD asks of the owner

Your time and your decision-makers

Under IPD the owner is a working member of the team from validation to warranty. If your PMT representative has to go back to a board for every decision, the team waits, and you’re paying for its time. Before choosing IPD, decide who your representatives will be, what they can approve alone, and what has to go higher.

The validation phase

During validation the team works together, at your cost, to develop the design concept, the Base Target Cost, the milestone schedule and the risk and contingency analysis, and to disclose its expected costs and profit. At the end you get a Validation Report and decide whether to proceed or end the agreement (Gowling WLG).

Treat the end of validation as a real decision. Have your own cost consultant review the Base Target Cost against an independent estimate, and check that the contingency analysis names real risks rather than a round percentage. Agree in advance what the team is paid if you stop, so the decision isn’t weighed down by sunk cost. Our article on why the first budget matters most explains why that early check pays off.

Funding the costs and the pool

You pay actual reimbursable costs as they’re incurred, and you fund the profit pool. A lender used to a fixed contract price will want to understand the target cost, the contingency and how overruns are handled, so talk to them before you commit. Our guide to construction financing in Ontario covers how lenders look at a construction budget generally.

Open books only help if someone on your side reads them. Use the audit procedures in the Validation Report to set how often you’ll audit and who does it.

Holdback, prompt payment and liens in Ontario

IPD doesn’t take a project outside Ontario’s Construction Act. The 10% holdback still applies (s. 22(1)), a proper invoice still starts the 28-day payment clock (s. 6.4(1)), and since 2026 holdback is released annually on contracts that run past their first anniversary (s. 26(4)). Your liability to lien claimants is still tied to the holdback you were required to keep (s. 23). Our article on construction liens and holdback in Ontario sets out how each of these works.

What’s less settled is how these rules fit IPD’s structure. A single agreement with several parties, each paid its own costs, means several holdback ledgers, several invoice streams and a profit pool paid on a timetable the contract sets. On the 2018 form, BLG noted that lien protection provisions weren’t in the formation documents and would likely need adding through supplementary conditions. Dentons describes the 2025 edition as updated to align with Ontario’s statutory framework, but none of the summaries we read set out how the 2025 form handles holdback on the profit pool or on each party’s costs. Have your lawyer confirm, in writing and in the supplementary conditions:

Who uses IPD in Canada

IPD and its close relative, the alliance contract, have been used mainly by public and institutional owners on large, complex buildings, and adoption is still limited. The Canadian Construction Association’s 2026 report on delivery methods describes alliance and IPD models as suited to “complex, high-risk projects with influential stakeholders” (CCA, Building forward, June 2026).

The clearest recent public example is in British Columbia. In June 2024, for the Burnaby Hospital redevelopment, Fraser Health and the Provincial Health Services Authority moved ahead with PCL Constructors Westcoast and Parkin Architects under what the province called a “single target outturn cost alliance development agreement.” The government’s release describes it as a multi-party contract under which “the owner, builder and designer team up for full project delivery” (Government of B.C., July 2024). It’s an alliance agreement, not CCDC 30, built on the same idea.

In Ontario, Infrastructure Ontario’s Mississauga hospital project, above, used a progressive model with a development phase rather than full IPD. For a private owner building one building, IPD is rarely the first method to consider.

Much of the published writing on IPD, including the AIA’s guide, is American and built around US contract forms. The principles apply here, but the contract, payment rules and lien regime are different in Ontario.

Frequently asked questions

What is the difference between IPD and design-build?

Under design-build you sign one contract with a design-builder, which hires the designers and builds for a price it carries. Under integrated project delivery you, the designers and the builder all sign the same contract, and you pay actual costs against a target rather than a fixed price. Design-build gives early price certainty, while IPD gives you more say and asks for much more of your time.

Is IPD used in Canada?

Yes, though not widely. CCDC 30, the Canadian standard IPD contract, was published in 2018 and updated in 2025, and alliance contracts built on the same idea are in use on public projects such as the Burnaby Hospital redevelopment in British Columbia. Most use so far is on large public and institutional buildings. Private owners more often choose construction management or progressive design-build.

What is a CCDC 30 contract?

CCDC 30 is the Canadian Construction Documents Committee’s standard form for integrated project delivery. The current edition, CCDC 30 – 2025, is a multi-party agreement on a cost plus target price basis, with the team’s profit held in a pool that depends on meeting agreed objectives. It runs through validation, design and procurement, construction and warranty, and sets out the senior and project management teams.

Who carries the risk in IPD?

The risk is shared, but not evenly. The design and construction team puts its profit at risk through the profit pool. The owner pays actual reimbursable costs, and on the 2018 form remained responsible for those costs even after the pool was used up. The parties also largely waive claims against each other. So the owner carries the cost risk, and IPD’s value lies in aligning everyone to keep that cost down.

What to do next

If someone has suggested IPD for your project, start with the suitability questions above and be honest about the owner’s side: your time, your decision-making and your need for a fixed number. If IPD still looks right, budget for a proper validation phase, an independent check of the Base Target Cost and a lawyer who has worked with CCDC 30. If it doesn’t, construction management under CCDC 5A or 5B or progressive design-build will give you much of the early collaboration with a contract structure you’ll find more familiar.

Our experience of delivery models and contracts was built over 20+ years at PCL Constructors and Oxford Properties, across $3B+ of projects in office, residential, retail and industrial. We’ve made the delivery decision on many projects, and we help owners choose the method that fits their building and their organization, test the budget before they commit, and review the contract before they sign, as part of our construction consulting.

Building something? Let’s talk before the numbers are locked in.

Owner’s representation and construction consulting for owners and developers across Canada.

Call 647-932-2902 Start a conversation
hello@myhalconstruction.com
Toronto, Ontario · Serving the GTA and working across Canada